Quarterly Activities & Cashflow Report - 31 March 2026
Released
Released
Announcement PDF
Theta Gold Mines Limited ACN 131 758 177
Registered Office: Level 35, One International Towers, 100 Barangaroo Avenue
Sydney, NSW 2000, Australia
30 April 2026
ASX ANNOUNCEMENT AND MEDIA RELEASE
(ASX: TGM)
QUARTERLY REPORT
1 January 2026 to 31 March 2026
Theta Gold Mines Limited ("Theta", “TGM” or the "Company") (ASX: TGM) is pleased to report on
its activities for the quarter ended 31 March 2026.
During the March 2026 quarter, Theta advanced its flagship gold project, the TGME Gold Project
(‘Project’), through the release of a Revised Feasibility Study, confirming a 13.1-year Life of Mine (LOM)
and positioning it as a high-margin, long-life gold operation in one of the world’s premier gold regions.
Bulk earthworks, civil works, water infrastructure and gold room foundations progressed Key
delivery-critical contracts were secured while the on-site workforce expanded with a strong local
employment focus. Project costs remained within budget and funding capacity was strengthened
through secured equity and ongoing discussions with debt funders.
Highlights:
During the March 2026 Quarter:
• Revised Feasibility Study released – confirming project economics, mine life and a clear path
to production.
• Construction progressed - bulk earthworks, civil works, water infrastructure, platforms and gold
room foundations advancing across site.
• TGME Gold Project team - expanded as recruitment of operational staff ramps up.
• Structural steel, mechanical and piping contracts were executed - with industry leaders PICM
and RM Process, supporting the next phase of plant construction.
• Manufacturing contract for crushing and screening plant awarded - to NMS Africa, securing a
critical long‑lead item.
• Equity funding totalling A$10.3 million (US$7 million) - was completed (before costs),
strengthening near‑term funding certainty.
• Strong operational performance was maintained - all engineering inspections and concrete
strength tests meeting project specifications.
• The debt syndication process progressed - construction capital funding discussions ongoing with
debt financiers.
• Conversion of Convertible Loans – A$7.8 million ( ̴ US$5.2 million) of Convertible Loans
extinguished by conversion to Shares issued to Convertible Lenders.
• Local workforce participation remained strong - over 70% of non‑specialist roles sourced from
nearby communities and more than 500 jobs expected at full production.
• The project remained within budget - clear visibility to first gold and continued progress across
critical path activities.
• Executive Chairman Bill Guy - represented the Company at the 121 Mining and Indaba Mining
Conference in Cape Town during February 2026
Upcoming Conferences -TGM Executive Chairman, Bill Guy will be presenting at RIU Resources Sydney
(5-7 May 2026).
2
FEASIBILITY STUDY BASE CASE HIGHLIGHTS:
Key operational results of the Revised Feasibility Study (FS):
❖ Production Start: Q1 2027 (TGME Gold Plant currently under construction)
❖ Head Grade LoM: 4.96g/t Base Case
❖ Base Case - Production: 871 Koz 4.28 g/t recovered grade (86.2% recovery)
❖ Base Case - Production: 1.06 Moz @ 4.40 g/t mined grade
❖ Production Ramp-up: Peak Production over 115 koz
❖ Ore Reserve Plan: 514 koz @ 4.11 g/t recovered grade (85.2% recovery)
❖ Gold plant: Plant construction underway
❖ Infrastructure: Existing surface/underground works, permitting in place
Robust Base Case Financials: (Gold price (avg) US$2,884/oz, (A$4,3651
/oz)) (Update 7 October
2025)
❖ Free Cashflow: US$0.9 billion, (A$1.4 billion)
❖ Post-tax NPV10%: (at a 10% discount rate) of US$455 m, (A$689 m)
❖ Revenue: US$2.5 billion, (A$3.8 billion)
❖ Post-tax IRR: 77%
❖ Life of Mine (LOM): 13.1 years
❖ All in sustaining cost: US$1,181/oz, (A$1,787/oz)
❖ Project payback: 29 months (from start of mining)
❖ Peak funding: US$77 m, (A$116 m)
Revised TGME Gold Project Feasibility Study
Independent Mining Engineers, Minxcon Pty Ltd (Minxcon) completed a revised Feasibility Study (FS) to
restart the historical TGME Underground Gold Mine Project in South Africa. As the original authors of
the 2022 FS, Minxcon bring deep familiarity with the asset. The revised FS reflects a conservative base
case gold price of US$2,884/oz — despite spot prices now exceeding US$4,500/oz — and unlocks
significantly enhanced economics.
