Permitting Update for TGME Underground Gold Project
Released
Released
Announcement PDF
27 April 2022
ASX ANNOUNCEMENT
PERMITTING UPDATE
THE TGME UNDERGROUND PROJECT
HIGHLIGHTS:
•
Final Scoping Report submitted with the South African Department of Mineral
Resources and Energy (‘MRE’)
•
Completion of environmental specialist and engineering designs required for MR 83
permitting
•
MR 83 permitting project now moves into the Environmental Impact Assessment (‘EIA’)
phase – completion anticipated in late Q4 2022
•
Water Use Licence application registered with the Department of Water and Sanitation
(‘DWS’) – final submission expected in Q3 followed by a 90-day review period
•
Department of Forestry, Fisheries and the Environment (‘DFFE’) presented with a
comprehensive ecological compensation programme for the continuance of mining at
the Beta and CDM Mines on areas which sit within the Forest Nature Reserve
• Upon approval the ecological compensation programme will add to Theta Gold’s
growing ESG program
Theta Gold Mines Limited (“Theta Gold” or the “Company”) (ASX: TGM| OTC: TGMGF) is pleased to
advise it has advanced its MR 83 permitting process, completing 20 environmental studies (Table 1)
to support the TGME Underground (‘UG’) project, which comprises the Beta, Frankfort, CDM, and
Rietfontein mines.
The Final Scoping Report was submitted on 12 April 2022 has been reviewed and accepted by the
South African Department of Mineral Resources and Energy (‘DMRE’) allowing the Company to
proceed to the EIA phase of the Environmental Authorisation (‘EA’) application process. The
acceptance of the Scoping Report is an important milestone for Theta Gold highlighting in that it marks
the conclusion of all environmental specialist and engineering designs required for the MR 83
permitting process necessary to progress underground mining at the Beta, Frankfort, and CDM mines.
Theta Management will now focus on securing approval for the Draft EIA Report and Environmental
Management Programme (Draft ‘EIA/EMPr’) which has been compiled for the public comment. This
document is presently available for a 60-day public review and comment period which commenced
1
on 19 April 2022. During this public review period, various meetings and a public open day will take
place to address any comments and concerns from stakeholders. The final EIA/EMPr will be submitted
to the DMRE for approval in Q3 and a decision on the EA application is expected in Q4.
In addition, the Water Use Licence (‘WUL’) application has been registered with the Department of
Water and Sanitation (‘DWS’) and a pre-application meeting was conducted with a DWS case officer.
The WUL is a separate process from the EIA, as highlighted by Table 2 showing permitting workstreams
have already been completed. The draft Integrated Water and Waste Management Plan (‘IWWMP’)
has been compiled and is also available for public review, running parallel with the EIA phase public
review period. The final submission of the WUL application is scheduled for Q3. Once submitted the
DWS will have 90 days to assess the application.
To continue mining in parts of the Beta and CDM Mines, approval from the Minister of the Department
of Forestry, Fisheries and the Environment (‘DFFE’) is also required. The DFFE has been offered an
Ecological Compensation Programme to assist with securing the future of the local catchment system.
As part of Theta ESG programs, Theta will cornerstone the investment with other NGO’S to protect,
rehabilitate and ensure the long-term sustainability of the local catchment area. The proposed
Ecological Compensation Programme includes;
•
•
•
•
•
•
Eradication and control of invasive alien plants species,
Fire belt implementation,
Rehabilitation of diverted streams and drainages,
Implementation of erosion and sediment control,
Facilitating the re-establishment of native grasslands and indigenous forests,
Optimising the hydrological functioning of the catchment area.
The Frankfort and Rietfontein Mines which fall outside the Morgenzon forest nature reserve areas are
excluded from the above DFFE dealings and will not have to meet this DFFE requirement. Frankfort
and Rietfontein and are only subject to the normal EA process highlighted above.
Chairman Mr. Bill Guy commented: “The acceptance of the final scoping report received from the MRE
marks a significant milestone for Theta as we have now completed all the required environmental
specialist and engineering designs required for MR 83 permitting. Its pleasing to see the support and
endorsement we have received not only from the government, but from our local communities and
landowners who all have a direct interest under the BEE structure. As we move to the Environmental
Impact Assessment stage, we expect to witness the same level of support from all stakeholders during
our meetings and public open day.
