Results of Independent Plant Design Optimisation Study
Released
Released
Announcement PDF
28 January 2020
ASX ANNOUNCEMENT
RESULTS OF THE INDEPENDENT PLANT DESIGN OPTIMISATION STUDY
(20% increase to 600 ktpa)
Highlights
Plant Optimisation Study evaluated a throughput increase to 600 ktpa
Incorporates the 2.5 MW ball mill purchased in October 2019 into a revised plant
design
Flexible plant design to facilitate expansion should the project grow
Capital costs estimated to be within 1% of Theta Project Feasibility Study (including
mill purchase and relocation costs)
Tender documents are ready for plant construction on an Engineering, Procurement,
Construction (EPC)/Lump Sum Turnkey (LSTK) basis
Ball Mill and associated infrastructure have been removed and are ready for transport
to TGME plant site in February 2020
Figure 1: 2.5MW Ball Mill being prepared for removal from structure
Theta Gold Mines Limited (“Theta Gold” or “Company”) (ASX: TGM, TGMO | OTCQB: TGMGF) is
pleased to announce that METS Engineering SA has completed a study into increasing the TGME
Gold Plant throughput from the original 500ktpa capacity in the Feasibility Study (ASX release 16
May 2019) to 600ktpa. The 20% increase in the new plant design is expected to be achieved with
less than a 1% change to the Feasibility Study Process Plant Capex of 24.85 M USD.
The Increased design parameters incorporate the newly purchased (October 2019) 2.5 MW ball
mill and the study was concluded in sufficient detail to allow for the development of a Lump Sum
Turnkey (LSTK) tender document.
More importantly the 20% improvement in capacity (primarily as the result of the procurement
of a 2.5 MW ball mill) is expected to only result in a 1% capital cost increase when compared to
the Theta Project Feasibility Study (See details in Appendix A).
Description
Feasibility
Study
500
353
24.84
14.2
Throughput (ktpa)
Capital Cost (ZAR M)
Capital Cost (USD M)
Exchange Rate (ZAR/USD)
Optimisation
Study
600
362
24.98
14.5
Variance
+ 20 %
+ 2.5%
+ 0.6 %
- 2.1 %
Recent work has also included ongoing optimization of the Theta project and focused on
improving the current throughput constraint of the tailings dam, specifically the annual
deposition rate. This annual deposition rate has now been confirmed at 600ktpa which matches
the increased plant throughput capacity.
The Company has also completed the removal of the 2.5 MW mill and the original equipment
manufacturer has confirmed that it is in good condition with minor repairs expected to be
completed on site during the installation of the mill.
Chairman Mr Bill Guy stated, “The optimization plant design study completed for the Theta
Project is further demonstration of the robust nature of the project. The inclusion of the 2.5 MW
mill and new design work means the plant can be readily expanded in future. The Company has
not lost sight of its medium-term production target of 100 kozpa.
The team is updating the mine schedule to accommodate any potential production increases.
The mill purchase mitigates potential future capital costs risks, but more importantly it is
traditionally one of the longest lead time pieces of equipment.”
This announcement was authorised for release by the Board of Directors.
For more information please visit www.thetagoldmines.com or contact:
Project Enquiries
Rob Thomson, Managing Director
Theta Gold Mines Limited
M: +61 2 8912 2126
robt@thetagoldmines.com
or
General Investor Enquiries
Bill Guy, Chairman
Theta Gold Mines Limited
T: + 61 2 8912 2126
billg@thetagoldmines.com
United States - Michael Porter, Porter, LeVay & Rose Inc: +1 212 564 4700,
theta@plrinvest.com
2
APPENDIX A
Plant Throughput Optimisation Study
Following the release of the Theta Project Feasibility Study, the company continued to investigate
the potential for increased throughput opportunities. The throughput constraint for the project
remains the annual deposition rate and total capacity on the existing permitted tailings dam.
Further work by the tailings engineers (Tailex) has unlocked an additional 100 kt per annum of
deposition rate, now 600 ktpa, however the overall tailings capacity remains unchanged at 2.5
Mt.
The company engaged METS (Part of the UMS Group) who completed the original plant design
and costing as part of the Theta Project Feasibility Study, to complete an optimized design at the
increased throughput.
The results of this study saw the delivery of updated capital and operating cost that has remained
within 1 % of those presented in the Theta Project Feasibility Study. The costs also include the
purchase, removal and relocation costs for the large 2.5 MW mill purchased in October 2019.