Figure 1 TGME Gold Mine Project Site - April 2026
1 Exchange rate USD:AUD applied in relation to revised DFS was 0.6606.
3
Table 1: Project Economics at Various Gold Prices – Base Case (AUD)
Project Economics at AU$
Gold Price
Unit
Forecast
(USD2,884 /
oz Avg)
USD
2,500/oz
USD
3,000/oz
USD
3,500/oz
USD
4,000/oz
USD
4,500/oz*
USD
5,000/oz
Gold Price AUD / oz2
AUD/oz 4,365 3784 4,541 5,298 6,055 6,812 7,568
NPV @ 10% (real) Pre-tax AUDm 991 758 1,070 1,382 1,695 2,008 2,321
NPV @ 10% (real) Post-tax AUDm 689 526 742 954 1,166 1,379 1,591
IRR (%) Pre-tax % 84% 69% 86% 102% 117% 131% 146%
IRR (%) Post-tax % 77% 63% 78% 92% 105% 118% 130%
AISC AUD/oz 1,787 1750 1,800 1,848 1,896 1,943 1,990
EBITDA annual average AUDm 163 131 175 219 263 307 351
EBIT annual average AUDm 148 116 160 204 248 292 336
Free Cash Flow (Post-tax) AUDm 1,413 1102 1,525 1,941 2,358 2,775 3,193
Development Capital – Peak
Funding
AUDm 116 131 116 116 116 116 116
Capital Sustaining AUDm 65 65 65 65 65 65 65
Payback post-tax Months 29 34 30 27 25 24 23
Capital Efficiency (Pre-Tax
NPV/Dev Capital
% 855% 580% 924% 1,194% 1,463% 1,734% 2,004%
Capital Efficiency (Post-Tax
NPV/Dev Capital
% 595% 403% 641% 824% 1,007% 1,190% 1,374%
* Note: at the time of release of this study, Spot Gold Price was trading in excess of $US4,500 / oz.
The Base Case Production Target and forecast financial information shown above and disclosed in this study are based on Mineral
Resources that include a proportion of Inferred Mineral Resources and the realisation of the full potential of the Base Case as
presented cannot be guaranteed. Inferred Mineral Resources are considered too speculative geologically to have the economic
considerations applied to them that would enable them to be classified as Ore Reserves. There is no certainty that further
exploration work or evaluation studies will result in the conversion of Inferred Mineral Resources to Indicated or Measured
Mineral Resources or Ore Reserves.
Table 2: Comparison of Base Case Financial Metrics – Feasibility Studies 2022 vs 2026
Project Economics at Gold Price US$
(Base Case)
Unit FS - Jul’ 223
FS - *Feb’ 26 % or Absolute
Life of Mine years 12.9 13.1 flat
Revenue USDbn 1.75 2.49 42%
Gold Price USD/oz 1,642 2,884 +1,242/oz
NPV @ 10% (real) Pre-tax USDm 324 654 102%
NPV @ 10% (real) Post-tax USDm 219 455 108%
IRR (%) Pre-tax % 65% 84% 29%
IRR (%) Post-tax % 57% 77% 35%
All In Sustaining Cost (AISC) USD/oz 834 1,181 42%
EBITDA (LoM) USDm 891 1,508 69%
EBITDA annual average USDm 69 115 67%
Free Cash Flow (Post-tax) USDm 508 933 84%
Development Capital – Peak Funding USDm 77 77 flat
Capital Sustaining USDm 37 44 7
Payback Post-tax Months 31 28 flat
Due to rounding, numbers presented throughout this document may not add up precisely to the totals provided and percentages may not
precisely reflect the absolute figures.
* - Mine Plan revised
2
Exchange rate USD:AUD applied throughout this document relating to the revised feasibility study is 0.6606.
3 Ref to ASX Release dated 27 July 2022 titled, “Theta Gold’s TGME Project DFS confirms NPV of AUD432 Million”.
Key Assumptions: Long term average spot gold price of US$2,884 applied in Base Case scenario over LOM / AISC estimation of US$1,181/oz at
+/- 15% level of accuracy.
