Quarterly Activities & Cashflow Reports - 30 June 2022
Released
Released
Announcement PDF
1 August 2022
ASX ANNOUNCEMENT
(ASX:TGM)
QUARTERLY REPORT
1 April 2022 to 30 June 2022
Theta Gold Mines Limited (“Theta Gold” or “Company”) (ASX: TGM | OTC: TGMGF) is pleased to
report on its activities for the period from 1 April 2022 to 30 June 2022.
HIGHLIGHTS
DURING THE JUNE 2022 QUARTER:
•
At the end of June 2022, the TGME Underground Definitive Feasibility Study (DFS) was
close to completion undergoing final internal and external reviews and approvals and
was subsequently released on 27 July 20221, after quarter end.
Key features of Feasibility Study (FS) include:
TGME Feasibility Study delivers 1.24Moz contained gold, underpinning an initial 12.9year mine life.
Strong financial return (based on LOM Plan), including (at a gold price of A$2,189/oz,
with first production targeted for 20242, including:
o Undiscounted free cash flows of US$508m, (A$678m), pre-tax US$717, (A$956m);
o NPV (at a 10% discount rate) of US$219m, (A$292m), pre-tax US$324m, (A$432m);
o Capital payback period of 31 months;
o Pre-tax IRR of 65%;
o Combined Underground Projects have an AISC of US$834/oz, (A$1,112/oz); and
o Peak Capital requirement is US$77m, (A$103m), total capital requirements
US$174m, (A$232m).
•
Front-End Engineering Design (FEED) of the TGME gold plant was completed, forming
an important input towards the finalisation of the Definitive Feasibility Study (DFS) of
the TGME underground project3.
1
Refer to ASX release dated 27 July 2022 titled “Theta’s TGME Project FS confirms NPV 10% of A$432 Million at
US$1,642 / Oz Gold Price”.
2
First gold production will be subject to securing financing and permitting approvals.
3
Refer to ASX release dated 20 June 2022 titled “TGME Gold Project Update”
Theta Gold Mines Limited ABN 30 131 758 177
Suite 80, Level 35 (Servcorp), International Tower One, 100 Barangaroo Avenue, Sydney NSW 2000
Tel: +61 2 8046 7584 Email: info@thetagoldmines.com
www.thetagoldmines.com
•
The Final Environmental Impact Assessment Report and Environmental Management
Programme (EIA/EMPr) were submitted to the Department of Mineral Resources and
Energy (DMRE) and the final technical documents for the integrated water use license
application to the Department of Water and Sanitation (DWS) for final decision.
•
The outcome of the decisions from the DMRE and DWS on the applications for MR 83
are expected in Q4 of 2022, followed by a 90-day review period.
•
An application for an Atmospheric Emissions License was submitted to the Department
of Forestry, Fisheries, and the Environment. The application is currently available for
public comments for a 30-day period that will end on 10 August 2022. A final decision
on the application is expected by the end of Q3 of 2022.
•
The Frankfort Mine Water Use License application registered with the Department of
Water and Sanitation (‘DWS’) – final decision expected in Q3 of 2022.
•
A positive decision from DWS will mean Frankfort Mine is fully permitted.
•
TGM completed a capital raise of A$1.4 million (before costs) through a private
placement, from a majority of existing institutional, professional and sophisticated
investors during the June 2022 quarter.
•
The Company entered into an agreement to extend the maturity date for the
outstanding A$6 million Secured Bond Facility (Secured Bond) it currently holds with
2Invest AG and its associates for a further 12 months.
POST JUNE 2022 QUARTER UPDATE:
•
TGME Underground Feasibility Study (FS) released underpinning a 12.9-year mine life
with a NPV(10%) of A$432m (pre-tax).4
•
TGM remains in advanced discussions with Financial Institutions to complete a capital
raising through the issue of New Shares . Final terms of the issue are expected to be
announced shortly.