Description
Throughput (ktpa)
Capital Cost (ZAR M)
Capital Cost (USD M)
Exchange Rate (ZAR/USD)
Feasibility
Study
500
353
24.84
14.2
Optimisation
Study
600
362
24.98
14.5
Variance
+ 20 %
+ 2.5%
+ 0.6 %
- 2.1 %
Table 1: Comparison table of Feasibility Study 500 ktpa to Optimisation Study 600 ktpa
The brief was to provide an updated detailed capital schedule and plant operating costs as well
as a detailed tender document that the company could use into the market for the delivery of a
Lump Sum Turnkey (LSTK) Price for the construction of the plant.
Figure 21: Theta Project Plant Process Flow Diagram
3
The design caters for potential future expansions up to 1.2 Mtpa throughput of oxide material.
Expansion of the plant would require further studies to confirm project economics at different
production rates. The crushing section allows for simple expansion to 1.2 Mtpa through the
inclusion of a tertiary crusher which can be installed while the plant continues to run and will
then only require a short 48 hours shutdown to tie in. This additional crusher will allow for a
reduction in feed size to the mill which will then allow for the 2.5 MW mill to increase throughput
to 1.2 Mtpa. The design allows for future increases required for pumping, cycloning and gravity
gold recovery. The CIL and cyanide destruction sections will simply be duplicated to allow for the
increased throughput however the elution section, gold room and reagents section are designed
to cater for any future increases in throughput.
Brief Process Design Overview
Run of Mine (ROM) ore will be stockpiled from the mining operation and introduced into the
plant by means of a Front-end Loader (FEL) into a feed bin, which will be used to feed a two stage,
crushing plant, in closed circuit. The crushing section of the plant is designed to treat 201 tph for
18 hours. a day, 7 days per week.
The crushing circuit consists of a primary jaw crusher including a vibrating grizzly feeder (VGF)
and crushing feed bin including a static grizzly on top. The undersize from the VGF will bypass the
crusher, discharging onto a conveyor reporting to a single deck screen. The primary crusher
discharge product, combined with the VGF undersize, reports to the single deck screen. The
screen undersize (-20 mm) proceeds to the mill feed stockpile, with the screen oversize being
sent to the secondary cone crusher with the product recycled back onto the screen feed (in closed
circuit).
The mill feed stockpile has been designed for a 60 hours live capacity providing sufficient buffer
capacity to maintain the required overall utilisation of the process plant. A precast concrete
tunnel beneath the stockpile will house vibrating pan feeders. The stockpile extraction feeders
will control feed onto the mill feed conveyor (via weightometer) and will feed the milling circuit.
The milling circuit will consist of a ball mill, classification cyclone and gravity concentration circuit.
The throughput to the process plant is 85 tph (0.6 MTPA), with the plant designed to operate 24
hours a day at 90% utilisation. The mill discharge will be pumped o the gravity concentration
circuit.
Feed to the gravity circuit will report to a 2 mm guard screen, and the oversized material will be
fed back to the mill feed. The undersized material will then be fed to the Gravity concentrator.
Concentrate from the gravity concentrator proceeds to a shaking table located in the wet section
of the gold room for further gold upgrading.
The shaking table will have a dedicated feed tank with pump and is designed as a batch operation.
The tailings from the shaking table will be pumped back to the mill discharge sump. Gold
accounting of the gravity gold will be separate from the CIL section of the plant.
The tails from the gravity concentrator will report to a sump and then be pumped to the mill
classification cyclone.
The mill cyclone overflow will pass over a trash screen to prevent any organic material entering
the CIL circuit. The underflow of the screen reports to the pre-leach thickener (24 m diameter)
and underflow at 50% solids will be pumped to the CIL conditioning tank. The thickener overflow
will return to the adjacent process water tank to be re-used in the plant.
4
The CIL circuit will have 8 agitated CIL tanks. Lime will be added at the pre-leach thickener and
conditioning tank to control the pH of the slurry at ±10.5.
Between the conditioning tank and the CIL circuit a MACH reactor has been added which
recirculates the plant feed at a ratio of 6 times through a needle tank. The MACH reactor ensures
high attritioning of feed material and improves on leach kinetics and efficiency. Overflow from
the needle tank will flow to CIL tank 1 or 2.
Reagent for gold dissolution is added in tanks 1 and 2 and topped-up, if required, in tank 5 and
6. A residual cyanide concentration of >100ppm in the leach tailings is desired to ensure excess
cyanide in the CIL to ensure a suitable environment for gold leaching to take place..
