Permitting Update - TGME Underground Gold Project
Released
Released
Announcement PDF
18 July 2022
ASX ANNOUNCEMENT
(ASX:TGM)
PERMITTING UPDATE
TGME UNDERGROUND GOLD PROJECT
HIGHLIGHTS:
•
•
•
•
•
•
The Final Environmental Impact Assessment Report and Environmental Management
Programme (EIA/EMPr) have been submitted to the Department of Mineral Resources
and Energy (DMRE) and the final technical documents for the integrated water use
license application to the Department of Water and Sanitation (DWS) for final
decision.
The findings from the EIA/EMPr and specialist studies have not identified any fatal
flaw.
The outcome of the decisions from the DMRE and DWS on the applications for MR 83
are expected in Q4 of 2022, followed by a 90-day review period.
An application for an Atmospheric Emissions License was submitted to the
Department of Forestry, Fisheries, and the Environment. The application is currently
available for public comments for a 30-day period that will end on 10 August 2022. A
final decision on the application is expected by the end of Q3 of 2022.
The Frankfort Mine Water Use License application registered with the Department of
Water and Sanitation (‘DWS’) – final decision expected in Q3 of 2022.
A positive decision from DWS will mean Frankfort Mine is fully permitted.
Theta Gold Mines Limited (“Theta Gold” or the “Company”) (ASX: TGM| OTC: TGMGF) is pleased to
advise that the final Environmental Impact Assessment Report and Environmental Management
Programme (EIA/EMPr) have been submitted to the Department of Mineral Resources and Energy
(DMRE) and the final technical documents for the integrated water use license application to the
Department of Water and Sanitation (DWS) for final decision.
The outcome of the decisions from the DMRE and DWS on the applications are expected in Q4 of 2022
with an additional 90-day review and objection period. A positive decision from the Competent
Authorities will enable the Company to commence with its MR83 underground project.
1
Over 20 studies have been completed as part of the EIA process (see Appendix 1 below for a list of
studies). The findings from the EIA/EMPr and specialist studies have not identified any fatal flaw,
unaddressed objection, or significantly high impact ratings.
The requisite mitigation measures are all imminently feasible and this should give all interested and
affected parties the confidence that the impacts of our proposed activities will not threaten the
environment.
A comprehensive stakeholder engagement process was undertaken before the submission of the
applications. A very successful open day was held in Pilgrims Rest on 28 May 2022. Feedback from the
open day was very positive and the community is very excited about the job opportunities and
economic upliftment that will be created by the project. With the good turnout at the open day and
various other stakeholder meetings it can be concluded that the procedural requirement to consult
during the EIA phase is satisfied. (Refer to Appendix 2 photo records of stakeholder engagement).
An application for an Atmospheric Emissions License was also submitted to the Department of
Forestry, Fisheries and the Environment during June 2022. The application is currently available for
public comments for a 30-day period that will end on 10 August 2022. A final decision on the
application is expected by the end of Q3 of 2022. This license will allow the operation of the processing
plant. (Appendix 4 contains an advertisement placed to notify stakeholders of the application).
Chairman Mr. Bill Guy commented: “We are now entering the final phase of the EA permitting process,
with strong community support. All workstreams have been completed and final documentation
delivered to DMRE so that a decision about the resumption of mining on MR83 can be made.”
“Theta has received many letters of support from Interested and affected parties (Ehlanzeni District
Municipality, Mpumalanga Department of Co-operative Governance and Traditional Affairs and Local
Ward Councilors). The local community and landowners have a direct project interest under the BEE
structure.”
“We also confirm that a decision from the DFFE about continued mining under Forrest Reserve is
expected in Q3 of 2022 (see ASX: release 25 October 2021 “TGME PROJECT PERMITTING UPDATE”
Affecting the Beta and CDM mines). The company offered to include the ecological compensation into
our growing ESG program, which will positively affect the local catchment area for years to come. Our
decision to cornerstone this investment and work with stakeholders and the DFFE is set to benefit future
generations in the region”.
2
Appendix 1: Specialist Studies Completed
Table 1 indicates the list of specialist studies conducted to date as part of the environmental
application process.
Specialist Studies
Air Quality impact assessment and Greenhouse Gas Assessment
Environmental Specialists
Status
Airshed Planning Professionals (Pty) Ltd
✓
Biodiversity impact assessment
SAS Environmental Group of Companies
✓
Blasting and Vibration study
Blast Management and Consulting
✓
Ecological Compensation Plan
Conservation Strategy, Tactics, and Insight
✓
Mine Closure and rehabilitation plan
OMI Solutions
✓
Freshwater and aquatic ecology impact assessment
SAS Environmental Group of Companies
✓
Geohydrological impact assessment
MvB Consulting
✓
Dolomite Stability assessment
Jones & Wagener
✓
Heritage and Paleontological impact assessment
Heritage Management Consulting
✓
Noise impact assessment
EnviroRoots (Pty) Ltd
✓
Socio-economic impact assessment
Kongiwe Environmental
✓
Soil and land use capability
SAS Environmental Group of Companies
Stormwater management plans/ Civil engineering designs
Eco Elementum Environmental and Engineering
Traffic impact assessment
Infratrans Pty (Ltd)
Visual impact assessment
SAS Environmental Group of Companies
Waste classification
GeoDyn Systems
Tailings Storage Facility Waste Risk Assessment
HydroScience
Rietfontein Prefeasibility Study: Freshwater and aquatic ecology
impact assessment
SAS Environmental Group of Companies
Rietfontein Prefeasibility Study: Soil and Land Use Capability
Assessment
SAS Environmental Group of Companies
Rietfontein Prefeasibility Study: Visual Impact Assessment
SAS Environmental Group of Companies
✓
✓
✓
✓
✓
✓
✓
✓
✓
3
Table 2 indicates the progress made in the current environmental approval process.