Theta Chairman Mr Bill Guy stated: “The definative feasibility study (DFS) was completed and released at
the end of July 2022 and marks a trumendous achievement for the Company. The Company has been able
to demonstrate that it has a project that can deliver low-cost, sustainable mining from a 12.9-years of mine
life from the first 4 mines of the TGME Underground Gold Project. The first phase which includes Beta,
Rietfontein, CDM and Frankfurt mines, gives us access of up to 1.24Moz’s of contained gold creating robust
returns to investors along with prosperity and economic benefits to the surrounding regions of the mine”
OPERATIONS AND DEVELOPMENT UPDATE SUMMARY
Feasibility Study for the TGME Underground Gold Mine Project
The Feasiblity Study (‘FS’) for the TGME Underground Gold Mine Project was delivered on 27 July
2022, confirming Theta Gold’s potential to be a significant near-term, high-margin gold
production project, with opportunities for future growth. Based on the FS results, the Project will
4
NPV of A$432m (pre-tax), under the Base Case results released to the ASX on 27 July 2022.
2
provide robust, financial returns from a long-life, large underground mining operation, for a
modest capital investment given the scale of operations envisaged.
The TGME Project LOM will initially comprise a 12.9-year mining operation starting in Q1, 20235
and delivering Life-of-Mine (LOM) production of 1.24Moz’s of contained gold. The estimated
peak development capital (“CAPEX”) is A$103 million, with the Project forecast to generate a pretax NPV10% of A$432 million and pre-tax internal Rate of Return (IRR) of 65% at a forecast average
gold price of A$2,189 / oz. Based on these metrics, the Project has a projected capital payback
period of 31 months.
The FS paves the way for a Final Investment Decision (‘FID’) by the Theta Gold Board in respect
to debt funding negotiations and on-going discussions with Financiers to respect to full debt or
partial debt and equity funding options. Theta Gold has appointed debt funding advisors to assist
it through this important process and will provide updates in due course.
Table 1: Key Project Metrics
Description
Units
Base Case
Reserve Plan
Project Start Date
Qtr/Year-yyyy
Q1 2023
Q1 2023
Commercial Production Start Date
Qtr/Year-yyyy
Q2 2024
Q2 2024
Production build up period
Months
14
14
Life of mine
years
12.9
7.3
Underground ore mined (LOM)
Mt
6.46
2.85
Mined Grade
g/t
5.95
6.09
Gold Mined (LOM)
Moz
1.24
0.56
Production Rate
Kt/a
540
540
Production Rate
Kt/m
45
45
Grind size
µ
106
106
Gold recovered (average LOM)
%
87
87
Gold recovered (LOM)
Moz
1.08
0.49
Project economics below shows the sensivities to the various gold price estimates and
demonstrates the robust financial returns of the Project.
5
Start time will be dependent on securing necessary funding and permitting approvals.
3
Table 2: Project Economics at Various Gold Prices – Base Case (AUD)
Project Economics at
gold price
NPV @ 10% (real) Pre-tax
NPV @ 10% (real) Posttax
IRR (%) Pre-tax
IRR (%) Post-tax
AISC
EBITDA annual average
EBIT annual average
Free Cash Flow (Pre-tax)
Free Cash Flow (Post-tax)
Development Capital –
Peak Funding
Capital Sustaining
Payback post-tax
Capital Efficiency (Pre-Tax
NPV/Dev Capital
Capital Efficiency (PostTax NPV/Dev Capital
NOTES:
1.
2.
Unit
AUDm
Forecast
USD1,500/ USD1,600/ USD1,800/ USD2,000/ USD2,200/
(USD1,642/
oz
oz
oz
oz
oz
oz Avg)
432
339
405
536
669
802
AUDm
292
232
274
359
447
533
%
%
AUD/oz
AUDm
AUDm
AUDm
AUDm
65%
57%
1,112
92
80
956
678
57%
50%
1,096
77
66
768
550
64%
56%
1,107
87
76
897
638
77%
67%
1,129
107
96
1,158
814
90%
78%
1,149
128
116
1,421
996
102%
87%
1,167
148
136
1,686
1,175
AUDm
102
102
102
102
102
102
AUDm
Months
49
31
49
33
49
31
49
28
49
25
49
24
%
422%
332%
395%
524%
653%
783%
%
285%
226%
268%
351%
437%
521%
Converted to AUD from USD using AUD:USD exchange rate of 1.333.