4
Cost Control/Value Focus:
TGM continues to deliver strong project execution and disciplined cost management. The TGME Project’s
post-tax value has surged to US$455 million—an impressive US$236 million uplift over the 2022 FS—
driven largely by higher gold prices. This pricing strength has unlocked the ability to profitably mine
lower-grade ore.
Project Summary:
The TGME Gold project, located in the Mpumalanga province of South Africa, is shown below.
Figure 2: TGME Gold Project Location Map
5
Two mine scheduling strategies have been investigated, namely:
• Base Case: LOM Plan includes a Production Target of 1.01 Moz targeting Measured, Indicated and
Inferred Mineral Resources; and
• Ore Reserve Plan: LOM Plan includes a Production Target of 604 koz targeting Measured and
Indicated Mineral Resources only.
The FS completed only includes the first of four mines out of a historical 43 mines that the company
will look to bring online, including:
• Beta;
• Frankfort;
• Clewer-Dukes Hill-Morgenzon (“CDM”); and
• Rietfontein.
Table 3: Base Case – Diluted Mineral Resource in Mine Plan
Mineral Resource
Classification
Tonnes Grade Au Content
kt g/t kg koz
Beta
Measured - - - -
Indicated 1,541 7.57 11,657 375
Inferred 1,044 5.53 5,773 186
Rietfontein
Measured - - - -
Indicated 500 7.99 3,998 129
Inferred 625 8.13 5,087 164
Frankfort
Measured 54 4.30 233 8
Indicated 251 3.93 984 32
Inferred 252 3.42 864 28
CDM
Measured - - - -
Indicated 278 2.52 700 23
Inferred 141 2.35 331 11
TGM Plant TSF
Measured - - - -
Indicated 1,210 0.97 1,171 38
Inferred - - - -
TGM Rock Dumps
Measured - - - -
Indicated - - - -
Inferred 443 1.45 643 21
Combined
Measured 54 4.30 233 8
Indicated 3,779 4.90 18,510 595
Inferred 2,506 5.07 12,699 408
Total 6,339 4.96 31,443 1,011
Notes:
1. A Mineral Resources inventory cut-off of 170 cm.g/t has been applied for the Beta Mine.
2. A Mineral Resources inventory cut-off of 150 cm.g/t has been applied for the Frankfort Mine.
3. A Mineral Resources inventory cut-off of 121 cm.g/t has been applied for the CDM Mine.
4. A Mineral Resources inventory cut-off of 160 cm.g/t has been applied for the Rietfontein Mine.
The process plant sits at the heart of Pilgrim’s Rest, a region steeped in gold mining history and home
to a skilled local workforce, just 370 km northeast of Johannesburg. Centrally located, the plant is only
2.5 km from Pilgrim’s Rest township, with Beta Mine just 1.3 km to the west, Frankfort and CDM 24 km
and 6.3 km north, and Rietfontein 21 km south-southeast—ensuring efficient ore delivery from all key
deposits.
6
Key Project Components:
• The Mineral Resource4
in the Base Case LoM Plan of 1,010 koz of gold now includes an additional
58koz (109koz available) of surface ore from historic rock dumps and MR83 tailings storage facility
(TSF) which was previously never recognised in the mining plan and provides early cashflow
opportunities.
• Phase 1 launches with four mines—Beta, Frankfort, CDM, and Rietfontein—leveraging the skilled
mining workforce of Pilgrim’s Rest and Sabie, 370 km northeast of Johannesburg.
• Over 43 historical mines underpin a long-term growth pipeline, with 3.6 Moz of Inferred Resources
available for future development—none included in the current Base Case.
• Execution-ready: Front-End Engineering Design (FEED) is complete, supporting modular expansion.
The plant build will use modular, plug-and-play equipment, significantly reducing construction risk
and enabling faster, more reliable commissioning.
• Site works underway: Old plant decommissioned; contracts for earthworks, civils, roads, and water
management signed in September 2025.
• Multi-phase ramp-up: Production will build to 45 ktpm across underground operations, following the
FS Base Case plan (Measured, Indicated, and Inferred Resources).
Beta Mine leads off: Mining starts with 18 months of pre-development at Beta before stoping begins.
