Quarterly Activities & Cashflow Report - 30 September 2022
Released
Released
Announcement PDF
31 October 2022
ASX ANNOUNCEMENT
(ASX:TGM)
QUARTERLY REPORT
1 July 2022 to 30 September 2022
Theta Gold Mines Limited (“Theta Gold” or “Company”) (ASX: TGM | OTC: TGMGF) is pleased to
report on its activities for the period from 1 July 2022 to 30 September 2022.
HIGHLIGHTS
POST SEPTEMBER 2022 QUARTER UPDATE:
•
Theta Gold signed a A$110m (US$70m) non-binding Term Sheet (“TGME Stream”) with
Sprott Streaming and Royalty Corporation (“Sprott”) for pre-development, development
capital and operating expenditure to bring the initial stage of TGME Gold Project (the
“Project”) into production and reach positive cash flow1.
Key features of Sprott TGME Stream Term Sheet include:
o Sprott to advance US$70 million cash in return for a gold stream on Theta’s TGME
Gold Project where Theta is expected to deliver to Sprott up to 100,000 ounces of
gold.
o The TGME Stream will be a significant milestone on the path of achieving Theta’s
initial 1.24Moz Life of Mine2 (“LOM”) strategy of first gold production at the TGME
Gold Project.
o The TGME Stream covers 90% of TGME Gold Project’s first stage US$77m peak
funding1 requirement; the funding provides further confidence for the Theta board
to deliver its growth strategy to achieve a 160,000 oz p.a production profile within
five years with potential to expand the mineral resource and incorporate up to 40
other mines near to the plant site.
o The Stream funding is conditional on completion of due diligence, final definitive
documentation, cost to complete certificate and South African regulatory
approvals.
1
Refer to Theta’s announcement “Theta Gold Executes a A$110M (US$70M) Non-Binding Funding Term Sheet with Sprott for its
TGME Gold Project”
2 Refer to Theta’s announcement “Theta’s TGME Definitive FS Confirms NPV10% OF $A432 Million at US$1,642/OZ Gold Price”
dated 27 July 2022 and Feasibility Study information booklet located on TGM website.
Theta Gold Mines Limited ABN 30 131 758 177
Suite 80, Level 35 (Servcorp), International Tower One, 100 Barangaroo Avenue, Sydney NSW 2000
Tel: +61 2 8046 7584 Email: info@thetagoldmines.com
www.thetagoldmines.com
•
TGM received firm commitments for A$1.7 million (before costs) through a Private
Placement (“Placement”) from existing and new institutional, professional and
sophisticated investors on 27 October 20223. Further to the Placement, the Company
also announced a Share Purchase Plan (“SPP”) to raise up to A$1.5 million on the same
terms as the Placement.
•
The Company announced that its 2022 Annual General Meeting (AGM) will be held on
Wednesday, 30 November 2022 at 11am (Sydney time) at the Boardroom, Servcorp
Offices, International Tower One, 100 Barangaroo Avenue, Barangaroo, Sydney, NSW,
2000. Shareholder Proxy votes must be received by the share registry by 11am (Sydney
time) on Monday, 28 November 2022.
DURING THE SEPTEMBER 2022 QUARTER:
•
On 27 July 20224, the TGME Underground Project definitive Feasibility Study (“FS”) was
released to ASX with an NPV10% of $A432 million at US$1,642 / oz gold price.
Key features of FS include:
o TGME Feasibility Study delivers 1.24Moz contained gold, underpinning an initial
12.9-year mine life.
o Strong financial return (based on LOM Plan), including (at a gold price of A$2,189/oz,
with first production targeted for 20245, including:
• Undiscounted free cash flows of US$508m, (A$678m), pre-tax US$717,
(A$956m);
• NPV (at a 10% discount rate) of US$219m (A$292m), pre-tax US$324m,
(A$432m);
• Capital payback period of 31 months;
• Pre-tax IRR of 65%;
• Combined Underground Projects have an AISC of US$834/oz (A$1,112/oz);
• Peak Capital requirement is US$77m (A$103m), total LOM capital
requirements US$174m (A$232m).
