Theta Gold's TGME Project DFS confirms NPV of AUD432 Million
Released
Released
Announcement PDF
27 July 2022
ASX ANNOUNCEMENT
(ASX: TGM)
THETA’S TGME PROJECT DEFINITIVE FS CONFIRMS NPV(10%) OF A$432
MILLION AT US$1,642/OZ GOLD PRICE
The Feasibility Study (‘FS’) presents a clear pathway to production via the re-development of
TGME’s gold assets within South Africa’s renowned gold mining regions, with a forecast total Life
of Mine (LOM) production of 1.24 Moz’s of contained gold. Early site development works,
finalisation of permitting and approvals are in progress.
FS KEY BASE CASE RESULTS:
•
Transvaal Gold Mining Estate (TGME) Underground Gold Mine Project, which initially includes
4 mines (Phase 1) - Beta, Frankfort, Clewer-Dukes Hill-Morgenzon (CDM) and Rietfontein located near the towns of Pilgrim’s Rest and Sabie in Mpumalanga Province, 370km northeast
of Johannesburg;
•
The TGME Gold Project contains more than 43 historical mines with a longer-term plan to bring
these large shallow goldfields back to production with minimum capital expenditure.
Additionally, there is 3.6 Moz of Inferred Mineral Resources available for future development
– not included1 in the Base Case LOM plan;
•
Execution ready with Front-End Engineering Design (FEED) of the TGME gold plant complete.
Plant designs support long-term growth initiatives;
•
Phase 1 of the Initial 12.9 year LOM plan at the processing rate of 540 ktpa with key physical
parameters including;
o Gold ore production build up over the first 41 months is 45 ktpm from the initial four
mines;
o Free-milling stand-alone processing plant, with doré produced on site to produce 80 –
100Koz p.a. @ 5.18 g/t recovered gold – at 87.1% gold recovery rate;
o First gold production is scheduled for Q2, 20242;
o Gold plant expected to produce over 100koz/pa by the third year of production;
o Recommission of existing on-site Tailings Storage Facility (TSF);
o LOM plan outlines a recovery of 1.08 Moz gold from 1.24 Moz mined;
1 These resources were not considered for this FS due to different environmental approval application process required/planned.
2 First gold produced timing will be subject to securing funding and obtaining all necessary regulatory permitting approvals
.
Theta Gold Mines Limited ABN 30 131 758 177
Suite 80, Level 35 (Servcorp), International Tower One, 100 Barangaroo Avenue, Sydney NSW 2000
Tel: +61 2 8046 7584 Email: info@thetagoldmines.com
www.thetagoldmines.com
o LOM plan includes 558koz Proven/Probable Reserve covering over 7 years of mining
and 662Koz of Inferred Mineral Resource;
o The focus of the mining strategy remains on extracting all the mineable Mineral
Resources, including 53% of Inferred Mineral Resources; and
o Over 3 Moz of Inferred Mineral Resources available for future development are not
included in the Base Case LOM plan.
•
Under average gold prices of US$1,642 / oz (A$2,189 3 / oz), the FS demonstrates strong
financial returns4 (based on LOM plan), including:
o Undiscounted free cash flows of US$508m (A$678m), pre-tax US$717m (A$956m);
o NPV (at a 10% discount rate) of US$219m (A$292m), pre-tax US$324m (A$432m);
o Capital payback period of 31 months;
o Pre-tax IRR of 65%;
o Combined Underground Projects have an AISC of US$834/oz (A$1,112/oz); and
o Peak Capital requirement is US$77m (A$103m)5, total capital US$174m (A$232m)6.
•
Potential upside beyond the FS includes:
o Phase 2 - Increase production to include 7 mines, with an expanded processing plant
to 80 ktpm producing up to 160 koz p.a. within five years;
o Enlarging mineral resources via exploration targets, alongside the incorporation of
additional mines from 40 neighbouring historical mines – located within a short
distance to the planned plant;
o Adoption of ESG fundamentals during the planning, design and development stages of
the project, which aims to deliver a reduction in energy consumption, diversify the
talent pool, and attract suppliers / contractors who utilise sustainable products;
o Tendering of mine services contracts in South Africa to achieve the most competitively
priced outcome; and
o All current reserves and LOM material are hosted in shallow orebodies.
•
Two scheduling strategies have been investigated, namely:
o Base Case: LOM Plan targeting the total Mineral Resources (Measured, Indicated and
Inferred); and
o Ore Reserve Plan: LOM Plan targets only Measured and Indicated Mineral Resources.