Due to rounding, numbers presented throughout this document may not add up precisely to the totals, provided and percentages
may not precisely reflect the absolute figures.
Figure 1: Annual Gold Production – Base Case
4
Figure 2: Annual and Cumulative Cash Flow (Post-Tax) – Base Case (AUD)
NOTES:1. Forecast Prices averaging USD1,642/oz over LOM.
2. Converted to AUD from USD at exchange rate of 1.333 AUD:USD.
The TGM Underground Project aims to restart historical underground gold mines located in a
historically prolific gold mining region in the Mpumalanga Province of South Africa. The Project
Areas are centred on the town of Pilgrims Rest, some 370 km due northeast of Johannesburg,
and ownership has always been vested in TGM or its partners.
The Project targets the Beta (including the Beta North, Beta Central and Beta South sections),
Rietfontein, Frankfort and Clewer-Dukes Hill-Morgenzon (“CDM”) Mines. A significant amount of
gold resources remain underground which were not mined historically due to technological
limitations, or limiting ore characteristics.
Beta is scheduled as the first operation to commence production, followed by Rietfontein, and
finally CDM and Frankfort simultaneously. In comparison to CDM and Frankfort, Beta and
Rietfontein are higher-grade mines.
A metallurgical plant, which acts as the central processing plant for all the historical operations,
is situated in close proximity with a maximum distance to operations of ~40km. A new facility will
be established on this footprint and will treat all the ore from the underground operations.
Two scheduling strategies have been investigated in the FS. The Base Case considers a life of mine
(“LOM”) plan targeting the total Mineral Resources (Measured, Indicated and Inferred). The Ore
Reserve Plan considers a LOM plan targeting only Measured and Indicated Mineral Resources.
This FS demonstrates the ability to achieve optimised cash flows by scheduling production from
the operations. The mine designs and associated costs per operational element feed into a
combined operations financial model. The Ore Reserve Plan supports the declaration of
compliant JORC Code 2012 Ore Reserves.
5
TGME Underground Gold Mine Development
As part of the preparation for the installation of the first phase new gold plant, TGME had
appointed the services of Jet Demolition to remove the redundant plant equipment. The process
started in the 2nd week of January 2022. Specialised equipment is utilised for demolition, after
which it is reduced in size and made ready for transport to scrap merchants. The project to
remove the old plant is now complete6.
Met63 was contracted to do a detailed design and costing of a processing plant designed for a
feed capacity of 45 ktpm which is equivalent to 67 tph at 92% availability. A flow schematic is
shown in Figure 3.
Figure 3: Process Flow Schematic Phase 1
The feasibility study has been split into three phases, allowing for various processing scenarios
aligned with the mining development program. The design of each phase is based on a standalone processing facility aligned with the mining plan of the ore body.
•
Phase 1 – Carbon-in-Leach Plant (Free milling ore is process for the first 7 Years figure
23).
The design and costing of a 45 ktpm oxide ore processing plant including crushing,
milling, CIL and elution with doré produced on site. Testwork undertaken on various
"free-milling" ores has indicated high undissolved gold losses, indicating the presence of
small amounts of sulphidic constituents.
This was particularly evident when completing standard cyanidation bottle roll trials on
Dukes and Morgenzon samples. Subsequent additional testwork supports this. As a
result, the Phase 1 circuit will include a flash flotation stage, post milling to remove
6
Ref to ASX release dated 4 March 2022 titled “DFS Update and High-Grade Ore Sweeped from New Historical
Mines”.
6
sulphide associated material before conventional cyanidation. This flotation mass pull
will join the concentrator product from Phase 2.
