2024 Annual Report
Released
Released
Announcement PDF
GOLD MINES
A N N UA L R E P O RT 2 0 2 4
CONTENTS
Chairman’s Letter
2
Significant Milestones Achieved in 2024
3
Review of Operations
4
FY24 Highlights
5
Theta’s TGME Underground Gold Mine Definitive
Feasibility Study (FS)
12
Environment, Social and Governance (ESG)
22
Ore Reserve and Mineral Resource Statement
31
Disclaimer’s
34
Corporate Governance Statement
37
Directors’ Report
42
Remuneration Report
53
Directors’ Declaration
61
Consolidated Entity Disclosure Statement
62
Auditor Independence Declaration
63
Financial Statements
64
Independent Auditor’s Report
101
Shareholder Information
106
Directory
108
1
THETA GOLD MINES LIMITED | ANNUAL REPORT 2024
CHAIRMANS
LETTER
Dear Fellow Shareholders,
On behalf of the Board of Directors, I am pleased
to present the 2024 Annual Report for Theta Gold
Mines Limited (ASX: TGM). The Company has made
significant progress over the last twelve months.
The company is advancing the TGME Underground
project on the ground. The team is on-site completing
execution documentation and final design for the gold
plant build process.
RM Process and Eco Elementum have been
appointed to complete the final designs for the plant,
tailings, and water management. They assist Theta
and Power China in compliance with local regulations.
RM Process, a South African-based process
engineering company, will assist with the Final
designs of the TGME Gold Plant and will form part of
the execution team with Theta and Power China.
The Eco Elementum group of companies provides
an array of independent, multidisciplinary, and
integrated environmental science, engineering, and
construction services. Eco Elementum will assist with
the final designs of water management systems and
assist the design team in environmental and legal
compliance with the Water Use Licence
During the year, the company has also examined
tailings and rock dumps with high gold prices. With
the 174,000 oz of gold sitting on the surface, the
company has been examining ways to accelerate the
path to gold production.
Theta selected Power China subsidiary as the
preferred EPC partner to build stage one of its
TGME Gold Plant and TSF facilities estimated at
US$30 million1.
In July 2022, the Company completed a FS for the
first four mines Beta, CDM, Frankfort and Rietfontein
(TGME Underground Gold Project). The Base Case life
of mine (LOM) plan will comprise a 12.9-year mining
operation starting in 2024 to deliver production
of 1.24 million ounces of contained gold. Peak
production is expected to be over 100,000 ounces
per year. By adding the fourth mine Rietfontein to
the mining schedule, there has been a significant
scale-up from the April 2021 pre-feasibility study
with a production rate of just above 60,000 ounces
per annum.
Underground mining will deliver higher-grade ore to
the gold plant with a much smaller environmental
footprint that’s well supported by the local
community and key stakeholders, with access to
a larger resource base of 4.5 million ounces of
underground mineral resources.
Environment, Social and Governance (ESG) The
Company’s focus remains to work closely with our
stakeholders and communities to strengthen the
existing relationships and, to establish a mutually
beneficial relationship that is healthy and sustainable.
The TGME Stakeholder Forum continues to gain good
momentum with open and honest communications
between all parties.
Theta is also developing an Ecological Compensation
Programme. Independent Environmental Scientist
has been requested to provide us with a proposal
to develop a guideline for the execution of the
compensation programme that was developed in
2022. This plan will include recommendations on the
Implementation Agreement.
Moving forward into the 2025 financial year, the
company will target finalising funding arrangements
and begin construction of the TGME Gold Project.
As part of this due diligence process, the Power China
team has been onsite drilling and collecting samples
for metallurgical test work with the Theta team. The
test work has assisted in refining the final plant design
and evaluating the tailings at the TGME mine site.
We appreciate the continued support from our
shareholders, and we welcome new shareholders
to the share register. The Company looks forward
to continuing to progress project development and
deliver good news for shareholders in 2024.
The TGME Underground Feasibility Study (FS) was
completed in July 2022, at $1642 USD gold price.
Now the gold price is trading at all time high levels
above 2,600+ USD at the time of this report.
Thank you for your continued support.