•
Front-End Engineering Design (“FEED”) of the TGME gold plant was completed, forming
an important input towards the finalisation of the FS of the TGME underground project6.
•
The Final Environmental Impact Assessment Report and Environmental Management
Programme (“EIA/EMPr”) were submitted to the Department of Mineral Resources and
Energy (“DMRE”) and the final technical documents for the integrated Water Use
License (“WUL”) application to the Department of Water and Sanitation (“DWS”) for
final decision.
•
Theta Gold Mines confirms the receipt of two project-critical regulatory licences7 for the
development of its TGME underground gold mine.
o Atmospheric Emissions Licence issued for the operation of the processing plant.
3
Refer to ASX release dated 27 October 2022 titled “Theta Gold raises funds to advance TGME Gold Project”
Refer to ASX release dated 27 July 2022 titled “Theta’s TGME Project FS confirms NPV10% of A$432 Million at
US$1,642 / Oz Gold Price”.
5
First gold production will be subject to financing and permitting approvals.
6
Refer to ASX release dated 20 June 2022 titled “TGME Gold Project Update”
7
Refer to ASX release dated 6 September 2022 titled” Two Licence Approvals Granted for the TGME Underground
Gold Project”
4
2
o State Forest Licence issued for Frankfort Mine.
•
The Frankfort Mine WUL application registered with the DWS – final decision expected
in Q4 of 2022.
•
A positive decision from DWS will mean Frankfort Mine is fully permitted and able to
commence mining.
•
TGM completed a capital raise of A$2.3 million (before costs) through a private
placement, from a majority of existing institutional, professional and sophisticated
investors during the September 2022 quarter8.
OPERATIONS AND DEVELOPMENT UPDATE SUMMARY
Feasibility Study for the TGME Underground Gold Mine Project
The definitive Feasiblity Study (“FS”) for the initial stage TGME Underground Gold Mine Project
(the “Project”) was delivered on 27 July 2022, confirming Theta Gold’s potential to be a significant
near-term, high-margin gold production project, with opportunities for future growth. TGME
stands for Transvaal Gold Mining Estate Limited, a 74% owned subsidiary controlled by the
Company, registered since 1895.
Based on the FS results, the Project will provide robust, financial returns from a long-life, large
underground mining operation, for a modest capital investment given the scale of operations
envisaged. The Project’s Life-of-Mine (“LOM”) will initially comprise a 12.9-year mining operation
starting in Q1, 2023 9 and delivering LOM production of 1.24Moz’s of contained gold. The
estimated peak development capital (“CAPEX”) is A$103 million (US$77m), with the Project
forecast to generate a pre-tax NPV10% of A$432 million and pre-tax internal Rate of Return (“IRR”)
of 65% at a forecast average gold price of A$2,189 / oz. Based on these metrics, the Project has
a projected capital payback period of 31 months.
The FS paves the way for a Final Investment Decision (“FID”) by the Theta Gold Board in respect
to debt funding negotiations and on-going discussions with financiers to respect to full debt or
partial debt and equity funding options. Theta Gold has appointed Sydney-based debt funding
advisor the Kamara Group10 to assist it through this important process.
The TGME Underground Gold Project aims to restart historical underground gold mines located
in a historically prolific gold mining region in the Mpumalanga Province of South Africa. The
Project Areas are centred on the town of Pilgrims Rest, some 370 km due northeast of
Johannesburg, and ownership has always been vested in TGM or its partners.
The Project targets the Beta (including the Beta North, Beta Central and Beta South sections),
Rietfontein, Frankfort and Clewer-Dukes Hill-Morgenzon (CDM) Mines. A significant amount of
gold resources remain underground which were not mined historically due to technological
limitations, or limiting ore characteristics.
8
Refer to ASX release dated 3 August 2022 titled “Share Placement and Funding”
Start time will be dependent on securing necessary funding and permitting approvals.