• Phase 1 entails the initial 13.1-year Base Case LOM plan at the processing rate of 540 ktpa with key
physical parameters including;
o Gold ore production build up to 45 ktpm, for the first 18 months will be from the initial 109K
oz of surface ore contained in historical rock dumps and tailings to provide early cashflow
while underground mine development is completed;
o First underground gold within 18 months of development from Beta Mine;
o Free-milling stand-alone processing plant, with doré produced on site to produce 90 –
120Koz p.a. @ 4.28 g/t recovered gold – at 86.2% gold recovery rate;
o First gold production is scheduled for Q1, 20275
;
o Gold plant expected to produce over 80koz/pa by the third year of production;
o Recommissioning of existing on-site Tailings Storage Facility (TSF);
o Base Case LOM plan outlines a recovery of 871 Koz gold from 1.01 Moz mined;
o Over 3 Moz of Inferred Mineral Resources available for future development are not included
in the Base Case LOM plan.
4 Including Inferred Resources.
5 First gold produced timing will be subject to securing funding, obtaining all necessary regulatory permitting approvals and mitigating any
weather-related interruptions.
7
Key FS Economic Results:
Under average gold prices of US$2,884 / oz (A$4,3656
/ oz), the Base Case scenario of FS demonstrates
strong financial returns7
(based on LOM plan), including:
o Undiscounted free cash flows of US$0.9 billion (A$1.4 billion), pre-tax US$1.3 billion (A$2.0
billion);
o NPV (at a 10% discount rate) of US$455 million (A$689 million), pre-tax US$654 million
(A$991 million);
o Capital payback period of 29 months;
o Post-tax IRR of 77%; pre-tax IRR of 84%
o Combined Underground Projects have an AISC of US$1,181/oz (A$1,787/oz); and
o Peak Capital requirement is US$77 million (A$116 million)8
, total initial capital US$102
million (A$154 million)9
.
Table 4: Key Project Metrics
Description Units Base Case Reserve Plan
Project Start Date1
Qtr/Year Q4 2025 Q4 2025
Commercial Production Date Qtr/Year Q1 2027 Q1 2027
Life of mine years 13.1 8.8
Underground ore mined (LOM) Mt 4.69 2.71
Surface ore remined (LoM) Mt 1.65 1.19
Mined Grade g/t 4.96 4.82
Gold Mined (LOM) Moz 1.01 0.60
Production Rate Kt/a 540 540
Production Rate Kt/m 45 45
Gold recovered (average LOM) % 86.2 85.2
Gold recovered (LOM) Moz 0.87 0.51
Strong Upside options:
• Phase 2 unlocks scale: 7 mines, 90 ktpm processing, and up to 160 koz/year gold output within
five years .
• Growth runway secured: 40 nearby historical mines and defined exploration targets offer
substantial resource upside.
• Low-cost mining advantage: All current reserves and LOM material hosted in shallow orebodies
(<400m).
• Cost discipline embedded: Competitive pricing achieved through active tendering of mine
services across South Africa.
• Built for sustainability: ESG-focused design reduces energy use, broadens workforce diversity,
and attracts green-aligned suppliers.
6 Exchange rate USD:AUD applied throughout this document in relation to the revised DFS is 0.6606.
7 Financial returns applying the ‘Base Case’ scenario statistics.
8 TGM is currently in discussion with debt financiers and has engaged an experienced debt advisors to assist in the negotiation of term-sheets for
funding of the Project. Further equity raises are also planned to fund working capital and part of the project capital if required, which may lead
to dilution to existing shareholders.
9 The FS demonstrates that post to Peak Funding, the balance of Total Capital requirement will be self-funded from project cashflow. The board
may however, consider external funding solutions such as via equity, debt, gold pre-sales, gold-streaming or a mixture of these methods.
8
Project Execution Strategy and Plan:
The project will ramp up in phases, targeting an initial Phase 1 Run-Of-Mine (RoM) output of 45 ktpm from
multiple underground mines. This staged approach is underpinned by the FS Base Case, leveraging
Measured, Indicated, and Inferred Resources to maximise early production and flexibility.
In order to achieve this, mining operations are planned to commence as follows:
• Beta Mine - Beta Mine will kick off with 18 months of pre-development, followed by stoping from
month 19. In the Base Case, the mine is expected to deliver around 30 ktpm of stoping ore for
8.5 years, within a total Life of Mine of 10.1 years.