Both schedules are presented in Table 1 to 3, Appendix A, and both demonstrate strong
project economics.
3 USD to AUD converted at an exchange rate of 1.333.
4
Financial returns applying the ‘Base Case’ scenario statistics.
5 TGM is currently in discussion with debt financiers and has engaged an experienced debt advisor to assist in the negotiation of term-sheets for
funding of the Project. Further equity raises are also planned to fund working capital and part of the project capital if required, which may lead to
dilution to existing shareholders.
6 Th FS demonstrates that post to Peak Funding, the balance of Total Capital requirement will be self-funded from project cashflow. The board may
however, consider external funding solutions such as via equity, debt, gold pre-sales, gold-streaming or a mixture of these methods.
2
Figure 1 Panoramic view of TGME Processing Plant, Workshops and Tailings Dam
Table 1: Key Project Metrics
Description
Units
Base Case
Reserve Plan
Project Start Date
Qtr/Year
Q1 2023
Q1 2023
Commercial Production Start Date
Qtr/Year
Q2 2024
Q2 2024
Production build up period
Months
14
14
Life of mine
years
12.9
7.3
Underground ore mined (LOM)
Mt
6.46
2.85
Mined Grade
g/t
5.95
6.09
Gold Mined (LOM)
Moz
1.24
0.56
Production Rate
Kt/a
540
540
Production Rate
Kt/m
45
45
Grind size
µ
106
106
Gold recovered (average LOM)
%
87
87
Gold recovered (LOM)
Moz
1.08
0.49
Table 2: Project Economics at Various Gold Prices – Base Case (AUD)
Forecast
(USD1,642/ USD1,500/oz USD1,600/oz USD1,800/oz USD2,000/oz USD2,200/oz
oz Avg)
NPV @ 10% (real) Pre-tax AUDm
432
339
405
536
669
802
292
232
274
359
447
533
NPV @ 10% (real) Post-tax AUDm
IRR (%) Pre-tax
%
65%
57%
64%
77%
90%
102%
%
57%
50%
56%
67%
78%
87%
IRR (%) Post-tax
AISC
AUD/oz
1,112
1,096
1,107
1,129
1,149
1,167
AUDm
92
77
87
107
128
148
EBITDA annual average
EBIT annual average
AUDm
80
66
76
96
116
136
AUDm
956
768
897
1,158
1,421
1,686
Free Cash Flow (Pre-tax)
Free Cash Flow (Post-tax) AUDm
678
550
638
814
996
1,175
Development Capital –
AUDm
102
102
102
102
102
102
Peak Funding
49
49
49
49
49
49
AUDm
Capital Sustaining
Payback post-tax
Months
31
33
31
28
25
24
Capital Efficiency (Pre-Tax
%
422%
332%
395%
524%
653%
783%
NPV/Dev Capital
Capital Efficiency (Post%
285%
226%
268%
351%
437%
521%
Tax NPV/Dev Capital
Project Economics at
gold price
Unit
NOTES: 1. Converted to AUD from USD using AUD:USD exchange rate of 1.333.
2. Due to rounding, numbers presented throughout this document may not add up precisely to the totals, provided and percentages may
not precisely reflect the absolute figures.
3
Table 3: Project Economics at Various Gold Prices – Reserve Plan (AUD)
Project Economics at
gold price
Unit
NPV @ 10% (real) Pre-tax AUDm
NPV @ 10% (real) PostAUDm
tax
%
IRR (%) Pre-tax
%
IRR (%) Post-tax
AUD/oz
AISC
AUDm
EBITDA annual average
AUDm
EBIT annual average
AUDm
Free Cash Flow (Pre-tax)
Free Cash Flow (Post-tax) AUDm
Development Capital –
AUDm
Peak Funding
AUDm
Capital Sustaining
Months
Payback post-tax
Capital Efficiency (Pre-Tax
%
NPV/Dev Capital
Capital Efficiency (Post%
Tax NPV/Dev Capital
Forecast
(USD1,635/ USD1,500/oz USD1,600/oz USD1,800/oz USD2,000/oz USD2,200/oz
oz Avg)
192
140
178
255
333
411
130
95
121
173
226
276
58%
50%
1,127
76
59
330
239
48%
41%
1,113
65
48
248
181
57%
48%
1,124
73
56
307
223
72%
61%
1,145
90
73
425
305
85%
74%
1,165
107
90
543
389
98%
84%
1,184
124
107
662
470
104
104
104
104
104
104
24
31
24
34
24
32
24
28
24
25
24
24
185%
134%
171%
246%
320%
395%
125%
92%
117%
166%
217%
266%
NOTE: 1. Converted to AUD from USD using AUD:USD exchange rate of 1.333.