10
https://kamaragroup.com/
9
3
Table 1: Key Project Metrics
Description
Units
Base Case
Reserve Plan
Project Start Date
Qtr/Year-yyyy
Q1 2023
Q1 2023
Commercial Production Start Date
Qtr/Year-yyyy
Q2 2024
Q2 2024
Production build up period
Months
14
14
Life of mine
years
12.9
7.3
Underground ore mined (LOM)
Mt
6.46
2.85
Mined Grade
g/t
5.95
6.09
Gold Mined (LOM)
Moz
1.24
0.56
Production Rate
Kt/a
540
540
Production Rate
Kt/m
45
45
Grind size
µ
106
106
Gold recovered (average LOM)
%
87
87
Gold recovered (LOM)
Moz
1.08
0.49
Project economics below shows the sensivities to the various gold price estimates and
demonstrates the robust financial returns of the Project.
Table 2: Project Economics at Various Gold Prices – Base Case (AUD)
Project Economics at
gold price
NPV @ 10% (real) Pre-tax
NPV @ 10% (real) Posttax
IRR (%) Pre-tax
IRR (%) Post-tax
AISC
EBITDA annual average
EBIT annual average
Free Cash Flow (Pre-tax)
Free Cash Flow (Post-tax)
Development Capital –
Peak Funding
Capital Sustaining
Payback post-tax
Capital Efficiency (Pre-Tax
NPV/Dev Capital
Capital Efficiency (PostTax NPV/Dev Capital
NOTES:
1.
2.
Unit
AUDm
Forecast
USD1,500/ USD1,600/ USD1,800/ USD2,000/ USD2,200/
(USD1,642/
oz
oz
oz
oz
oz
oz Avg)
432
339
405
536
669
802
AUDm
292
232
274
359
447
533
%
%
AUD/oz
AUDm
AUDm
AUDm
AUDm
65%
57%
1,112
92
80
956
678
57%
50%
1,096
77
66
768
550
64%
56%
1,107
87
76
897
638
77%
67%
1,129
107
96
1,158
814
90%
78%
1,149
128
116
1,421
996
102%
87%
1,167
148
136
1,686
1,175
AUDm
102
102
102
102
102
102
AUDm
Months
49
31
49
33
49
31
49
28
49
25
49
24
%
422%
332%
395%
524%
653%
783%
%
285%
226%
268%
351%
437%
521%
Converted to AUD from USD using AUD:USD exchange rate of 1.333.
Due to rounding, numbers presented throughout this document may not add up precisely to the totals, provided and percentages
may not precisely reflect the absolute figures.
4
Figure 1: Annual Gold Production – Base Case
Figure 2: Annual and Cumulative Cash Flow (Post-Tax) – Base Case (AUD)
NOTES:1. Forecast Prices averaging USD1,642/oz over LOM.
2. Converted to AUD from USD at exchange rate of 1.333 AUD:USD.
Beta is scheduled as the first operation to commence production, followed by Rietfontein, and
finally CDM and Frankfort simultaneously. In comparison to CDM and Frankfort, Beta and
Rietfontein are higher-grade mines.
A metallurgical plant, which acts as the central processing plant for all the historical operations,
is situated in close proximity with a maximum distance to operations of ~40km. A new facility will
be established on this footprint and will treat all the ore from the underground operations.
Two scheduling strategies have been investigated in the FS. The Base Case considers a LOM plan
targeting the total Mineral Resources (Measured, Indicated and Inferred). The Ore Reserve Plan
considers a LOM plan targeting only Measured and Indicated Mineral Resources.
5
This FS demonstrates the ability to achieve optimised cash flows by scheduling production from
the operations. The mine designs and associated costs per operational element feed into a
combined operations financial model. The Ore Reserve Plan supports the declaration of
compliant JORC Code 2012 Ore Reserves.
Figure 3: Process Flow Schematic Phase 1
The FS has been split into three phases, allowing for various processing scenarios aligned with
the mining development program. The design of each phase is based on a stand-alone processing
facility aligned with the mining plan of the ore body.
•
Phase 1 – Carbon-in-Leach (“CIL”) Plant
Free milling ore is process for the first 7 Years. The design and costing of a 45 ktpm oxide
ore processing plant including crushing, milling, CIL and elution with doré produced on
site. Testwork undertaken on various "free-milling" ores has indicated high undissolved
gold losses, indicating the presence of small amounts of sulphidic constituents.