Bill Guy
Charles (Bill) Guy
Chairman
Refer to ASX Release dated 14 February 2024 titled, “Theta Gold selects PowerChina’s subsidiary as its preferred EPC Partner to build its stage one
TGME Gold Plant and TSF Facilities estimate at US$30 million”.
1
2
SIGNIFICANT
MILESTONES
ACHIEVED IN
2024
•
Received the Water Use License for its TGME
Gold Project over Mining Right 83 from the
Department of Water and Sanitation (DWS) of
South Africa;
•
Final Environmental Authorisation (EA)
received for Mining Right 83 from the
Department of Mineral Resource and Energy
(DMRE) of South Africa as announced on
14 March 20244;
•
Granted a Water Use License (WUL)
for Frankfort mine by the South African
Department of Water and Sanitation (DWS)
resulting in Frankfort being fully permitted;
•
Metallurgical Test Work completed and
confirmed that gold is recoverable from the
TGME Tailings Storage Facility and Rock
Dumps5 (174,000 OZ AU);
•
Execution of A$46m (US$30m) nonbinding MOU2 with Yellow River Co. Ltd
(“YRC”), a subsidiary of Power Construction
Corporation of China (“PowerChina”) to
build Theta’s Stage-one TGME Gold Plant
(estimated at 45kt/month RoM capacity)
including its talings storage facility and
wastewater dams;
•
Redemption of 2Invest AG Secured Bonds for
AU6 million as announced on 16 September
2024, allowing the Company to engage with
financiers for the greater Capex requirements
of project.
Figure 1: Miners entering Frankfort gold Mine
Refer to ASX Release dated 14 February 2024 titled, “Theta Gold selects PowerChina subsidiary as EPC partner”.
Refer to ASX Release dated 11 April 2023 titled, “Theta Received Water Use Licence for Mining Right 83”.
Refer to ASX Release dated 14 March 2024 titled, “Theta now fully permitted with mining right secured”.
5
Refer to ASX Release dated 30 July 2024 titled, “Metallurgical Test Results confirms that gold is recoverable from the TGME Tailings Storage Facility and Rock Dumps”.
2
3
4
3
THETA GOLD MINES LIMITED | ANNUAL REPORT 2024
REVIEW OF
OPERATIONS
OVERVIEW
The TGME Project (Phase 1) incorporates the
first four mines. In April 2021 Theta declared a
maiden underground Mining Reserve of 419,000 oz
@ 5.49 g/t Gold, along with the first Maiden
Underground Pre-Feasibility Study. The Mining
Reserve were based on only 16% of the 4.5 Moz
underground gold resource and incorporated only
three mines across the project area.
Theta Gold Mines Limited (“the Company” or
“Theta Gold” or “TGM”) is a gold exploration
and development company that holds a range of
prospective gold assets through its 74%-owned
subsidiary Transvaal Gold Mining Estate Ltd (TGME)
in a world-renowned South African gold mining
region. The Company’s shares are dual listed on the
Australian Securities Exchange (ASX: TGM).
The Company’s TGME Underground Gold Mine
Project (“The Project” or “TGME Project”) phase
one consists of four existing mines, Beta, Frankfort,
CDM and the Rietfontein mine. The Project is
located next to the historical gold mining town of
Pilgrim’s Rest, in the Mpumalanga Province, some
370km northeast of Johannesburg or 95km north of
Nelspruit (the Provincial Capital City) and includes
more than 43 historical mines identified across the
vast prospective gold field of 620 square kilometres
(62,000 hectares).
The Company delivered its very first definitive
Feasibility Study (FS) in July 2022 which presents a
clear pathway to production via the re-development
of TGME’s gold assets and is currently focused on
the holistic strategy to deliver long term organic
growth, with initial development focusing on the
permitting of six mines to target a production profile
of 160,000 ounces Au per annum.