Theta Gold Mines Limited (“Theta Gold” or “Company”) (ASX: TGM| OTC: TGMGF) is pleased to
deliver a FS for the TGME Underground Gold Mine Project, delivering a 6.46 Mt resource @ 5.95 g/t
Au for 1.24M oz of contained gold.
Theta Gold Chairman, Mr. Bill Guy stated: “The completion of the definitive FS marks a significant
milestone achievement for Theta Gold shareholders, and brings with it the rebirth of one of South
Africa’s historical mine projects offering significant opportunities for our employees and their families
as well as the local communities within the region.
The definitive FS has confirmed the mining method, technical aspects, and the economic viability of
the 540 ktpa mining and processing operation. The stand-alone CIL plant is to be constructed in
modules using technology that enhances the design efficiency and construction of the metallurgical
plant, with the optionality to expand production capacity in the future as additional mines are
brought into production.
The definitive FS uses a base gold price of US$1,642 / oz (A$2,189 / oz) with an AISC of US$834 /oz
(A$1,112/oz), thus displaying the financial robustness of the project which delivers a capital payback
of US$99m, (A$132m) in 31 months.
Once up to 7 mines are brought into production, including Vaalhoek, Desire and Glynn’s Mines, an
annual production of 160 koz/pa will make Theta one of South Africa’s most significant, mid-tier
listed gold doré producing companies.”
[ENDS]
This announcement was approved for release by Theta Gold Mines Limited’s Board and ceases the Trading
Halt of the Company's securities on the ASX.
4
For more information, please visit www.thetagoldmines.com or contact:
Bill Guy, Chairman
Theta Gold Mines Limited
T: + 61 2 8046 7584 E: billg@thetagoldmines.com
Investor Relations
Australia: Ben Jarvis, Six Degrees Investor Relations: +61 (0) 413 150 448
Webpage: www.thetagoldmines.com
https://twitter.com/ThetaGoldMines
https://www.linkedin.com/company/thetagoldmines/
ABOUT THETA GOLD MINES LIMITED
Theta Gold Mines Limited (ASX: TGM | OTCQB: TGMGF) is a gold development company that holds a range
of prospective gold assets in a world-renowned South African gold mining region. These assets include several
surface and near-surface high-grade gold projects which provide cost advantages relative to other gold
producers in the region.
Theta Gold’s core project is located next to the historical gold mining town of Pilgrim’s Rest, in Mpumalanga
Province, some 370km northeast of Johannesburg by road or 95km north of Nelspruit (Capital City of
Mpumalanga Province). Following small scale production from 2011 – 2015, the Company is currently
focussing on the construction of a new gold processing plant within its approved footprint at the TGME plant,
and for the processing of the Theta oxide gold ore. Nearby surface and underground mines and prospects
are expected to be further evaluated in the future.
The Company aims to build a solid production platform to over 160kozpa based primarily around shallow,
open-pit or adit-entry shallow underground hard rock mining sources. Theta Gold has access to over 43
historical mines and prospect areas that can be accessed and explored, with over 6.7Moz of historical
production recorded.
Theta Gold holds 100% issued capital of its South African subsidiary, Theta Gold SA (Pty) Ltd (“TGSA”). TGSA
holds a 74% shareholding in both Transvaal Gold Mining Estates Limited (“TGME”) and Sabie Mines (Pty) Ltd
(“Sabie Mines”). The balance of shareholding is held by Black Economic Empowerment (“BEE”) entities. The
South African Mining Charter requires a minimum of 26% meaningful economic participation by the
historically disadvantaged South Africans (“HDSAs”). The BEE shareholding in TGME and Sabie Mines is
comprised of a combination of local community trusts, an employee trust and a strategic entrepreneurial
partner.