This was particularly evident when completing standard cyanidation bottle roll trials on
Dukes and Morgenzon samples. Subsequent additional testwork supports this. As a result,
the Phase 1 circuit will include a flash flotation stage, post milling to remove sulphide
associated material before conventional cyanidation. This flotation mass pull will join the
concentrator product from Phase 2.
•
Phase 2 – Gold Concentrator Plant
The design and cost of a 20 ktpm concentrating plant including crushing, milling, DMS and
flotation. The final products consist of a combined carbon and sulphide flotation
concentrate. The carbon flotation concentrate being processed through the CIL 3 plant
and the sulphide flotation concentrate is processed through the CIL 1 plant.
6
•
Phase 3 – Oxidative Leaching of Sulphide Concentrate
The Phase 3 plant includes a 45 ktpm Leach-oxdisation process plant that was designed
and costed, including crushing, milling and carbon/sulphide flotation. The phase 3 plant
consists of both the gold concentrator plant as well as the CIL plant as described in Phase
1 and Phase 2. The carbon flotation concentrate processed in a dedicated CIL circuit (CIL
3), sulphide flotation concentrate oxidised under atmospheric conditions with liquid
oxygen injection and high shear reactors. Oxidised product to be treated in a separate
batch CIL process (CIL 1) with the tails treated in a large CIL (CIL 2), that also processes the
flotation tails as well as “free-milling” ore feed. This option allows for all recovered gold
to be produced as doré on-site with no concentrate produced.
Although there are some shared infrastructure and processing equipment between the phases,
for the purposes of this FS the phase One plant will be constructed first to treat CDM, Rietfontein
and Beta ore with phase three being constructed at a later stage before mining of Frankfort ore
commences.
The plant will be developed by an Engineering, Procurement and Construction (“EPC”) contractor.
The Company will run a tender process to evaluate contracts for the construction and upgrade
of existing infrastructure including detailed engineering for the plant, procurement, fabrication
and delivery to site of plant, equipment and materials and construction of the process plant
facilities.
Project Finance – Sprott Term Sheet
Theta Gold announced it has signed a non-binding Term Sheet (“Term Sheet”) with Sprott
Resource Streaming and Royalty Corporation (“Sprott”) under which Sprott is to advance US$70
million (A$110 million) cash in return for a gold stream on Theta’s TGME Gold Project. The Project
is expected to deliver to Sprott up to 100,000 ounces of gold over its LOM, for which Sprott will
pay 10% of the gold price per ounce delivered under the stream. Theta has the option to buyback 50% of the stream based on a pre-agreed price, following which Theta will deliver 2% of the
ongoing gold production. Prior to initial gold delivery, Theta will pay in cash or scrip (at 10%
discount to 5 days volume-weighted-average-price (“VWAP”)) on a semi-annual basis, 9.5% per
annum interest to Sprott for the funds advanced.
Under the Term Sheet, conditions precedent to closing include the completion of technical, legal,
and environmental and social due diligence, the receipt and review of the project’s final
development budget and schedule, the completion of definitive documentation, and the receipt
of applicable environmental permits, operating licences and regulatory approvals. Closing is
scheduled by the first quarter of 2023 and the funds will be applied towards the construction of
the TGME Gold Project.
A due diligence team involving externally appointed consultants by Sprott shall start
immediately; upon a satisfactory conclusion, a Binding Gold Stream Agreement between Sprott
and Theta Gold shall be finalised, executed and announced to the market in detail.
Sydney-based debt specialist the Kamara Group is advising and representing the Company to
complete this project financing process.
7
Project Permits and Approvals
The Company announced in July 202211 that the final Environmental Impact Assessment Report
and Environmental Management Programme (“EIA/EMPr”) have been submitted to the
Department of Mineral Resources and Energy (“DMRE”) and the final technical documents for
the integrated water use license application to the Department of Water and Sanitation (“DWS”)
for final decision.