Figure 2: Drilling at TGME Tailings Dam
Figure 3: Location of Theta Gold Mine Project
4
PROJECT
HIGHLIGHTS
US$843/oz
DEFINITIVE FEASIBILITY
STUDY (TGME
UNDERGROUND GOLD
MINE PROJECT)
all-in-sustaining
cost
• TGME Feasibility Study6 (FS) delivers 1.24Moz
contained gold production, underpinning an initial
12.9-year mine life;
• Strong financial return based on LOM plan
(at average gold price of A$2,189/oz) with first
production targeted for 20247 including:
– Undiscounted free cash flows of US$508m,
(A$678m), pre-tax US$717, (A$956m);
– NPV (at a 10% discount rate) of US$219m,
(A$292m), pre-tax US$324m, (A$432m);
– Capital payback period of 31 months;
– Pre-tax IRR of 65%; and
ll-in-sustaining Cost (AISC) of US$834/oz
A
(A$1,112/oz) over LOM sits on the bottom
quartile of South Africa and Australian
gold producers;
– Peak production over 100,000 oz Gold.
• All-in-sustaining Cost (AISC) of US$834/oz
(A$1,112/oz) over LOM sits on the bottom quartile
of South Africa and Australian gold producers;
• Peak Capital requirement is US$77m, (A$103m),
total capital requirements US$174m, (A$232m);
and
US$77m
• Front-End Engineering Design (FEED) of the TGME
gold plant completed, forming an important input
towards the finalisation of the definitive Feasibility
Study (FS) of the TGME underground project8.
peak capital
requirements
US$508m
undiscounted
free cash flows
efer to ASX release dated 27 July 2022 titled “Theta’s TGME Project Definitive FS Confirms NPV10% of
R
A$432 million at US$1,642/Oz Gold price.”
First gold produced timing will be subject to securing funding and obtaining all necessary regulatory
permitting approvals.
8
Refer to ASX release dated 20 June 2022 titled “TGME Gold Project Update”.
6
7
Undiscounted free cash flows of US$508m,
(A$678m), pre-tax US$717, (A$956m);
5
THETA GOLD MINES LIMITED | ANNUAL REPORT 2024
OPERATIONS
DRILLING AND SAMPLING
ON THE TGME GOLD MINE
TAILINGS DAM
The Company announced that the Power China
team has been onsite drilling and collecting
samples for metallurgical test work. The test work
will assist in refining plant design and evaluating
the tailings at the TGME mine site. The tailings
dams contain 140,000 oz gold and will be tested
for metallurgical gold recovery. SGS South
Africa (Pty) (Assay Laboratory) Ltd, engaged
by TGM’s preferred Engineering Procurement
and Construction (“EPC”) partner Power China
subsidiary, (Yellow River Co., Pty (“YRC”) to
complete a drilling and sampling program at
various tailing dams around the Company’s
TGME gold plant for metallurgical test work.
The program was completed with a total of
407 meters drilled, 273.5 meters drilled into
the TGME main and four (4) Blyde tailings and
133.5 meters into the Glynn’s tailings. Theta
Gold currently records 141,000 ounces of gold
JORC Resources across multiple tailings dams
around the gold plant. In total, 174,000 gold
ounces sit on the surface surrounding the TGME
gold plant, including 140,000 ounces indicated
as a resource in various tailings dams around the
TGME plant area.
Figures 4 & 5: Drilling team by SGS at the Blyde #2 tailings near the
TGME Plant and drill samples been indexed by SGS team.
The drill results for the TGME Main Tailings
Storage Facility (“Main TSF”) have confirmed the
tailings dams contain gold at the expected grades
(See Table 1). Test results for metallurgical gold
recovery were also positive.
Figure 6: Location Map – TSF.
6
Table 1 at right is a summary of the drill results
for the TGME Main TSF, where the Company is
considering early processing/production through
Theta’s new gold plant to provide early cashflow
for the Company whilst development of the
underground Beta Mine is underway.
Composite samples were collected for
metallurgical test work. These samples
obtained from the main tailings dam were
collected from drill samples and additional
samples were collected from historic surface rock
dumps via trenching.
Table 1: Summary of TGME Main Tailings Dam drill results
Hole
Number
Hole
Depth
Metres
Number of
Samples
Per Hole
Weighted
Avr. Grade
Per Hole
(g/t)
TGME 1
5
4
1.49
TGME 2
5
4
1.54
TGME 3
19.5
13
1.38
TGME 4
16.5
11
0.93
TGME 5
3
2
1.28
TGME 6
10.5
7
1.14
TGME 7
22.5
15
1.07
TGME 8
13
9
1.45
TGME 9
4
3
1.54
TGME 10
18
12
1.36
Figure 7: Drill hole location map of the holes drilled by SGS team at the TGME Main TSF
7
THETA GOLD MINES LIMITED | ANNUAL REPORT 2024
Table 2: Highlights the best laboratory results for the composite samples.