COMPETENT PERSON’S STATEMENTS
MINERAL RESOURCES
Mr. Uwe Engelmann confirms that he is the Competent Person for the TGM Mineral Resources as reported
on TGM’s Mineral Resources which is extracted from TGM’s ASX announcement dated 8 April 2021 (Initial
Maiden Underground Mining Reserve) and 25 October 2021 (TGME Project Permitting Update) available to
view at www.asx.com.au and was prepared in accordance with the guidelines of the 2012 Edition of the
Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code,
2012). Mr. Engelmann has read and understood the requirements of the JORC Code (2012).
Mr. Engelmann is a Competent Person as defined by the JORC Code, 2012, having more than five years’
experience that is relevant to the style of mineralisation and type of deposit described in this report and to
the activity for which he is accepting responsibility. Mr. Engelmann (BSc (Zoo. & Bot.), BSc Hons (Geol.),
Pr.Sci.Nat. No. 400058/08, MGSSA), is a director of Minxcon (Pty) Ltd and a member of the South African
5
Council for Natural Scientific Professions. Mr. Engelmann is a full-time employee of Minxcon (Pty) Ltd and
has reviewed this report and consents to the inclusion of the matters based on his supporting information in
the form and context in which it appears.
The information in this announcement that relates to TGM’s Mineral Resources is extracted from TGM’s ASX
announcement dated 8 April 2021 (Initial Maiden Underground Mining Reserve) and 25 October 2021 (TGME
Project Permitting Update) available to view at www.asx.com.au, and was prepared in accordance with the
guidelines of the JORC Code (2012). TGM confirms that it is not aware of any new information or data that
materially affects the information included in the original market announcement and that all material
assumptions and technical parameters underpinning the Mineral Resources estimates in the relevant market
announcement continue to apply and have not materially changed. TGM confirms that the form and content
in which the Competent Person’s findings are presented have not been materially modified from the original
market announcement.
ORE RESERVES
The information in this report relating to Ore Reserves is based on, and fairly reflects, the information and
supporting documentation compiled by Mr. Daniel van Heerden (B.Eng (Mining M.Com (Business
Management), member of Engineering Council of South Africa (Pr.Eng. Reg. No. 20050318)), a director of
Minxcon Pty Ltd and a fellow of the South African Institute of Mining and Metallurgy (FSAIMM Reg. No.
37309).
Mr van Heerden has sufficient experience that is relevant to the style of mineralisation under consideration
and to the activity being undertaken to qualify as a Competent Person as defined in the JORC Code (2012).
Mr van Heerden consents to the inclusion in the report of the matters based on his information in the form
and context in which it appears.
The information in this announcement that relates to TGM’s Ore Reserves is extracted from TGM’s ASX
announcement dated 8 April 2021 (Initial Maiden Underground Mining Reserve) and 25 October 2021 (TGME
Project Permitting Update) available to view at www.asx.com.au, and was prepared in accordance with the
guidelines of the JORC Code (2012). TGM confirms that it is not aware of any new information or data that
materially affects the information included in the original market announcement and that all material
assumptions and technical parameters underpinning the Ore Reserve estimates in the relevant market
announcement continue to apply and have not materially changed. TGM confirms that the form and content
in which the Competent Person’s findings are presented have not been materially modified from the original
market announcement.
DISCLAIMERS
This announcement has been prepared by and issued by Theta Gold Mines Limited to assist in informing
interested parties about the Company and should not be considered as an offer or invitation to subscribe for
or purchase any securities in the Company or as an inducement to make an offer or invitation with respect
to those securities. No agreement to subscribe for securities in the Company will be entered into on the basis
of this announcement.
This announcement may contain forward looking statements. Whilst Theta Gold has no reason to believe
that any such statements and projections are either false, misleading or incorrect, it does not warrant or
guarantee such statements. Nothing contained in this announcement constitutes investment, legal, tax or
other advice. This overview of Theta Gold does not purport to be all inclusive or to contain all information
which its recipients may require in order to make an informed assessment of the Company’s prospects.
Before making an investment decision, you should consult your professional adviser, and perform your own
analysis prior to making any investment decision. To the maximum extent permitted by law, the Company
makes no representation and gives no assurance, guarantee or warranty, express or implied, as to, and take
no responsibility and assume no liability for, the authenticity, validity, accuracy, suitability or completeness
of, or any errors in or omissions, from any information, statement or opinion contained in this
announcement. This announcement contains information, ideas and analysis which are proprietary to Theta
Gold.