Regenerated carbon will be added in either tank 7 or 8 and pumped upstream to tank 1. Dissolved
gold is loaded onto the carbon as the carbon moves upstream. A total leach residence time of 24
hours has been allowed for.
Loaded carbon is then pumped from either CIL tank 1 or 2 to the elution circuit where it will be
stripped, and the carbon regenerated for re-use in the CIL circuit. Slurry moves downstream from
tanks 1 to 8 and is pumped by interstage up-pumper screens from one tank to the next.
CIL tailings pass over a carbon catchment screen to recover any gold bearing fine carbon before
the tailings is disposed of. The tailings then undergoes a cyanide detoxification process by
chemical means (INCO Process) before being split 50/50 with 50% of the tailings reporting to a
dewatering plant and the remaining 50% pumped as a slurry to the tailings dam. The dewatering
plant may be deferred for a period of up to 12 months however thereafter 100% of the tailings
will need to be filtered in order to cater for the requirements of the tailings dam construction.
The dewatering plant will treat 50% of the mass flow and this will be pumped into a filter press
system for dewatering in order to produce a filter cake. This filter cake will be used to construct
the outer walls of the TSF.
The elution process will be the ZADRA design, which is a continuous circulation of eluate through
the elution column and electrowinning cells via the heat exchangers and eluate tank. The gold
bearing cathodes will proceed to the calcine and smelting furnace to produce gold doré bars.
5
Figure 3: Optimised Plant Layout Showing CIL Duplication for Possible Expansion
Detailed tender documents for the construction of the mine and plant have also been delivered
that are of sufficient detail to allow for an Engineering, Procurement, Construction (EPC)/Lump
Sum Turnkey (LSTK) basis tender.
As part of the optimization process, the Company and consultants carefully considered the
battery limits for the delivery of the study to ensure that the designs captured any downstream
elements that could affect the design e.g. Plant design battery limit included the use of cyclones
on the dam and design catered for the required operating conditions of the cyclones. In addition,
any area where synergies or skills could be shared were also catered for e.g. the transport of
filtered tailings from the plant to the tailings dam which has been included into the mining
tender.
Ball Mill
Following the completion of a purchase agreement to purchase a 2.5 MW mill (ASX release 2
October 2019: Theta Agrees to Purchase Ball Mill Operated by Glencore), the Company
commenced the process of dismantling and removing the mill from its current location at the
Glencore Smelter site in Rustenburg.
The purchase of this mill is considered by management to be one of the critical pieces of plant
equipment for the proposed new gold processing plant. The purchase mitigates potential future
6
capital costs risks, but more importantly it mitigates construction time risks as this is traditionally
a long lead time piece of equipment.
In October 2019, the Company returned to the site with various engineers to commence with the
planning and detailed costing for the removal of the mill and relocation to TGME and in
November the Original Equipment Manufacturer (OEM), Thyssen Krupps, was engaged to
complete the dismantling and removal of the mill and associated equipment.
On 15 December 2019 the mill was finally removed from the structure and placed in a storage
area on site with the rest of the associated equipment for the mill and in preparation for road
transport in early 2020.
Figure 4: Mill Removal From Structure
Figure 5: Mill and Containers of Associated Equipment Ready for Transport
The transport of the mill and associated equipment from Rustenburg to the TGME Plant in
Pilgrims Rest is expected to occur in February 2020.
7
ABOUT THETA GOLD MINES LIMITED
Theta Gold Mines Limited (ASX: TGM, TGMO | OTCQB: TGMGF) is a gold development company that holds a
range of prospective gold assets in a world-renowned South African gold mining region. These assets include
several surface and near-surface high-grade gold projects which provide cost advantages relative to other gold
producers in the region.
Theta Gold’s core project is located next to the historical gold mining town of Pilgrim’s Rest, in Mpumalanga
Province, some 370km northeast of Johannesburg by road or 95km north of Nelspruit (Capital City of
Mpumalanga Province). Following small scale production from 2011 – 2015, the Company is currently
focussing on the construction of a new gold processing plant within its approved footprint at the TGME plant,
and for the processing of the Theta Open Pit oxide gold ore. Nearby surface and underground mines and
prospects are expected to be further evaluated in the future.
The Company aims to build a solid production platform to over 100kozpa based primarily around shallow, opencut or adit-entry hard rock mining sources. Theta Gold has access to over 43 historical mines and prospect
areas that can be accessed and explored, with over 6.7Moz of historical production recorded.
Theta Gold holds 100% issued capital of its South African subsidiary, Stonewall Mining (Pty) Ltd (“Stonewall”).