The outcome of the decisions from the DMRE and DWS on the applications are expected in Q4
of 2022 with an additional 90-day review and objection period. A positive decision from the
Competent Authorities will enable the Company to commence with its initial stage TGME
Underground Gold Project, covered by Mining Right 83 (“MR83”).
In September 202212 Theta Gold announced that it has received two environmental licences for
the TGME Underground Gold Project.The successful approvals mark another key step forward
for the development of the Project and leave the Company on track to achieve its target of full
project permitting by Q1 2023.
Theta Gold confirmed receipt of an Atmospheric Emissions Licence from the South African
Department of Forestry, Fisheries, and Environment (“DFFE”).
This licence was issued in accordance with section 41(1) the National Environmental
Management: Air Quality Act, 2004 (Act 39 of 2004), and provides Theta Gold with the permitting
approval to operate the gold processing plant.
Secondly, a State Forest Licence was issued to the Company in accordance with Sections 23 and
24 of the National Forests Act, 1998 (Act No 84 of 1998) for the Frankfort Mine. The issuing of
this licence is outside the normal Department Mines Resource and Energy (DMRE) permitting
process, but was required in this instance as the forestry company is also the landowner at
Frankfort Mine.
The successful approvals are the by-product of an extensive period of engagement with domestic
regulators, which required the company to satisfy a broad range of criteria to meet the standards
set out by government departments at the federal level.
In light of its latest round of successful license applications, the Company continues to advance
the long-term environmental approvals process for MR83 following the release of its definitive
Feasibility Study13 earlier this year (refer ASX Announcement 27 July 2022).
11
Ref to ASX release dated 18 July 2022 titled “Permitting Update TGME Underground Gold Mine”
Ref to ASX release dated 6 September 2022 titled “Two Licence Approvals Granted for the TGME Underground
Gold Project”
13
ASX release dated 27 July 2022 titled “Theta Gold's TGME Project DFS confirms NPV10% of AUD432 Million”
12
8
Environmental Approvals for MINING RIGHT (MR) 83 – Progress Table
Forestry permit applications with the DFFE for the continuation of mining remain in progress14
(refer ASX Announcement 18 July 2022)
The Company looks forward to providing further updates on its regulatory pathway in Q4 2022,
as it remains on track to obtain full regulatory approval for the project in the March quarter of
2023.
Gold Plant Front-End Engineering Design Complete
Front-End Engineering Design (“FEED”) of the TGME gold plant has been completed, forming an
important input towards the finalisation of the Feasibility Study of the TGME underground gold
project.
Theta Gold provide an update on the MR83 gold processing plant advising that it had appointed
MET63 15 , which specialises in the design and construction of advanced modular processing
plants, to undertake and complete the plant design, based on a thorough metallurgical testwork
program, and with multi-tier internal and independent oversight.
Key Features of the Gold Process Plant:
•
•
•
•
14
15
The new gold process plant is designed to have a milling capacity of 540,000 tons per
annum. The plant design consists of two individual processing streams, capable of
processing “free-milling” and sulphide ore separately.
The new gold processing plant is designed to fit into the current plant footprint which
forms part of the MR83, therefore no additional environmental permitting will be
required.
The new processing plant components include three-stage crushing, milling, reagent,
flotation, CIL, elution, and gold room sections as indicated in figure 4 & 5.
The gold plant will produce dore gold bars.
ASX release date 18 July 2022 titled “Permitting Update TGME Underground Gold Project”
https://met63.com/
9
•
•
Engineering and costing have been completed to the required level of accuracy for the
definitive FS.
The completed design includes water and power reticulation with the scope to increase
the capacity with modular units for future plant expansions, consistent with the
Company’s strategy to reach its gold production target of 160,000 oz/a within five years.
The latest proven available automation technologies were incorporated into the gold
processing plant design which will reduce labour requirements and enhance productivity
levels.
The tailings disposal will be onto the existing tailings storage facility located some 150m
from the plant.
Some existing plant infrastructures were incorporated into the new gold processing plant.