6
FORWARD-LOOKING AND CAUSIONARY STATEMENTS
This announcement may refer to the intention of Theta Gold Mines regarding estimates or future events
which could be considered forward looking statements. Forward looking statements are typically preceded
by words such as “Forecast”, “Planned”, “Expected”, “Intends”, “Potential”, “Conceptual”, “Believes”,
“Anticipates”, “Predicted”, “Estimated” or similar expressions. Forward looking statements, opinions and
estimates included in this announcement are based on assumptions and contingencies which are subject to
change without notice, and may be influenced by such factors including but not limited to funding availability,
market-related forces (commodity prices, exchange rates, stock market indices and the like) and political,
environmental or economic events (including government or community issues, land owners, global or
systemic events). Forward looking statements are provided as a general reflection of the intention of the
Company as at the date of release of the document, however are subject to change without notice, and at
any time. Future events are subject to risks and uncertainties, and as such results, performance and
achievements may in fact differ from those referred to in this announcement. Mining, by its nature, and
related activities including mineral exploration, are subject to a large number of variables and risks, many of
which cannot be adequately addressed, or be expected to be assessed, in this document. Work contained
within or referenced in this report may contain incorrect statements, errors, miscalculations, omissions and
other mistakes. For this reason, any conclusions, inferences, judgments, opinions, recommendations or other
interpretations either contained in this announcement, or referencing this announcement, cannot be relied
upon. There can be no assurance that future results or events will be consistent with any such opinions,
forecasts or estimates. The Company believes it has a reasonable basis for making the forward looking
statements contained in this document, with respect to any production targets, resource statements or
financial estimates, however further work to define Mineral Resources or Reserves, technical studies
including feasibilities, and related investigations are required prior to commencement of mining. No liability
is accepted for any loss, cost or damage suffered or incurred by the reliance on the sufficiency or
completeness of the information, opinions or beliefs contained in this announcement.
Theta Gold undertakes no obligation to update publicly or release any revisions to these forward-looking
statements to reflect events or circumstances after today’s date or to reflect the occurrence of unanticipated
events other than required by the Corporations Act and ASX Listing Rules. Accordingly, you should not place
undue reliance on any forward-looking statement.
The Feasibility Study referred to in this announcement is based on technical and economic assessments to
support the estimation of Ore Reserves. There is no assurance that the intended development referred to will
proceed as described, and will rely on access to future funding to implement. Theta Gold Mines believes it
has reasonable grounds the results of the Feasibility Study. At this stage there is no guarantee that funding
will be available, and investors are to be aware of any potential dilution of existing issued capital. The
production targets and forward looking statements referred to are based on information available to the
Company at the time of release, and should not be solely relied upon by investors when making investment
decisions. Theta Gold cautions that mining and exploration are high risk, and subject to change based on
new information or interpretation, commodity prices or foreign exchange rates. Actual results may differ
materially from the results or production targets contained in this release. Further evaluation is required
prior to a decision to conduct mining being made. The estimated Mineral Resources quoted in this release
have been prepared by Competent Persons as required under the JORC Code (2012). Material assumptions
and other important information are contained in this release.
Cautionary Statement for the LOM Base Case – The Base Case is presented as potential upside to the Project.
However, the Base Case is supported by a significant portion of Inferred Mineral Resources. Inferred Mineral
Resources inherently have a lower level of confidence and although it would be reasonable to expect that the
majority of Inferred Mineral Resources would upgrade to Indicated Mineral Resources with continued
exploration, it should not be assumed that such upgrading will occur. The realisation of the full potential of
the Base Case as presented thus cannot be guaranteed.
7
APPENDIX A – DETAIL SUMMARY OF TGME UNDERGROUND GOLD MINE FEASIBILITY
STUDY
FS HIGHLIGHTS
Minxcon (Pty) Ltd completed a Feasibility Study for Theta Gold Mines Limited with the report finalised in July
2022 to restart the following historical underground projects situated in Mpumalanga Province, South Africa:
• Beta (including the Beta North, Beta Central and Beta South sections);
• Frankfort;
• Clewer-Dukes Hill-Morgenzon (or CDM); and
• Rietfontein.
Two scheduling strategies have been investigated, namely:
• Base Case: life of mine plan targeting the total Mineral Resources (Measured, Indicated and Inferred);
and
• Ore Reserve Plan: LOM plan targeting only Measured and Indicated Mineral Resources.
Beta is scheduled as the first operation to commence production, followed by Rietfontein, and finally CDM
and Frankfort simultaneously. Beta and Rietfontein are higher-grade mines compared to CDM and Frankfort.