•
Phase 2 – Gold Concentrator Plant
The design and cost of a 20 ktpm concentrating plant including crushing, milling, DMS
and flotation. The final products consist of a combined carbon and sulphide flotation
concentrate. The carbon flotation concentrate being processed through the CIL 3 plant
and the sulphide flotation concentrate is processed through the CIL 1 plant.
•
Phase 3 – Oxidative Leaching of Sulphide Concentrate
The Phase 3 plant includes a 45 ktpm Leach-ox process plant that was designed and
costed, including crushing, milling and carbon/sulphide flotation. The phase 3 plant
consists of both the gold concentrator plant as well as the CIL plant as described in
Phase 1 and Phase 2. The carbon flotation concentrate processed in a dedicated CIL
circuit (CIL 3), sulphide flotation concentrate oxidised under atmospheric conditions
with liquid oxygen injection and high shear reactors. Oxidised product to be treated in a
separate batch CIL process (CIL 1) with the tails treated in a large CIL (CIL 2), that also
processes the flotation tails as well as "free-milling" ore feed. This option allows for all
recovered gold to be produced as doré on-site with no concentrate produced.
Although there are some shared infrastructure and processing equipment between the phases,
for the purposes of this FS the phase One plant will be constructed first to treat CDM, Rietfontein
and Beta ore with phase three being constructed at a later stage before mining of Frankfort ore
commences.
The plant will be developed by an Engineering, Procurement and Construction (EPC) contractor.
The Company will run a tender process to evaluate contracts for the construction and upgrade
of existing infrastructure including detailed engineering for the plant, procurement, fabrication
and delivery to site of plant, equipment and materials and construction of the process plant
facilities.
Project Finance
Theta Gold has engaged with debt funding advisors to assist in negotiations for the required
Capital requirements of the A$103 million peak capital. The Company is expected to complete
negotiations with debt financing in the coming months.
Project Permits and Approvals
The Company announced in July 20227 that the final Environmental Impact Assessment Report
and Environmental Management Programme (EIA/EMPr) have been submitted to the
Department of Mineral Resources and Energy (DMRE) and the final technical documents for the
7
Ref to ASX release dated 18 July 2022 titled “Permitting Update TGME Underground Gold Mine”
7
integrated water use license application to the Department of Water and Sanitation (DWS) for
final decision.
The outcome of the decisions from the DMRE and DWS on the applications are expected in Q4
of 2022 with an additional 90-day review and objection period. A positive decision from the
Competent Authorities will enable the Company to commence with its MR83 underground
project.
Over 20 studies have been completed as part of the Environmental Impact Assessment (EIA)
process. The findings from the EIA/EMPr and specialist studies have not identified any fatal flaw,
unaddressed objection, or significantly high impact ratings. The requisite mitigation measures
are all imminently feasible and this should give all interested and affected parties the confidence
that the impacts of our proposed activities will not threaten the environment.
A comprehensive stakeholder engagement process was undertaken before the submission of the
applications. A very successful open day was held in Pilgrims Rest on 28 May 2022. Feedback
from the open day was very positive and the community is very excited about the job
opportunities and economic upliftment that will be created by the project. With the good turnout
at the open day and various other stakeholder meetings it can be concluded that the procedural
requirement to consult during the EIA phase is satisfied.
An application for an Atmospheric Emissions License was also submitted to the Department of
Forestry, Fisheries and the Environment during June 2022. The application is currently available
for public comments for a 30-day period that will end on 10 August 2022. A final decision on the
application is expected by the end of Q3 of 2022. This license will allow the operation of the
processing plant.
It has been advised that the Department of Forestry, Fisheries and the Environment (“DFFE”) is
currently conducting interdepartmental consultations on the Company’s request for Ministerial
conditions for continued mining in certain sections of Morgenzon Forest Nature Reserve (“FNR”)
that was declared in October 2021.