Sample No.
Type
Head Grade
Gold (g/t)
Gold
Recovery %
TGME A
Tailings Dam Material
1.24 g/t
58.95%
Beta and Peach Tree
Surface Rock Dump
0.94 g/t
95.43%
Vaalhoek 1
Surface Rock Dump
1.19 g/t
95.46%
Note:
• TGME A sample: material from the main tailings dam
• Top 9 metres of the Main Tailings Dam contains a high grade gold zone (Figure 7)
• The Beta and Peach Tree samples are from surface rock dumps from the historical mining of the Beta mine, which is over 60% of the
current mine schedule.
• Beta Mine gold recovery in the Feasibility Study is set at 88%, results show a higher average recovery of 95%.
• Vaalhoek 1 samples – collected from the Vaalhoek mine area. Vaalhoek resource currently does not form part of the LOM schedule.
Figure 8: Shows Main Tailings Dam cross section showing the distribution of gold values. Note the higher grades occur in the upper 9 metres.
EXECUTION
READINESS
The Theta team is currently preparing the final
execution documentation for the TGME Gold Plant
build process. This way, the team will be ready
when the final funding for the build process is
secured. The final EPC contract will need to be
completed with Power China before construction
can start.
RM Process and Eco Elementum have been
appointed to complete the final designs for the
plant, tailings, and water management. They
assist Theta and Power China in compliance with
local regulations.
RM Process, a South African-based process
engineering company, will assist with the Final
designs of the TGME Gold Plant and will form part
of the execution team with Theta and Power China.
The Eco Elementum group of companies provides
an array of independent, multidisciplinary, and
integrated environmental science, engineering,
and construction services. Eco Elementum
will assist with the final designs of water
management systems and assist the design team
in environmental and legal compliance with the
Water Use Licence.
8
WORK IN
PROGRESS
• Updated flow sheet
• 75% completion of the scope of works
• Draft schedule completed for the final
plant designs
• Draft schedules completed for the
plant construction
• Draft schedule completed for the
dewatering plant, water management and
tailings deposition
ENGINEERING
DRILLING
As part of the water use licence conditions,
Theta is required to drill geotechnical infill holes to
ensure the tailings and existing Plant footprint are
• 69% completion of the tender process and RFQ
• RM Process and EcoE teams to visit the Mine in
the week of 7 July 2024
• NDA’s out to all vetted possible OEMs
• Team integration to start as of the first week of
July 2024 (TGME, RM and EcoE)
• Long leading items identified and
71% completed
• Project Execution Plan at 82% completed
• Data sets at 72% completed
not affected by dolomites (voids in the bedrock).
The old gold plant tailing has been in place for
40 years and was previously drilled.
The first holes were completed at an average hole
depth of 35m, with samples collected for rock
classification and final designs.
Figure 9: Engineering drilling team onsite near tailings dam.
9
THETA GOLD MINES LIMITED | ANNUAL REPORT 2024
ENVIRONMENTAL PERMITTING MR83
Mining Right (MR) 83 is now fully permitted for mining. MR 83 includes the Beta Mine, CDM Mine, and Frankfort
Mine, three of the four mines included in the mining schedule of the Definitive Feasibility Study.
Theta now has all the required approvals for MR 83 to start mining:
• Atmospheric Emissions Licence (Gold Plant)
• Explosive licence for transport and usage
• Forrest Licence (Frankfort area)
• MR 83 Environmental Authorisation
• Water Use Licence (for tailings, plant and mining)
• Environmental Rehabilitation Guarantee in place for MR 83
• Updated Social and Labour Plan for MR 83
• Heritage Record of Decision
During September 2023, MR 83 had an objection lodged against its environmental approvals as part of a 90-day
public review period9 by one individual out of over 900 public & private members. This objection was rejected by
the Department of Forest Fishery and Environment (“DFFE”) and all other related departments.