•
A 3D rendering of the processing plant is illustrated in Figure 4
•
•
•
Figure 4: 3D Plant Rendering Final design Phase 1-3.
10
Figure 5: New TGME Plant Layout
Figure 6: Existing Plant Drone View (post demolition of old sections)
11
Environmental Social Governance (ESG)
Environmental Monitoring Programme
A detailed environmental monitoring program has been established for the Project mining areas
within MR83 that include dust monitoring, surface water monitoring, groundwater monitoring,
water abstraction and biomonitoring.
The monitoring program is based on the requirements of the various Integrated Water Use
Licenses (“WULs”) and Environmental Management Programmes (“EMPrs”) granted to TGME.
The dust monitoring program consists of a dust fallout monitoring network, comprising of four
(4) single dust fallout units installed around the Tailings dam (“TSF”). The TSF dust samples are
collected monthly by the TGME environmental department and taken to Regen Waters
Laboratory in Witbank for analysis.
Biomonitoring is conducted bi-annually at the biomonitoring sites as required by the conditions
of the granted WULs to TGME. The biomonitoring site assessments for the 2022 dry season were
conducted during the week of 19 September 2022.
Future CO2-e footprint
Airshed Planning Professionals calculated the amount of CO2-e per gold production once the
mine is in production. The calculations were based on the equipment list and hours for the MR83
underground project. The amount of CO2-e per gold production is 0.25 tCO2e/oz.
The work on CO2-e footprint is preliminary but it does demonstrate with hard work the project
will have a very modest CO2-e footprint. More work is required to validated the assumptions and
projections of this initial work.
Figure 7,8: Samples taken to determine the assessment of the habitat integrity of the river. Surface water
quality variables measured a Hach HQ40d Multimeter
12
Social and Labour Plan development
A great deal of work went into the finalization of the information required for the drafting of the
new 5-year Social and Labour Plan (“SLP”) for MR83. Investigations were done to find potential
buildings to be uilised for the SLP implementation.
A site visit to Tsakhane Community was conducted on 13 September 2022 to gain better insight
into the small-scale household farming project that has been implemented by Umsizi Sustainable
Social Solutions on behalf of a Gold Mining Company in Johannesburg.
Stakeholder Meetings
TGME is an active member of the Lower Oliphants Catchment Management Forum. The forum
provides for information sharing and stakeholder inputs in water resources management issues
throughout the water management area. TGME hosted the catchment meeting in Pilgrims Rest
on 9 September 2022. During this meeting, TGME presented on the MR83 underground project,
our proposed ecological compensation program.
13
CORPORATE / GOVERNANCE UPDATE SUMMARY
Completion of Capital Riase via a Private Placement
On 3 August 202216, TGM announced it had completed a capital raise of A$2.3 million (before
costs) through a private placement from a majority of existing institutional, professional and
sophisticated investors.
The Company issued 35,384,615 new TGM Ordinary Shares at the issue price of A$0.065 cents
per share, using the Company’s existing placement capacity pursuant to Listing Rule 7.1.
Use of funds raised from the share placement as follows:
a) Project expenditure including pre-liminary development and planning activities for the
TGME Underground Gold Mine Project;
b) Progress towards completion of permitting approvals for the project, and
c) General working capital and corporate overheads.
Cash Position and Subsequent Funding
As at 30 September 2022, the Group had US$26,000 in cash.
On 27 October, the Company announced it received firm commitments for A$1.7 million (before
costs) through a private placement from existing and new institutional, professional and
sophisticated investors 17 . Further to the Placement, the Company also announced a Share
Purchase Plan (“SPP”) to raise up to A$1.5 million on the same terms as the Placement.
Registered shareholders of the Company as at 5:00pm (AEDT) 26 th October 2022 (Record Date).
The SPP is available to all existing shareholders with a registered address in Australia or New
Zealand at the Record Date to apply for shares by participating in a SPP. The shares issued under
the SPP will be purchased free of brokerage and no prospectus will be issued.