• Rietfontein Mine - Rietfontein Mine will start mining in 18 months after Beta, stoping after eight
months of pre-development. Stoping begins in month 27, with plans to produce 15 ktpm of ore.
• Frankfort and CDM Mines - Frankfort and CDM Mines will begin mining in months 104 and 90,
with 16 and 19 months of pre-development planned, respectively. Frankfort is set to produce 15
ktpm, feeding a DMS plant that delivers 9.5 ktpm. CDM will also produce 15 ktpm at steady state.
Mining of the historic rock dumps and TGM Plant TSF will beginin months 7 and 16, respectively, following
the start of operations. The Waste Rock Dump will be mined over 10 months at 45 ktpm, enabling a
smooth ramp-up of Beta’s operations. TSF material will feed the plant for 4 months during ramp-up and
continue as needed, with a total retreatment life of 79 months.
Figure 3: Annual and Cumulative Cash Flow (Post-Tax) – Base Case (AUD)
NOTES:
1. Forecast Prices averaging USD2,884/oz over LOM.
2. Converted to AUD from USD at exchange rate of 1.514 AUD:USD.
9
Figure 4: Annual Gold Production – Base Case
TGME Site Construction Update
Site photographs below capture progress across civil and concrete works undertaken during the quarter,
including foundations and structural elements. These works represent key milestones in the ongoing
construction programme.
Figure 5: Concrete Pumping - Gold Room Figure 6 : Thickener Tank foundations in progress
Figure 7: Gold Room Wall Progress – formwork removal Figure 8: Tower Crane delivered to site
10
Crushing and Screening Plant
A manufacturing contract for a crushing and screening plant with NMS Africa (Pty) Ltd (“NMS”), was
signed this quarter a critical step toward first gold and early cashflows.
The contract covers the manufacture of a three-stage crushing and screening plant designed to meet
initial production requirements, while allowing for future expansion as the project scales. The plant
includes ore feed, primary, secondary and tertiary crushing, plus screening circuits. With a 125-day
delivery lead time, this long-lead item is now locked in, further reducing execution risk and keeping the
TGME Gold Project on track.
TGM management concluded vendor inspections with NMS and process engineers ahead of contract
award, shown below:
Figure 9 : NMS plant inspection (TGM: COO: Jacques Du Triou, ED: Richie Yang; RM Processing: Rogan Roulstone,
Alan Phillips)
Structural Steel, Mechanical Components and Piping (SMPP)
Theta signed SMPP contracts with industry leaders PICM and RM Process. The SMPP contracts cover
structural steel, mechanical components and piping.
• Modular: All steelworks fabricated are completed off-site at PICM’s facilities. This approach
streamlines transportation and on-site installation, reducing risk and accelerating timelines.
• Cost Savings: PICM and RM Process teams already on site, busy with earthworks and civils,
synergy savings targeted.
• Equipment: Mobile and stationary cranes purchased to assist with construction work.
11
Funding and Finance Update
Reduction of ̴ A$7.8 Million of Convertible Loans to Strengthen Balance Sheet
Extinguishment of ̴ A$7.8 million of Convertible Loans through the issue of 44,029,575 fully paid ordinary
shares (Convertible Lender Shares) along with 10,000,000 unlisted options (Convertible Lender Options).
The Convertible Lender Shares and Options were issued following the agreement of the Convertible
Lenders to convert the outstanding principal and interest totalling ̴A$7.8 million on 20 October 2025
reducing liabilities on the balance sheet.
The Convertible Lender Shares were converted at the exercise price of $0.17647 (which represented 85%
of the 10-day VWAP of the 10-trading day period prior to the conversion notice been received). The
Convertible Lender Options will have an exercise price of A$0.32 (32 cents) and expiry date being 18
months from the date of grant.
Completion of Placements - Tranche Three Cornerstone Investors and Director Participation
The Company advised on 13 February 202610
that it had completed US$7 million, (A$10.3 million) of
funding as part of equity funding announcements released on 711
and 2112
October 2025 and has issued
66,184,225 new fully paid ordinary shares and granted 27,808,499 attaching unlisted options, all of which
will be held in voluntary escrow for a period of 24 months from the date of issue.