Task
Duration
Submit application for EA
29 November 2021
Obtain Reference number from DMRE for EA application
15 February 2022
Status
✓
✓
(acknowledgement letter)
Submit draft scoping report to the public for review
06 December 2021
✓
Public Review Period – draft scoping report
07 December 2021 – 26 January 2022
✓
Public Participation Meetings for Scoping Phase
12 January 2022 – 15 January 2022
✓
Open day meeting
15 January 2022
✓
Submission of final scoping report to the DMRE
03 February 2022
✓
Submit pre-application enquiry for WUL application
21 February 2022
✓
Specialists EIA Studies Completed
31 March 2022
✓
Pre-application meeting with DWS
11 April 2022
✓
DMRE acceptance of final scoping report
12 April 2022
✓
Draft EIA/EMPr and the Draft IWWMP submitted for public review
24 April 2022
✓
Submission of Final EIA/EMPr and technical documents for the
13 July 2022
✓
integrated water use licence application
4
Appendix 2 Photo Record of Stakeholder Engagements
Figure 1: Stakeholder meeting with SAFCOL
representatives
Figure 2: Stakeholder meeting with
representatives of the Sabie Business Chamber
Figure 3: Stakeholder meeting with Ward
Councillors
Figure 4: Stakeholder meeting with Ward
Councillors
Figure 5: Open day meeting
Figure 6: Open day meeting
5
Figure 7: Open day meeting
Figure 8: Open day meeting
Figure 9: Open day meeting
Figure 10: DWS Site inspection
meeting
Figure 11: DWS Site inspection meeting
Figure 12: Site inspection meeting
6
Figure 13: Site inspection meeting
Figure 14: Site inspection meeting
Figure 15: Site inspection meeting
Figure 16: Site inspection meeting
7
Appendix 3 Photo Record of Submission of Final EIA/EMPR to the DMRE
Figure 17: Submission of Final EIA/EMPR to
Figure 18: Final EIA/EMPR documents
the DMRE
Appendix 4 Notice of the Application of the Atmospheric Emissions Licence Application as
advertised in the newspapers
Figure 19: Advertisement for Atmospheric Emissions Licence in Lowvelder and Steelburger.
[ENDS]
8
This announcement was approved for release by Theta Gold Mines Limited’s Board.
For more information, please visit www.thetagoldmines.com or contact:
Bill Guy, Chairman
Theta Gold Mines Limited
T: + 61 2 8046 7584 E: billg@thetagoldmines.com
Investor Relations
Australia: Ben Jarvis, Six Degrees Investor Relations: +61 (0) 413 150 448
Webpage: www.thetagoldmines.com
https://twitter.com/ThetaGoldMines
https://www.linkedin.com/company/thetagoldmines/
ABOUT THETA GOLD MINES LIMITED
Theta Gold Mines Limited (ASX: TGM | OTCQB: TGMGF) is a gold development company that holds a range
of prospective gold assets in a world-renowned South African gold mining region. These assets include
several surface and near-surface high-grade gold projects which provide cost advantages relative to other
gold producers in the region.
Theta Gold’s core project is located next to the historical gold mining town of Pilgrim’s Rest, in Mpumalanga
Province, some 370km northeast of Johannesburg by road or 95km north of Nelspruit (Capital City of
Mpumalanga Province). Following small scale production from 2011 – 2015, the Company is currently
focussing on the construction of a new gold processing plant within its approved footprint at the TGME
plant, and for the processing of the Theta Open Pit oxide gold ore. Nearby surface and underground mines
and prospects are expected to be further evaluated in the future.
The Company aims to build a solid production platform to over 160kozpa based primarily around shallow,
open-pit or adit-entry shallow underground hard rock mining sources. Theta Gold has access to over 43
historical mines and prospect areas that can be accessed and explored, with over 6.7Moz of historical
production recorded.
Theta Gold holds 100% issued capital of its South African subsidiary, Theta Gold SA (Pty) Ltd (“TGSA”). TGSA
holds a 74% shareholding in both Transvaal Gold Mining Estates Limited (“TGME”) and Sabie Mines (Pty)
Ltd (“Sabie Mines”). The balance of shareholding is held by Black Economic Empowerment (“BEE”) entities.
The South African Mining Charter requires a minimum of 26% meaningful economic participation by the
historically disadvantaged South Africans (“HDSAs”). The BEE shareholding in TGME and Sabie Mines is
comprised of a combination of local community trusts, an employee trust and a strategic entrepreneurial
partner.
9
DISCLAIMER
This announcement has been prepared by and issued by Theta Gold Mines Limited to assist in
informing interested parties about the Company and should not be considered as an offer or
invitation to subscribe for or purchase any securities in the Company or as an inducement to make
an offer or invitation with respect to those securities. No agreement to subscribe for securities in the
Company will be entered into on the basis of this announcement.
This announcement may contain forward looking statements. Whilst Theta Gold has no reason to
believe that any such statements and projections are either false, misleading or incorrect, it does not
warrant or guarantee such statements. Nothing contained in this announcement constitutes
investment, legal, tax or other advice. This overview of Theta Gold does not purport to be all
inclusive or to contain all information which its recipients may require in order to make an informed
assessment of the Company’s prospects. Before making an investment decision, you should consult
your professional adviser, and perform your own analysis prior to making any investment decision.
To the maximum extent permitted by law, the Company makes no representation and gives no
assurance, guarantee or warranty, express or implied, as to, and take no responsibility and assume
no liability for, the authenticity, validity, accuracy, suitability or completeness of, or any errors in or
omissions, from any information, statement or opinion contained in this announcement. This