The SPP will provide each eligible shareholder with the opportunity to apply for up to $30,000
worth of shares as the same issue price as under the Placement, being A$0.07 per share. In the
event that less than A$1.5 million is subscribed for under the SPP, any shortfall maybe allocated
at the discretion of the board of the Company and subject to shareholder approval.
The funds raised under the SPP will be used for the same purposes as the Private Placement and
any shares issued under the SPP will rank equally with the existing shares on issue.
Full details of the SPP will be set out in an offer document which is scheduled to be dispatched
to eligible shareholders before Monday, 7th November 2022 with the closing date for acceptances
expected to be Tuesday, 29th November 2022. The timing of the SPP is indicative only and the
Directors reserve the right to vary the dates and times without notice.
16
17
Ref to ASX release dated 3 August 2022 titled ”Share Placement and Funding”
Refer to ASX release dated 27 October 2022 titled “Theta Gold raises funds to advance TGME Gold Project”
14
As announced on 25 March 2021, the Company entered into an At-The-Market Subscription Deed
(“ATM”) with Acuity Capital. The ATM provides the Company with up to AU$15 million of standby
equity capital with the expiry of the ATM being 31 July 2023. There are no requirements on the
Company to utilise the ATM and the Company may terminate the ATM at any time, without cost
or penalty. As security for the ATM, the Company has issued 24 million Theta Gold shares to be
held by Acuity Capital. As of the date of this report, this position remains unchanged.
In accordance with ASX Listing Rules 5.3.1 and 5.3.2, the Company provides the following
summary of expenditure incurred during the Quarter:
Mining exploration costs (incl exploration labour)
Mining Production and Development Costs (incl trial mining)
Licence to Operate Costs
Total
US
US
US
US
$240,660
$125,145
$67,361
$433,166
The Company’s Quarterly Appendix 5B reported US$31,180 payments to related parties and their
associates; as noted on the Appendix 5B this payment was for directors fees and consulting fees
(includes payments relating to current and prior quarters).
Capital Structure
The current capital structure of the Company at 30 September 2022 is as follows:
Fully paid ordinary shares (ASX: TGM | OTC: TGMGF)
Unlisted options, performance rights and bonds (see “Annexure C”)
Number
586,811,952
79,231,433
The Company issued 35,384,615 new shares during the quarter relating to the completion of a
private placement and 1,200,000 shares to a consulting advisor in lieu of cash payment of fees.
The Company also issued 20,000,000 unlisted options to 2InvestAG as compensation under a
Corporate Advisory Agreement where 2Invest AG will provide non-exclusive services in
connection with identifying development funding investors for TGME Underground Gold Project.
The market capitalisation of TGM was A$41 million 18 million (US$26.7m) as at 30 September
2022.
This announcement was authorised for release by the Board of Directors.
For more information, please visit www.thetagoldmines.com or contact:
Bill Guy, Chairman
Theta Gold Mines Limited
T: +61 2 8046 7584
billg@thetagoldmines.com
18
Calculated as 586,811,952 fully-paid ordinary shares on issue at the closing price of AU$0.07 cents per share as
at 30 September 2022 converted at the RBA exchange rate of AUD:USD of 0.6502.
15
Investor Relations
Australia: Ben Jarvis, Six Degrees Investor Relations: +61 (0) 431 271 538
https://twitter.com/ThetaGoldMines
https://www.linkedin.com/company/thetagoldmines/
Competent Persons Statement
Mineral Resources and Ore Reserves
The information in this report relating to mineral resources and ore reserves is based on, and fairly
reflects, the information and supporting documentation compiled by Mr Uwe Engelmann (BSc (Zoo. &
Bot.), BSc Hons (Geol.), Pr.Sci.Nat. No. 400058/08, MGSSA), a director of Minxcon (Pty) Ltd and a
member of the South African Council for Natural Scientific Professions and Mr Daniel van Heerden
(B.Ing (Mining M.Com (Business Management), member of Engineering Council of South Africa (Pr.Eng.
Reg. No. 20050318)), a director of Minxcon (Pty) Ltd and a fellow of the South African Institute of Mining
and Metallurgy (FSAIMM Reg. No. 37309).
Metallurgical results
The information in this report relating to exploration res