The Company is confident that it can successfully implement its mining operations to better
protect the strategic water source and biodiversity area. It is of great concern to the local
community and downstream farmers that environmental degradation is accelerating in this
catchment area. A positive resonse on the request to the Minister will therefore be welcomed by
stakeholders in the light of current challenges in the catchment, the manageable environmental
impacts from the proposed MR83 underground project, and the significant value offering of the
proposed Ecological Compansation Programme to support DFFE’s wider environmental, social
and governance (“ESG”) objectives in the region.
Gold Plant Front-End Engineering Design (Feed) Complete
Front-End Engineering Design (FEED) of the TGME gold plant has been completed, forming an
important input towards the finalisation of the Feasibility Study (FS) of the TGME underground
project.
Theta Gold provide an update on the MR 83 gold processing plant advising that it had appointed
MET63, which specialises in the design and construction of advanced modular processing plants,
8
to undertake and complete the plant design, based on a thorough metallurgical testwork
program, and with multi-tier internal and independent oversight.
Key Features of the Gold Process Plant:
•
•
•
•
•
•
•
•
•
The new gold process plant is designed to have a milling capacity of 540,000 tons per
annum. The plant design consists of two individual processing streams, capable of
processing free-milling and sulphide ore separately.
The new gold processing plant is designed to fit into the current plant footprint which
forms part of the Mining Right MR83, therefore no additional environmental permitting
will be required.
The new processing plant components include three-stage crushing, milling, reagent,
flotation, CIL, elution, and gold room sections as indicated in figure 4 & 5.
The gold plant will produce dore gold bars.
Engineering and costing have been completed to the required level of accuracy for the
DFS.
The completed design includes water and power reticulation with the scope to increase
the capacity with modular units for future plant expansions, consistent with the
Company’s strategy to reach its gold production target of 160koz/a within five years.
The latest proven available automation technologies were incorporated into the gold
processing plant design which will reduce labour requirements and enhance productivity
levels.
The tailings disposal will be onto the existing tailings storage facility located some 150m
from the plant.
Some existing plant infrastructures were incorporated into the new gold processing plant.
A 3D rendering of the processing plant is illustrated in Figure 4
9
Figure 4: 3D Plant Rendering Final design Phase 1-3.
Figure 5: New TGME Plant Layout
10
Figure 6: Existing Plant Drone View (post demolition of old sections)
Changes to the Senior Management Team
The Company advised recently that it will be making changes to the management and corporate
structure as it prepares to bring the TGME Underground Gold Project into development,
construction and production. The Company also announced that its in-country CEO was no long
with the Company and that role will be restructured in coming months.
This may include further changes to its Senior Management team and additions as well as
changes to its board make-up. Theta Gold recognises that its important to have member with the
necessary experience and expertise to bring this trumentous project on-line in the most efficient
and effective manner.
CORPORATE UPDATE SUMMARY
Completion of Capital Riase via a Private Placement
On 4 May 20228, TGM announced it had completed a capital raise of $1.4 million (before costs)
through a private placement from a majority of existing institutional, professional and
sophisticated investors.
The Company issued 12,350,000 new TGM Ordinary Shares at the issue price of A$0.129 cents
per share, using the Company’s existing placement capacity pursuant to Listing Rule 7.1.
8
Ref to ASX Release dated 4 May 2022 titled “Funds Raised to Support TGME Underground Gold Mine Project”
Shares issue price of $0.12 cents has been calculated on the 10 day VWAP just prior to completion of the capital
raising.
9
11
Use of funds raised from the share placement as follows:
a) Project expenditure including permitting, underground trial mining and completion
Definitive Feasibility Study (‘DFS’);
b) Progress towards Environmental Impact Assessment (‘EIA’) and Environmental
Management Program (‘EMPr’); and
c) General working capital and corporate overheads.
Option to Extend Secured Bond Facility for a further 12 months
On the 13 May 202210, the Company announced it has entered into an agreement to extend the
maturity date for the outstanding A$6 million Secured Bond Facility (Secured Bond)11 it currently
holds with 2Invest AG and its associates for a further 12 months, if required.
