TGME Gold Plant Build Accelerates – Contractors Mobilised, Ground Broken
Key Highlights
• Mobilisation Complete: Contractors and heavy equipment on site, enabling bulk earthworks to
ramp up on schedule. (See Annexure A – progress photos)
• Civil Works Commenced: Construction underway at the Carbon-in-Leach (CIL) section and
associated retaining walls.
• Supplier Engagement: Negotiations advancing with long-lead equipment suppliers for mills and
crushing circuits.
• Workforce Growth: 50+ locals trained and 120+ personnel now on site. Full-scale operations
will create 500+ jobs, powered by global best practice AI-driven training.
• Strong Financial Position: Recent capital raises and convertible loan conversions have
strengthened the balance sheet, supporting civil works and debt syndication process.
• Clear Path to Production: Targeting Q1 2027, Plant commissioning targeted for end-2026.
Figure 1: TGME Project - Breaking New Ground
Theta Gold Mines Limited (ASX: TGM, the “Company”) has reached a significant milestone at its TGME
Gold Mine Project. All contractors and equipment are now fully mobilised, enabling bulk earthworks to
ramp up on schedule. Heavy machinery is shaping the site for major infrastructure, while civil works
have commenced at the Carbon-in-Leach (CIL) section and retaining walls, critical steps toward building
a robust, efficient processing plant.
2
Comments by the Executive Chairman, Bill Guy:
“Bulk earthworks are in full swing, and initial civil works have commenced — rapid progress continues
on site (see Annexure A). We’ve also advanced negotiations with long-lead suppliers for mills and
crushing circuits, all of whom bring proven gold-processing expertise.”
“Contractors and equipment are now fully mobilised, and site earthworks are underway - accelerating
the transformation of this historic site into a modern gold producer.”
“Recent capital raises and convertible loan conversions have strengthened our balance sheet, positioning
us to complete civil works and advance debt syndication. With funding and construction aligned, we
remain firmly on track to commission the plant by the end of 2026. We thank our long-term shareholders
for their continued support as we move toward production “.
[ENDS]
This announcement was approved for release by Theta Gold Mines Limited’s Board.
For more information, please visit www.thetagoldmines.com or contact:
Bill Guy (Chairman): T: + 61 2 8046 7584 E: billg@thetagoldmines.com
Richie Yang (Executive Director): E: richiey@thetagoldmines.com
Investor Relations
We’re committed to keeping you informed and involved. Download the Engage IR App today
and join the conversation.
Webpage: www.thetagoldmines.com
https://twitter.com/ThetaGoldMines
https://www.linkedin.com/company/thetagoldmines/
3
Annexure A- Picture Gallery
Figure 2: First Stage TGME Gold Plant (Plan View)
Figure 3: Aerial View of Plant Footprint Progress
4
Figure 4: Earthworks on Platform 2
Figure 5: Steel reinforcing being delivered
5
Figure 6: Earthworks on Platform 4
Figure 7: Earthworks on Platform 2
6
Figure 8: 21/10/2025 General Site Overview
Figure 9: Safety toolbox meeting before starting work
ABOUT THETA GOLD MINES LIMITED
Theta Gold Mines Limited (ASX: TGM) is a gold development company that holds a range of prospective
gold assets in a world-renowned South African gold mining region. These assets include several surface
and near-surface high-grade gold projects, which provide cost advantages relative to other gold
producers in the region.
Theta Gold’s core project is located next to the historical gold mining town of Pilgrim’s Rest, in
Mpumalanga Province, some 370km northeast of Johannesburg by road or 95km north of Nelspruit
(Capital City of Mpumalanga Province). Following small-scale production from 2011 – 2015, the
Company is currently focusing on the construction and financing of a new gold processing plant within
its approved footprint at the TGME plant.
7
TGM holds 100% of Theta Gold SA (Pty) Ltd, which in turn owns 74% of TGME and Sabie Mines, meeting
Black Economic Empowerment (BEE) ownership standards as per South African Mining Charter
requirements.
DISCLAIMER
This announcement has been prepared by and issued by Theta Gold Mines Limited to assist in informing
interested parties about the Company and should not be considered as an offer or invitation to
subscribe for or purchase any securities in the Company or as an inducement to make an offer or
invitation with respect to those securities. No agreement to subscribe for securities in the Company will
be entered into on the basis of this announcement.
This announcement may contain forward looking statements. Whilst Theta Gold has no reason to
believe that any such statements and projections are either false, misleading or incorrect, it does not
warrant or guarantee such statements. Nothing contained in this announcement constitutes
investment, legal, tax or other advice. This overview of Theta Gold does not purport to be all inclusive
or to contain all information which its recipients may require in order to make an informed assessment
of the Company’s prospects. Before making an investment decision, you should consult your
professional adviser, and perform your own analysis prior to making any investment decision. To the
maximum extent permitted by law, the Company makes no representation and gives no assurance,
guarantee or warranty, express or implied, as to, and take no responsibility and assume no liability for,
the authenticity, validity, accuracy, suitability or completeness of, or any errors in or omissions, from
any information, statement or opinion contained in this announcement. This announcement contains
information, ideas and analysis which are proprietary to Theta Gold.
Share your feedback
Discover