For the Rietfontein Mine, the environmental authorisation application was submitted to the DMRE on 10 October
2023 and the final scoping report was submitted on 20 November 2023. The DMRE accepted the Final Scoping
Report on 5 April 2024 and TGME may now proceed to the EIA phase of the Environmental Authorisation (EA)
application process.
CORPORATE FUNDING
Theta Gold Raised a total of AU$5 million, (US$3.3million) during 2024 fiscal year in development funding for the
TGME gold mine project, and had received a further AU$21.2 million, (US$14 million) in commitments via share
subscription agreements with proceeds to be received post 30 June 2024 as follows:
2023 PLACEMENTS COMPLETED:
•
AU$5 million, (US$3.3 million) of capital raised (before costs) via a Private Placement as announced to ASX
on 4 July 202310 to strategic professional and sophisticated investors including cornerstone investor, Hong
Kong Ruihua Investment Management Limited (Ruihua) numerous existing shareholders, new institutional,
professional, and sophisticated investors.
•
The Company issued 76,923,077 new fully paid TGM Ordinary Shares at the issue price of AU$0.065
per share.
CONVERSION OF OPTIONS:
• AU$0.290 million, (US$0.188 million) of capital raised (before costs) via the conversion of 5,000,000 unlisted
options into 5,000,000 new TGM fully paid ordinary shares as announced to ASX on 20 September 2023.
The funds raised from the conversion were used to further advance the TGME gold project.
• AU$0.068 million, (US$0.044 million) of capital raised (before costs) via the conversion of 1,000,000 unlisted
options into 1,000,000 new TGM fully paid ordinary shares as announced to ASX on 9 November 2023.
The funds raised from the conversion were used to further advance the TGME gold project.
• AU$0.066 million, (US$0.043 million) of capital raised (before costs) via the conversion of 1,000,000 unlisted
options into 1,000,000 new TGM fully paid ordinary shares as announced to ASX on 12 December 2023.
The funds raised from the conversion were used to further advance the TGME gold project.
9
Refer to ASX release dated 11 September 2023 “ENVIRONMENTAL AUTHORISATION UPDATE FOR MR83”.
Refer to ASX Released dated 4 July 2024 titled, “$5 Million Private Placement and Corporate Update”.
10
10
US$4 MILLION PRIVATE PLACEMENT
• Theta further announced on the 26 June 2024 it had received firm commitments from existing and new
sophisticated and wholesale investors to raise a further US$4.0 million (AU$6.02 million) (before costs) via
Share Subscription Application(s) in a private placement, on the same terms as the previously announced
Two-$10 million Placement announced on 6 May 2024.
• Additional proceeds raised in the June 2024 Placement will result in the Company issuing approximately a
further 46,276,113 million new fully paid TGM Ordinary Shares at the issue price of AU$0.13 (13 cents) per
share along with approximately 23,138,057 new attaching Options to be issued on a one (1) free Option for
every two (2) new TGM Shares issued in the June 2024 Placement.
• Each Option will have an exercise price equal to an 8% discount to the 15-day VWAP to the last closing price
at the time of exercise (but no less than AU$0.13), and an expiry date 2 years from the date of issue. Options
issued under the Placement will not be quoted.
POST – FY 24 COMMITMENTS VIA SHARE SUBSCRIPTIONS
US$10 million Two-Tranche Placement:
• The Company announced on 26 May 2024 a Share Subscription Agreement (Subscription Agreement) in a
two-tranche Placement to raise approximately US$10.0 million (AU$15.2 million) (before costs) through a
private placement (Placement) by an existing long term institutional investor of the Company.
• Hong Kong Ruihua Investment Management Limited (“Ruihua”) had committed up to US$10.0 million
(AU$15.2 million) in the placement. Ruihua is a wholly-owned subsidiary to its Nanjing based parent company
Jiangsu Ruihua Investment Holding Group Co., Ltd (since 2003), a fund manager with over US$3 billion AUM
who specialises in equity markets, including secondary market trading, private placements, venture capital
and private equity activities.
• Proceeds raised in the Placement will be provided in two-tranches and the Company will issue in total,
approximately 116.93 million new fully paid TGM Ordinary Shares at the issue price of AU$0.13 (13 cents) per
share along with approximately 58.47 million new attaching Options to be issued on a one (1) free option for
every two (2) new TGM Shares issued in the Placement.