The maturity date and repayment of the A$6 million Secured Bond is currently 23 January 2023
which may be extended for a further 12 months to 23 January 2024, at the discretion of the
Board.
All other existing terms and conditions of the Secured Bond remain unchanged.
As part of the agreement, the Company issued 15 million12 unlisted Series C Options to 2Invest
AG with an exercise price of $0.17 and expiry date on or before the 16 January 2024. Unlisted
options will be issued pursuant to the Company’s existing capacity under Listing Rule 7.1.
Cash Position and Funding
As at 30 June 2022, the Group had US$21,000 in cash.
TGM is currently finalising the terms of a capital raising with the issues of New Shares to
professional and sophisticated investors including existing shareholders. The funding transaction
is expected to be completed shortly with final terms and pricing to be announced to the market.
As announced on 25 March 2021, the Company entered into an At-The-Market Subscription Deed
(“ATM”) with Acuity Capital. The ATM provides the Company with up to AU$15 million of standby
equity capital with the expiry of the ATM being 31 July 2023. There are no requirements on the
Company to utilise the ATM and the Company may terminate the ATM at any time, without cost
or penalty. As security for the ATM, the Company has issued 24 million Theta Gold shares to be
held by Acuity Capital. As of the date of this report, this position remains unchanged.
10
Refer to ASX Release dated, 13 May 2022 titled “Option to Extend Bond Facility Maturity Date and Issue of New
Call Options”
11
Refer to ASX Release dated, 30 July 2021 titled “Over $10m New Funding Package Secured, Led by German
Investors to Accelerate the TGME Gold Project Development”
12
Refer to Notification to issue un-quoted securities dated, 16 May 2022.
12
In accordance with ASX Listing Rules 5.3.1 and 5.3.2, the Company provides the following
summary of expenditure incurred during the Quarter:
Mining exploration costs (incl exploration labour)
Mining Production and Development Costs (incl trial mining)
Licence to Operate Costs
Total
US
US
US
US
$406,734
$117,690
$230,364
$754,788
The Company’s Quarterly Appendix 5B reported US$181,000 payments to related parties and
their associates; as noted on the Appendix 5B this payment was for directors fees and consulting
fees (includes payments relating to current and prior quarters).
Capital Structure
The current capital structure of the Company is as follows:
Fully paid ordinary shares (ASX: TGM | OTC: TGMGF)
Unlisted options, performance rights and bonds (see “Annexure C”)
Number
550,227,337
66,431,433
The Company issued 12,350,000 new shares during the quarter relating to the completion of a
private placement and issued 15,000,000 unlisted options to 2InvestAG as part of negoitations
to extend the secured bond for a further 12 months.
The market capitalisation of TGM was US$2313 million (AU$33 million) as at 30 June 2022.
This announcement was authorised for release by the Board of Directors.
For more information, please visit www.thetagoldmines.com or contact:
Bill Guy, Chairman
Theta Gold Mines Limited
T: +61 2 8046 7584
billg@thetagoldmines.com
Investor Relations
Australia: Ben Jarvis, Six Degrees Investor Relations: +61 (0) 431 271 538
https://twitter.com/ThetaGoldMines
https://www.linkedin.com/company/thetagoldmines/
13
Calculated as 550,227,337 fully-paid ordinary shares on issue at the closing price of AU$0.06 cents per share as
at 30 June 2022 converted at the RBA exchange rate of AUD:USD of 0.6889.
13
Competent Persons Statement
Mineral Resources and Ore Reserves
The information in this report relating to mineral resources and ore reserves is based on, and fairly
reflects, the information and supporting documentation compiled by Mr Uwe Engelmann (BSc (Zoo. &
Bot.), BSc Hons (Geol.), Pr.Sci.Nat. No. 400058/08, MGSSA), a director of Minxcon (Pty) Ltd and a
member of the South African Council for Natural Scientific Professions and Mr Daniel van Heerden
(B.Ing (Mining M.Com (Business Management), member of Engineering Council of South Africa (Pr.Eng.