The breakdown of the issues were as follows:
• Tranche Three – Cornerstone Investors: US$6 million, (A$8.8 million) completed with US$3 million
received in December 2025 with the remaining US$3 million received in February 2026 from
Cornerstone Investors - Hongkong Ruihua Investment Management Limited and private investor
Jingsha Diao who each subscribed for shares via Subscription Agreements. As a result, the
Company has issued 56,469,40413
new fully paid ordinary shares (Tranche Three Shares) at the
issue price of A$0.155 (15.5 cents) per share along with 23,726,64114
unlisted attaching options
(Tranche Three Options).
The Tranche Three Options have an exercise price equal to the higher of (i) 80% of the 10-day
VWAP for shares traded on ASX in the 10 trading days immediately preceding to exercise of the
option or (ii)A$0.155 cents and have an expiry date of 10 October 2027.
• Director Participation: US$1 million, (A$1.5 million) completed following the receipt of US$1
million late in 2025 from Non-Executive Director, Mr Brett Tang, through his associated company
NC New Energy Limited. As a result, the Company has now issued in February 2026 9,714,82115
new fully paid ordinary shares (Director Shares) as the issue price of A$0.155 (15.5 cents) and
granted 4,081,85816
unlisted options (Director Options). Terms of the Directors Options are the
same as the Tranche Three Options above.
10 Refer to ASX Release dated 13 February 2026 titled, “Completion of Tranche Three to Cornerstone Investors + Director Participation”.
11 Ref to ASX Release dated 7 October 2025 titled, “TGM secures total ~A$51.4m debt and equity to advance TGME Gold Mine Project”.
12 Ref to ASX Release dated 21 October 2025 titled, “Additional US$6m (~A$9.3m) Private Placement Secured and Full Conversion of
Convertible Loans Proposed”.
13 The number of Tranche Three Shares issued was calculated by converting the USD:AUD using the RBA rate on the date the funds were
receipted.
14 Cornerstone Investors received 1 unlisted option for every 2.38 shares they subscribed for under the subscription agreement.
15 The number of Director Shares issued was calculated by converting the USD:AUD using the RBA rate on the date the funds were receipted.
16 The Director received 1 unlisted option for every 2.38 Director Shares subscribed for under the subscription agreement.
12
Commercial Lender’s Syndication Close to Completion
TGM has advanced debt syndication process with lenders with Legal and technical due diligence
significantly advanced. The Company is confident that it will be able to conclude discussions with a
suitable funder by Q2 2026.
Upon closing of a debt facility with a lender, TGM will be fully-funded which will allow the Company to
complete the construction and commissioning phase of the TGME Gold Processing Plant.
The Company will continue to provide updates with regards to due diligence progress or terms with
debt funders.
Cash Position
As of 31 March 2026, the Group had US$10.7 (A$15.6) million in cash.
In accordance with ASX Listing Rules 5.3.1 and 5.3.2, the Company provides the following summary of
expenditures incurred during the Quarter:
Mining exploration costs (including exploration labour) US $ -
Mining Production and Development Costs US $ 4,051,112
Licence to Operate Costs US $ 88,763
Total US $ 4,139,875
The Company’s Quarterly Appendix 5B reported US$118,000 in payments to related parties and their
associates, as noted in the Appendix 5B this payment was for directors' fees and consulting fees.
Capital Structure
The current capital structure of the Company at 31 March 2026 is as follows:
Number
Fully paid ordinary shares (ASX: TGM) 1,156,766,199
Listed /Unlisted options and performance rights (see “Annexure C”) 283,607,306
The estimated market capitalisation of TGM was A$242.92 million17
(US$166 million) as at 31 March
2026.
[ENDS]
This announcement was approved for release by Theta Gold Mines Limited’s Board.
For more information, please visit www.thetagoldmines.com or contact:
Bill Guy, Chairman
Theta Gold Mines Limited
T: + 61 2 8046 7584 E: billg@thetagoldmines.com
17 Calculated as 1,156,766,199 fully-paid ordinary shares on issue at the closing price of AU$0.21 cents per share as at 31 March 2026
converted at the RBA exchange rate of AUD:USD of 0.6845.
13
Investor Relations and Media Communications
We’re committed to keeping you informed and involved. Sign up for the Engage IR App and
Investor Hub today and join the conversation.