• Each Option will have an exercise price equal to an 8% discount to the 15-day VWAP to the last closing price at
the time of exercise (but no less than $0.13), and an expiry date 2 years from the date of issue. Options issued
under the Placement will not be quoted.
• Tranche 1 Shares and Options were issued on 18 September 2024.
US$2 MILLION PLACEMENT
Oversubscribed Private Placement:
• The Company further advised on 16 September 202411 that it has received a firm commitment for an
additional US$2 million (~AU$3 million) from institutional investors on the same terms as the US$10 million
Two-Tranche Placement.
• The Company issued approximately 23,048,11312 new TGM Shares, at the issue price of AU$0.13 (13 cents)
per share, along with approximately 11,524,056 attaching options.
11
12
11
Ref to ASX Release dated 16 September 2024 titled, “US$8 million Private Placement and Full Redemption of AU$6 million secured bond.
Number of new shares is calculated after conversion of USD to AUD at a rate of 0.6675 and applying the per share issue price of 13 cents.
THETA GOLD MINES LIMITED | ANNUAL REPORT 2024
THETA’S TGME GOLD PROJECT DEFINITIVE FEASIBILITY
STUDY (FS)
The FS13 for the TGME Project was delivered on 27 July 2022, confirming Theta Gold’s potential to be a
significant near-term, high-margin, low-cost gold production project with tremendous opportunities for
future growth. Based on the FS results, the Project will provide robust financial returns from a long-life large
underground mining operation for a modest capital investment given the scale of operations envisaged.
The Project LOM will initially comprise a 12.9-year mining operation starting in, 202414 calendar year and
delivering LOM production of 1.24 Moz of contained gold. The estimated peak development Capital Expenditure
(“Capex”) is A$103 million, with the Project forecast to generate a pre-tax NPV10% of A$432 million and pretax internal Rate of Return (IRR) of 65% at a forecast average gold price of A$2,189 per ounce. Based on these
metrics, the Project has a projected capital payback period of 31 months.
The FS paves the way for a Final Investment Decision (‘FID’) by the Theta Gold Board in respect to funding
negotiations and on-going discussions with financiers with respect to full/partial debt and equity funding options.
Theta Gold has appointed a debt funding advisor to manage this important process and will provide updates in
due course.
KEY FEATURES OF PROJECT
Table 3: Key Project Metrics
Description
Units
Base Case
Reserve Plan
Project Start Date¹
Year
2024
2024
Commercial Production Start Date
Year
2025
2025
Production build up period
Months
14
14
Life of mine
years
12.9
7.3
Underground ore mined (LOM)
Mt
6.46
2.85
Mined Grade
g/t
5.95
6.09
Gold Mined (LOM)
Moz
1.24
0.56
Production Rate
Kt/a
540
540
Production Rate
Kt/m
45
45
Grind size
µ
106
106
Gold recovered (average LOM)
%
87
87
Gold recovered (LOM)
Moz
1.08
0.49
Project economics below shows the sensitivities to the various gold price estimates and demonstrates the robust
financial returns of the Project. The FS completed in July 2022 used an average gold price of USD 1,642 / Oz as a
base case.
1. Start-up of project and commercial production is subject to receiving all necessary funding and permit approvals.
13
14
Refer to ASX Release dated 27 July 2022 titled “Theta’s TGME Project Definitive FS Confirms NPV(10%) of A$432 Million at US$1,642 / Oz Gold Price”.
Start time will be dependent on securing necessary funding and permitting approvals.