Stonewall holds a 74% shareholding in both Transvaal Gold Mining Estates Limited (“TGME”) and Sabie Mines
(Pty) Ltd (“Sabie Mines”). The balance of shareholding is held by Black Economic Empowerment (“BEE”) entities.
The South African Mining Charter requires a minimum of 26% meaningful economic participation by the
historically disadvantaged South Africans (“HDSAs”). The BEE shareholding in TGME and Sabie Mines is
comprised of a combination of local community trusts, an employee trust and a strategic entrepreneurial
partner.
DISCLAIMER
This announcement has been prepared by and issued by Theta Gold Mines Limited to assist in informing
interested parties about the Company and should not be considered as an offer or invitation to subscribe
for or purchase any securities in the Company or as an inducement to make an offer or invitation with
respect to those securities. No agreement to subscribe for securities in the Company will be entered into
on the basis of this announcement.
This announcement may contain forward looking statements. Whilst Theta Gold has no reason to believe
that any such statements and projections are either false, misleading or incorrect, it does not warrant or
guarantee such statements. Nothing contained in this announcement constitutes investment, legal, tax
or other advice. This overview of Theta Gold does not purport to be all inclusive or to contain all
information which its recipients may require in order to make an informed assessment of the Company’s
prospects. Before making an investment decision, you should consult your professional adviser, and
perform your own analysis prior to making any investment decision. To the maximum extent permitted by
law, the Company makes no representation and gives no assurance, guarantee or warranty, express or
implied, as to, and take no responsibility and assume no liability for, the authenticity, validity, accuracy,
suitability or completeness of, or any errors in or omissions, from any information, statement or opinion
8
contained in this announcement. This announcement contains information, ideas and analysis which are
proprietary to Theta Gold.
FORWARD LOOKING AND CAUTIONARY STATEMENTS
This announcement may refer to the intention of Theta Gold regarding estimates or future events which
could be considered forward looking statements. Forward looking statements are typically preceded by
words such as “Forecast”, “Planned”, “Expected”, “Intends”, “Potential”, “Conceptual”, “Believes”,
“Anticipates”, “Predicted”, “Estimated” or similar expressions. Forward looking statements, opinions and
estimates included in this announcement are based on assumptions and contingencies which are subject
to change without notice, and may be influenced by such factors as funding availability, market-related
forces (commodity prices, exchange rates, stock market indices and the like) and political or economic
events (including government or community issues, global or systemic events). Forward looking
statements are provided as a general reflection of the intention of the Company as at the date of release
of the document, however are subject to change without notice, and at any time. Future events are subject
to risks and uncertainties, and as such results, performance and achievements may in fact differ from
those referred to in this announcement. Mining, by its nature, and related activities including mineral
exploration, are subject to a large number of variables and risks, many of which cannot be adequately
addressed, or be expected to be assessed, in this document. Work contained within or referenced in this
report may contain incorrect statements, errors, miscalculations, omissions and other mistakes. For this
reason, any conclusions, inferences, judgments, opinions, recommendations or other interpretations
either contained in this announcement, or referencing this announcement, cannot be relied upon. There
can be no assurance that future results or events will be consistent with any such opinions, forecasts or
estimates. The Company believes it has a reasonable basis for making the forward looking statements
contained in this document, with respect to any production targets, resource statements or financial
estimates, however further work to define Mineral Resources or Reserves, technical studies including
feasibilities, and related investigations are required prior to commencement of mining. No liability is
accepted for any loss, cost or damage suffered or incurred by the reliance on the sufficiency or
completeness of the information, opinions or beliefs contained in this announcement.
The Feasibility Study referred to in this announcement is based on technical and economic assessments
to support the estimation of Ore Reserves. There is no assurance that the intended development referred
to will proceed as described, and will rely on access to future funding to implement. Theta Gold believes
it has reasonable grounds the results of the Feasibility Study. At this stage there is no guarantee that
funding will be available, and investors are to be aware of any potential dilution of existing issued capital.
The production targets and forward looking statements referred to are based on information available to
the Company at the time of release, and should not be solely relied upon by investors when making
investment decisions. Theta Gold cautions that mining and exploration are high risk, and subject to change
based on new information or interpretation, commodity prices or foreign exchange rates. Actual results
may differ materially from the results or production targets contained in this release. Further evaluation
is required prior to a decision to conduct mining being made. The estimated Mineral Resources quoted in
this release have been prepared by Competent Persons as required under the JORC Code (2012). Material
assumptions and other important information are contained in this release.