GEOTECHNICAL DRILLING AND GEOPHYSICS UNDERWAY
FOR STARTER THETA PIT
Highlights:
Geotechnical drilling and geophysics underway for starter Theta pit
Design engineering work also advancing
Mining is defined as an essential service in South Africa – limited impact to on-site works
timetable
Trial mining is planned for late this calendar year
Theta Gold Mines Limited (“Theta Gold” or “Company”) (ASX: TGM, TGMO | OTCQB: TGMGF) is
pleased to provide this update on ongoing project development activities at the Starter Theta
Project with geotechnical drilling and a geophysical survey now underway (see figures 1&2
overleaf).
Theta Gold is undertaking a geotechnical assessment of the areas identified for the Waste Rock
Dumps (WRDs) and Pollution Control Dams (PCD) within the plan area. Design engineering work
for minesite infrastructure is progressing well with all these initiatives scheduled for completion
by the end of September.
Theta Gold has not witnessed any impact to its works program as a result of lockdown measures
due to COVID-19. Under section 213 of the Labour Relations Act. 1995, mining operations in
South Africa are deemed as an essential service i and Theta Gold’s operations are thus not
affected. The Company’s onsite team has completed all necessary paperwork and safety
protocols and mine site development activities onsite remain on-track.
Chairman Mr Bill Guy stated, “We are pleased to kick off geotechnical drilling and geophysical
survey work. This activity is another crucial step in our ongoing project development works which
are progressing to plan and are not delayed.
“We can confirm that all of our team is on site and safely managing this works program. We have
an exceptionally busy program underway at the Starter Theta Pit. We are also finalising
engineering plans for roads and infrastructure, another critical mine development milestone, and
getting prepared for trial mining which is scheduled for late in the year.
“I look forward to keeping shareholders updated on progress as we continue to steadily work our
way through these project development initiatives.”
Theta Gold Mines Limited ABN 30 131 758 177
Suite 80, Level 35 (Servcorp), International Tower One, 100 Barangaroo Avenue, Sydney NSW 2000
Tel: +61 2 8046 7584 Email: info@thetagoldmines.com
www.thetagoldmines.com
Figure 1: Track mounted reverse circulation drill rig and compressor on site at the Starter Theta Pit
Figure 2: Drilling activities in the Plant Area
2
This announcement was authorised for release by the Board of Directors.
For more information please visit www.thetagoldmines.com or contact:
Bill Guy, Chairman
Theta Gold Mines Limited
T: +61 2 8046 7584
billg@thetagoldmines.com
Investor Relations:
Australia - Ben Jarvis, Six Degrees Investor Relations: +61 2 9230 0661
United States - Michael Porter, Porter, LeVay & Rose Inc: +1 212 564 4700,
theta@plrinvest.com
ABOUT THETA GOLD MINES LIMITED
Theta Gold Mines Limited (ASX: TGM, TGMO | OTCQB: TGMGF) is a gold development company that holds
a range of prospective gold assets in a world-renowned South African gold mining region. These assets
include several surface and near-surface high-grade gold projects which provide cost advantages relative
to other gold producers in the region.
Theta Gold’s core project is located next to the historical gold mining town of Pilgrim’s Rest, in
Mpumalanga Province, some 370km northeast of Johannesburg by road or 95km north of Nelspruit
(Capital City of Mpumalanga Province). Following small scale production from 2011 – 2015, the Company
is currently focussing on the construction of a new gold processing plant within its approved footprint at
the TGME plant, and for the processing of the Theta Open Pit oxide gold ore. Nearby surface and
underground mines and prospects are expected to be further evaluated in the future.
The Company aims to build a solid production platform to over 150kozpa based primarily around shallow,
open-pit or adit-entry shallow underground hard rock mining sources. Theta Gold has access to over 43
historical mines and prospect areas that can be accessed and explored, with over 6.7Moz of historical
production recorded.
Theta Gold holds 100% issued capital of its South African subsidiary, Stonewall Mining (Pty) Ltd
(“Stonewall”). Stonewall holds a 74% shareholding in both Transvaal Gold Mining Estates Limited
(“TGME”) and Sabie Mines (Pty) Ltd (“Sabie Mines”). The balance of shareholding is held by Black Economic
Empowerment (“BEE”) entities. The South African Mining Charter requires a minimum of 26% meaningful
economic participation by the historically disadvantaged South Africans (“HDSAs”). The BEE shareholding
in TGME and Sabie Mines is comprised of a combination of local community trusts, an employee trust and
a strategic entrepreneurial partner.
3
DISCLAIMER
This announcement has been prepared by and issued by Theta Gold Mines Limited to assist in informing
interested parties about the Company and should not be considered as an offer or invitation to subscribe
for or purchase any securities in the Company or as an inducement to make an offer or invitation with
respect to those securities. No agreement to subscribe for securities in the Company will be entered into
on the basis of this announcement.
This announcement may contain forward looking statements. Whilst Theta Gold has no reason to believe
that any such statements and projections are either false, misleading or incorrect, it does not warrant or
guarantee such statements. Nothing contained in this announcement constitutes investment, legal, tax
or other advice. This overview of Theta Gold does not purport to be all inclusive or to contain all
information which its recipients may require in order to make an informed assessment of the Company’s
prospects. Before making an investment decision, you should consult your professional adviser, and
perform your own analysis prior to making any investment decision. To the maximum extent permitted by
law, the Company makes no representation and gives no assurance, guarantee or warranty, express or
implied, as to, and take no responsibility and assume no liability for, the authenticity, validity, accuracy,
suitability or completeness of, or any errors in or omissions, from any information, statement or opinion
contained in this announcement. This announcement contains information, ideas and analysis which are
proprietary to Theta Gold.
FORWARD LOOKING AND CAUTIONARY STATEMENTS
This announcement may refer to the intention of Theta Gold regarding estimates or future events which
could be considered forward looking statements. Forward looking statements are typically preceded by
words such as “Forecast”, “Planned”, “Expected”, “Intends”, “Potential”, “Conceptual”, “Believes”,
“Anticipates”, “Predicted”, “Estimated” or similar expressions. Forward looking statements, opinions and
estimates included in this announcement are based on assumptions and contingencies which are subject
to change without notice, and may be influenced by such factors as funding availability, market-related
forces (commodity prices, exchange rates, stock market indices and the like) and political or economic
events (including government or community issues, global or systemic events). Forward looking
statements are provided as a general reflection of the intention of the Company as at the date of release
of the document, however are subject to change without notice, and at any time. Future events are subject
to risks and uncertainties, and as such results, performance and achievements may in fact differ from
those referred to in this announcement. Mining, by its nature, and related activities including mineral
exploration, are subject to a large number of variables and risks, many of which cannot be adequately
addressed, or be expected to be assessed, in this document. Work contained within or referenced in this
report may contain incorrect statements, errors, miscalculations, omissions and other mistakes. For this
reason, any conclusions, inferences, judgments, opinions, recommendations or other interpretations
either contained in this announcement, or referencing this announcement, cannot be relied upon. There
can be no assurance that future results or events will be consistent with any such opinions, forecasts or
estimates. The Company believes it has a reasonable basis for making the forward looking statements
contained in this document, with respect to any production targets, resource statements or financial
estimates, however further work to define Mineral Resources or Reserves, technical studies including
feasibilities, and related investigations are required prior to commencement of mining. No liability is
accepted for any loss, cost or damage suffered or incurred by the reliance on the sufficiency or
completeness of the information, opinions or beliefs contained in this announcement.
i
https://www.gov.za/documents/labour-relations-act
4
Share your feedback
Discover