12
Table 4: Project Economics at Various Gold Prices – Base Case (AUD)
Project Economics at gold price
Unit
Forecast
USD1,500/oz USD1,600/oz
(USD1,642/ oz Avg)
USD1,800/oz USD2,000/oz USD2,200/oz
NPV @ 10% (real) Pre-tax
AUDm
432
339
405
536
669
802
NPV @ 10% (real) Post-tax
AUDm
292
232
274
359
447
533
IRR (%) Pre-tax
%
65%
57%
64%
77%
90%
102%
IRR (%) Post-tax
%
57%
50%
56%
67%
78%
87%
AISC
AUD/oz
1,112
1,096
1,107
1,129
1,149
1,167
EBITDA annual average
AUDm
92
77
87
107
128
148
EBIT annual average
AUDm
80
66
76
96
116
136
Free Cash Flow (Pre-tax)
AUDm
956
768
897
1,158
1,421
1,686
Free Cash Flow (Post-tax)
AUDm
678
550
638
814
996
1,175
Development Capital – Peak Funding
AUDm
102
102
102
102
102
102
Capital Sustaining
AUDm
49
49
49
49
49
49
Payback post-tax
Months
31
33
31
28
25
24
Capital Efficiency (Pre-Tax NPV/Dev Capital
%
422%
332%
395%
524%
653%
783%
Capital Efficiency (Post-Tax NPV/Dev Capital
%
285%
226%
268%
351%
437%
521%
NOTES:
1. Converted to AUD from USD using AUD:USD exchange rate of 1.333.
2. Due to rounding, numbers presented throughout this document may not add up precisely to the totals, provided and percentages may not precisely reflect the absolute figures.
Figure 10: Annual Gold Production – Base Case
13
THETA GOLD MINES LIMITED | ANNUAL REPORT 2024
Figure 11: Annual and Cumulative Cash Flow (Post-Tax) – Base Case (AUD)
NOTES:
1. Forecast Prices averaging USD1,642/oz over LOM.
2. Converted to AUD from USD at exchange rate of 1.333 AUD:USD.
The TGME Project targets to restart historical underground gold mines located in a historically prolific gold mining
region in the Mpumalanga Province of South Africa. The Project Areas are centred in the town of Pilgrims Rest,
some 370 km due northeast of Johannesburg, and vast majority of the tenements were under TGME’s ownership
since the late 1800s.
The Project targets the Beta (including the Beta North, Beta Central and Beta South sections), Rietfontein,
Frankfort and Clewer-Dukes Hill-Morgenzon (“CDM”) mines. A significant amount of gold resources remain
underground which were not mined historically due to technological limitations or limiting ore characteristics.
Beta is scheduled as the first operation to commence production, followed by Rietfontein, and finally CDM and
Frankfort simultaneously. In comparison to CDM and Frankfort, Beta and Rietfontein are higher-grade mines.
A gold plant, which acts as the central processing plant for all the historical operations, is situated in close
proximity with a maximum distance to operations of approximately 40km. A new facility will be established on this
footprint to treat all the ore from the surrounding operations.
Two scheduling strategies have been investigated in the FS. The Base Case considers a LOM plan targeting
the total Mineral Resources (Measured, Indicated and Inferred). The Ore Reserve Case considers a LOM plan
targeting only Measured and Indicated Mineral Resources.
This FS demonstrates the ability to achieve optimised cash flows by scheduling production from the operations.
The mine designs and associated costs per operational element feed into a combined operations financial model.
The Ore Reserve Case supports the declaration of compliant JORC Code 2012 Ore Reserves.
TGME UNDERGROUND GOLD MINE DEVELOPMENT
As part of the preparation for the installation of the first phase new gold plant, TGME had appointed the services
of Jet Demolition to remove the redundant plant equipment. The process started in the second week of January
2022. Specialised equipment was utilised for demolition, after which it was reduced in size and made ready for
transport to scrap merchants. The project to remove the old plant is now complete15.
Processing consultants Met63 was contracted to do a detailed design and costing of a processing plant designed
for a feed capacity of 45,000 tons per month which is equivalent to 67 tons per hour at 92% availability. A flow
schematic is shown in Figure 12.
15
Refer to ASX release dated 4 March 2022 titled “DFS Update and High-Grade Ore Sweeped from New Historical Mines”.
14
Figure 12: Process Flow Schematic Phase 1
The FS has been split into three phases, allowing for various processing scenarios aligned with the mining
development program. The design of each phase is based on a stand-alone processing facility aligned with the
mining plan of the ore body.
•
Phase 1 – Carbon-in-Leach (CIL) Plant (Free-milling ore is process for the first 7 Years, see figure 12).
The design and costing of a 45,000 tons per month oxide ore processing plant including crushing,
milling, CIL and elution with gold Doré produced on site. Test work undertaken on various “free-milling”
ores has indicate