The Base Case LOM plan will comprise a 12.9-year mining operation starting in 2023 and delivering
production of 1.24 million ounces of contained gold. The estimated development capital or peak funding
requirement is USD77 million (AUD102 million)7, with the Project forecast to generate a pre-tax NPV10% of
USD324 million (AUD432 million) and pre-tax Internal Rate of Return (IRR) of 65% at the forecast gold price
of averaging USD1,642/oz over the LOM. Based on these metrics, the Project has a projected payback period
of 31 months. First gold production is planned for Q2 2024.
FS KEY METRICS
Table 4: Key Project Parameters
Description
Units
Base Case
Reserve Plan
Project Start Date1
Qtr/Year
Q1 2023
Q1 2023
Commercial Production Date
Qtr/Year
Q2 2024
Q2 2024
Production build up period
Months
14
14
Life of mine
years
12.9
7.3
Underground ore mined (LOM)
Mt
6.46
2.85
Mined Grade
g/t
5.95
6.09
Gold Mined (LOM)
Moz
1.24
0.56
Production Rate
Kt/a
540
540
Production Rate
Kt/m
45
45
Grind size
µ
106
106
Gold recovered (average LOM)
%
87
87
Gold recovered (LOM)
Moz
1.08
0.49
Note: 1. Start date subject to project Finance and permitting approvals.
7
TGM is currently in discussion with debt financiers and has engaged an experienced debt advisor to assist in the negotiation of term-sheets for
funding of the Project. Further equity raises are also planned to fund working capital and part of the project capital if required, which may lead to
dilution to existing shareholders.
8
Base Case
Table 5 and Table 6 detail the Project economics of the Base Case at various price scenarios in USD terms
and AUD terms, respectively.
Table 5: Project Economics at Various Gold Prices – Base Case (USD)
Project Economics at
gold price
Forecast
(USD1,642/ USD1,500/oz USD1,600/oz USD1,800/oz USD2,000/oz USD2,200/oz
oz Avg)
USDm
324
255
304
402
501
601
Unit
NPV @ 10% (real) Pre-tax
NPV @ 10% (real) PostUSDm
tax
%
IRR (%) Pre-tax
%
IRR (%) Post-tax
USD/oz
AISC
USDm
EBITDA annual average
USDm
EBIT annual average
USDm
Free Cash Flow (Pre-tax)
Free Cash Flow (Post-tax) USDm
Development Capital –
USDm
Peak Funding
USDm
Capital Sustaining
Months
Payback post-tax
Capital Efficiency (Pre-Tax
%
NPV/Dev Capital
Capital Efficiency (Post%
Tax NPV/Dev Capital
219
174
206
269
335
400
65%
57%
834
69
60
717
508
57%
50%
822
58
49
576
412
64%
56%
831
66
57
673
478
77%
67%
847
81
72
869
611
90%
78%
862
96
87
1066
747
102%
87%
876
111
102
1264
881
77
77
77
77
77
77
37
31
37
33
37
31
37
28
37
25
37
24
422%
332%
395%
524%
653%
783%
285%
226%
268%
351%
437%
521%
Table 6: Project Economics at Various Gold Prices – Base Case (AUD)
Project Economics at
gold price
Forecast
(USD1,642/ USD1,500/oz USD1,600/oz USD1,800/oz USD2,000/oz USD2,200/oz
oz Avg)
AUDm
432
339
405
536
669
802
Unit
NPV @ 10% (real) Pre-tax
NPV @ 10% (real) PostAUDm
tax
%
IRR (%) Pre-tax
%
IRR (%) Post-tax
AUD/oz
AISC
AUDm
EBITDA annual average
AUDm
EBIT annual average
AUDm
Free Cash Flow (Pre-tax)
Free Cash Flow (Post-tax) AUDm
Development Capital –
AUDm
Peak Funding
AUDm
Capital Sustaining
Months
Payback post-tax
Capital Efficiency (Pre-Tax
%
NPV/Dev Capital
Capital Efficiency (Post%
Tax NPV/Dev Capital
292
232
274
359
447
533
65%
57%
1,112
92
80
956
678
57%
50%
1,096
77
66
768
550
64%
56%
1,107
87
76
897
638
77%
67%
1,129
107
96
1,158
814
90%
78%
1,149
128
116
1,421
996
102%
87%
1,167
148
136
1,686
1,175
102
102
102
102
102
102
49
31
49
33
49
31
49
28
49
25
49
24
422%
332%
395%
524%
653%
783%
285%
226%
268%
351%
437%
521%
NOTE:- 1. Converted to AUD from USD using AUD:USD exchange rate of 1.333.