Webpage: www.thetagoldmines.com
https://twitter.com/ThetaGoldMines
https://www.linkedin.com/company/thetagoldmines/
14
Figure 10 Stationary Crane now fixed in place at site for construction and maintenance
15
Competent Persons Statement
MINERAL RESOURCES
Mr. Uwe Engelmann confirms that he is the Competent Person for the TGM Mineral Resources as
reported on TGM’s Mineral Resources which is extracted from TGM’s ASX announcement dated 8 April
2021(Initial Maiden Underground Mining Reserve) available to view at www.asx.com.au and was
prepared in accordance with the guidelines of the 2012 Edition of the Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves (JORC Code, 2012). Mr. Engelmann has read
and understood the requirements of the JORC Code (2012).
Mr. Engelmann is a Competent Person as defined by the JORC Code, 2012, having more than five years’
experience that is relevant to the style of mineralisation and type of deposit described in this report and
to the activity for which he is accepting responsibility. Mr. Engelmann (BSc (Zoo. & Bot.), BSc Hons (Geol.),
Pr.Sci.Nat. No. 400058/08, FGSSA), is a director of Minxcon (Pty) Ltd and a member of the South African
Council for Natural Scientific Professions. Mr. Engelmann is a full-time employee of Minxcon (Pty Ltd and
has reviewed this report and consents to the inclusion of the matters based on his supporting information
in the form and context in which it appears.
METALLURGICAL RESULTS
Mr. Rogan Roulstone confirms that he is the Competent Person in terms of Mineral Resources and Ore
Reserves (JORC Code, 2012). Mr. Roulstone has read and understood the requirements of the JORC Code
(2012).
Mr. Roulstone is a Competent Person as defined by the JORC Code, 2012, having more than five years’
experience that is relevant to gold extraction and in particular gold extraction from a refractory ore body.
Mr Roulstone is a Chemical Engineering (NHD) that graduated in 1993 and is member of the SAIMM
(705817). Mr Roulstone is the managing director of RM process and has over nine years’ experience on
the TGME process plant design.
The information in this announcement that relates to TGM’s Mineral Resources is extracted from TGM’s
ASX announcement dated 8 April 2021 (Initial Maiden Underground Mining Reserve) available to view at
www.asx.com.au and was prepared in accordance with the guidelines of the JORC Code (2012). TGM
confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcement and that all material assumptions and technical
parameters underpinning the Mineral Resources estimates in the relevant market announcement
continue to apply and have not materially changed other than as disclosed in TGM’s ASX announcement
dated 25 October 2021 regarding the TGME Project Permitting Update. TGM confirms that the form and
content in which the Competent Person’s findings are presented have not been materially modified from
the original market announcement.
ORE RESERVES
The information in this report relating to Ore Reserves is based on, and fairly reflects, the information
and supporting documentation compiled by Mr. Daniel van Heerden (B.Eng (Mining M.Com (Business
Management), member of Engineering Council of South Africa (Pr.Eng. Reg. No. 20050318)), a director
of Minxcon (Pty) Ltd and a fellow of the South African Institute of Mining and Metallurgy (FSAIMM Reg.
No. 37309).
Mr Van Heerden has sufficient experience that is relevant to the style of mineralisation under
consideration and to the activity being undertaken to qualify as a Competent Person as defined in the
JORC Code (2012). Mr van Heerden consents to the inclusion in the report of the matters based on his
information in the form and context in which it appears.
The information in this announcement that relates to TGM’s Ore Reserves is extracted from TGM’s ASX
announcement dated 8 April 2021 (Initial Maiden Underground Mining Reserve) available to view at
www.asx.com.au and was prepared in accordance with the guidelines of the JORC Code (2012). TGM
confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcement and that all material assumptions and technical
16
parameters underpinning the Ore Reserve estimates in the relevant market announcement continue to
apply and have not materially changed other than as disclosed in TGM’s ASX announcement dated 25
October 2021 regarding the TGME Project Permitting Update. TGM confirms that the form and content
in which the Competent Person’s findings are presented have not been materially modified from the
original market announcement.
About Theta Gold Mines Limited
Theta Gold Mines Limited (ASX: TGM) is an advanced gold development company focused on unlocking
value from its extensive suite of projects in South Africa’s renowned Eastern Transvaal goldfields. The
Company’s flagship TGME Gold Project offers near surface and shallow underground ore bodies with
compelling cost advantages, with 6.1m Oz’s of gold Resource.