Reg. No. 20050318)), a director of Minxcon (Pty) Ltd and a fellow of the South African Institute of Mining
and Metallurgy (FSAIMM Reg. No. 37309).
Metallurgical results
The information in this report relating to exploration results is based on, and fairly reflects, the
information and supporting documentation compiled by Mr Phil Bentley (MSc (Geol), MSc (MinEx),
Pr.Sci.Nat. No. 400208/05, FGSSA), a consultant to the Company and a member of the South African
Council for Natural Scientific Professions.
The original reports titled “Theta Gold Increases Mineral Resource to over 6Moz” dated 16 May 2019,
“Optimised Mine Schedule for Theta Open Pit Starter Project Delivers Significant Improvements” dated
20 April 2020, “Excellent Bulk Metallurgical Results Provides Confidence For Underground PFS” and
“Initial Maiden Underground Mining Reserve 419,000 oz Gold” dated 8 April 2021 were released to the
Australian Securities Exchange (ASX) on those dates. The Company confirms that:
•
•
it is not aware of any new information or data that materially affects the information included in
the ASX announcements; and
all material assumptions and technical parameters underpinning the estimates in the ASX
announcements continue to apply and have not materially changed.
14
ABOUT THETA GOLD MINES LIMITED
Theta Gold Mines Limited (ASX: TGM | OTC: TGMGF) is a gold mining development company that holds a
range of prospective gold assets in a world-renowned South African gold mining region. These assets
include several surface and near-surface high-grade gold projects which provide cost advantages relative
to other gold producers in the region.
Theta Gold’s core project is located next to the historical gold mining town of Pilgrim’s Rest, in
Mpumalanga Province, some 370km northeast of Johannesburg by road or 95km north of Nelspruit
(Capital City of Mpumalanga Province). Following small scale production from 2011 – 2015, the Company
is currently focussing on the construction of a new gold processing plant within its approved footprint at
the TGME plant, and for the processing of the Theta Open Pit oxide gold ore. Nearby surface and
underground mines and prospects are being evaluated.
The Company aims to build a solid production platform to over 160 kozpa based primarily around shallow,
open-cut or adit-entry hard rock mining sources. Theta Gold has access to over 43 historical mines and
prospect areas that can be accessed and explored, with over 6.7Moz of historical production recorded.
Theta Gold holds 100% issued capital of its South African subsidiary, Theta Gold SA (Pty) Ltd (“SGSA”).
SGSA holds a 74% shareholding in both Transvaal Gold Mining Estates Limited (“TGME”) and Sabie Mines
(Pty) Ltd (“Sabie Mines”). The balance of shareholding is held by Black Economic Empowerment (“BEE”)
entities. The BEE shareholding in TGME and Sabie Mines is comprised of a combination of local community
trusts, an employee trust and a strategic entrepreneurial partner.
DISCLAIMER
This announcement has been prepared by and issued by Theta Gold Mines Limited to assist in informing
interested parties about the Company and should not be considered as an offer or invitation to subscribe
for or purchase any securities in the Company or as an inducement to make an offer or invitation with
respect to those securities. No agreement to subscribe for securities in the Company will be entered into
on the basis of this announcement.
This announcement may contain forward looking statements. Whilst Theta Gold has no reason to believe
that any such statements and projections are either false, misleading or incorrect, it does not warrant or
guarantee such statements. Nothing contained in this announcement constitutes investment, legal, tax or
other advice. This overview of Theta Gold does not purport to be all inclusive or to contain all information
which its recipients may require in order to make an informed assessment of the Company’s prospects.
Before making an investment decision, you should consult your professional adviser, and perform your
own analysis prior to making any investment decision. To the maximum extent permitted by law, the
Company makes no representation and gives no assurance, guarantee or warranty, express or implied, as
to, and take no responsibility and assume no liability for, the authenticity, validity, accuracy, suitability or
completeness of, or any errors in or omissions, from any information, s