9
Figure 2: Annual Gold Production – Base Case
Figure 3: Annual and Cumulative Cash Flow (Post-Tax) – Base Case (AUD)
NOTES:
1. Forecast Prices averaging USD1,642/oz over LOM.
2. Converted to AUD from USD at exchange rate of 1.333 AUD:USD.
Reserve Plan
Table 7 and Table 8 detail the Project economics of the Reserve Plan at various price scenarios in
USD terms and AUD terms, respectively.
10
Table 7: Project Economics at Various Gold Prices – Reserve Plan (USD)
Project Economics at
gold price
Unit
NPV @ 10% (real) Pre-tax USDm
NPV @ 10% (real) PostUSDm
tax
%
IRR (%) Pre-tax
%
IRR (%) Post-tax
USD/oz
AISC
USDm
EBITDA annual average
USDm
EBIT annual average
USDm
Free Cash Flow (Pre-tax)
Free Cash Flow (Post-tax) USDm
Development Capital –
USDm
Peak Funding
USDm
Capital Sustaining
Months
Payback post-tax
Capital Efficiency (Pre-Tax
%
NPV/Dev Capital
Capital Efficiency (Post%
Tax NPV/Dev Capital
Forecast
(USD1,635/ USD1,500/oz USD1,600/oz USD1,800/oz USD2,000/oz USD2,200/oz
oz Avg)
144
105
134
191
250
308
98
71
91
130
169
207
58%
50%
846
57
45
247
179
48%
41%
835
48
36
186
136
57%
48%
843
55
42
230
167
72%
61%
859
67
55
318
229
85%
74%
874
80
67
407
292
98%
84%
888
93
80
497
353
78
78
78
78
78
78
18
31
18
34
18
32
18
28
18
25
18
24
185%
134%
171%
246%
320%
395%
125%
92%
117%
166%
217%
266%
Table 8: Project Economics at Various Gold Prices – Reserve Plan (AUD)
Project Economics at
gold price
Unit
NPV @ 10% (real) Pre-tax AUDm
NPV @ 10% (real) PostAUDm
tax
%
IRR (%) Pre-tax
%
IRR (%) Post-tax
AUD/oz
AISC
AUDm
EBITDA annual average
AUDm
EBIT annual average
AUDm
Free Cash Flow (Pre-tax)
Free Cash Flow (Post-tax) AUDm
Development Capital –
AUDm
Peak Funding
AUDm
Capital Sustaining
Months
Payback post-tax
Capital Efficiency (Pre-Tax
%
NPV/Dev Capital
Capital Efficiency (Post%
Tax NPV/Dev Capital
Forecast
(USD1,635/ USD1,500/oz USD1,600/oz USD1,800/oz USD2,000/oz USD2,200/oz
oz Avg)
192
140
178
255
333
411
130
95
121
173
226
276
58%
50%
1,127
76
59
330
239
48%
41%
1,113
65
48
248
181
57%
48%
1,124
73
56
307
223
72%
61%
1,145
90
73
425
305
85%
74%
1,165
107
90
543
389
98%
84%
1,184
124
107
662
470
104
104
104
104
104
104
24
31
24
34
24
32
24
28
24
25
24
24
185%
134%
171%
246%
320%
395%
125%
92%
117%
166%
217%
266%
NOTE: 1. Converted to AUD from USD using AUD:USD exchange rate of 1.333.
11
Figure 4: Annual Gold Production – Reserve Plan
Figure 5: Annual and Cumulative Cash Flow (Post-Tax) – Reserve Plan (AUD)
NOTES:1.
2.
Forecast Prices averaging USD1,635/oz over LOM.
Converted to AUD from USD at exchange rate of 1.333.
PROJECT DESIGN
The TGM Underground Project aims to restart historical underground gold mines located in a historically
prolific gold mining region in the Mpumalanga Province of South Africa. The Project Areas are centred on the
town of Pilgrims Rest, some 370 km due northeast of Johannesburg, and ownership has always been vested
in TGM or its partners.
The Project targets the Beta (including the Beta North, Beta Central and Beta South sections), Rietfontein,
Frankfort and Clewer-Dukes Hill-Morgenzon (“CDM”) Mines. A
Share your feedback
Discover