“At the Beta and CDM mines, by including the ecological compensation into our growing ESG program,
we will positively affect the local catchment area for years to come. Our decision to cornerstone this
investment and work with stakeholders and the DFFE is set to benefit future generations in the region.
As we continue to make encouraging progress towards the DFS, I look forward to providing
shareholders with ongoing updates.”
2
Table 1 indicates the list of specialist studies conducted to date as part of the environmental
application process.
Specialist Studies
Environmental Specialists
Air Quality impact assessment and Greenhouse Gas Assessment
Status
Airshed Planning Professionals (Pty) Ltd
✓
Biodiversity impact assessment
SAS Environmental Group of Companies
✓
Blasting and Vibration study
Blast Management and Consulting
✓
Ecological Compensation Plan
Conservation Strategy, Tactics, and Insight
✓
Mine Closure and rehabilitation plan
OMI Solutions
✓
Freshwater and aquatic ecology impact assessment
SAS Environmental Group of Companies
✓
Geohydrological impact assessment
MvB Consulting
✓
Dolomite Stability assessment
Jones & Wagener
✓
Heritage and Paleontological impact assessment
Heritage Management Consulting
✓
Noise impact assessment
EnviroRoots (Pty) Ltd
✓
Socio-economic impact assessment
Kongiwe Environmental
✓
Soil and land use capability
SAS Environmental Group of Companies
Stormwater management plans/ Civil engineering designs
Eco Elementum Environmental and Engineering
Traffic impact assessment
Infratrans Pty (Ltd)
Visual impact assessment
SAS Environmental Group of Companies
Waste classification
GeoDyn Systems
Tailings Storage Facility Waste Risk Assessment
HydroScience
Rietfontein Prefeasibility Study: Freshwater and aquatic ecology
impact assessment
SAS Environmental Group of Companies
Rietfontein Prefeasibility Study: Soil and Land Use Capability
Assessment
SAS Environmental Group of Companies
Rietfontein Prefeasibility Study: Visual Impact Assessment
SAS Environmental Group of Companies
✓
✓
✓
✓
✓
✓
✓
✓
✓
Table 1 - Specialist studies conducted.
3
Table 2 indicates the progress made in the current environmental approval process.
Task
Duration
Submit application for EA
29 November 2021
Obtain Reference number from DMRE for EA application
15 February 2022
Status
✓
✓
(acknowledgement letter)
Submit draft scoping report to the public for review
06 December 2021
✓
Public Review Period – draft scoping report
07 December 2021 – 26 January 2022
✓
Public Participation Meetings for Scoping Phase
12 January 2022 – 15 January 2022
✓
Open day meeting
15 January 2022
✓
Submission of final scoping report to the DMRE
03 February 2022
✓
Submit pre-application enquiry for WUL application
21 February 2022
✓
Specialists EIA Studies Completed
31 March 2022
✓
Pre-application meeting with DWS
11 April 2022
✓
DMRE acceptance of final scoping report
12 April 2022
✓
Draft EIA/EMPr and the Draft IWWMP submitted for public review
19 April 2022
✓
Table 2 – Progress made in current environmental approval process.
[ENDS]
This announcement was approved for release by Theta Gold Mines Limited’s Board.
For more information, please visit www.thetagoldmines.com or contact:
Bill Guy, Chairman
Theta Gold Mines Limited
T: + 61 2 8046 7584 E: billg@thetagoldmines.com
Investor Relations
Australia: Ben Jarvis, Six Degrees Investor Relations: +61 (0) 413 150 448
Webpage: www.thetagoldmines.com
https://twitter.com/ThetaGoldMines
https://www.linkedin.com/company/thetagoldmines/
ABOUT THETA GOLD MINES LIMITED
Theta Gold Mines Limited (ASX: TGM | OTCQB: TGMGF) is a gold development company that holds a range
of prospective gold assets in a world-renowned South African gold mining region. These assets include
several surface and near-surface high-grade gold projects which provide cost advantages relative to other
gold producers in the region.
4
Theta Gold’s core project is located next to the historical gold mining town of Pilgrim’s Rest, in Mpumalanga
Province, some 370km northeast of Johannesburg by road or 95km north of Nelspruit (Capital City of
Mpumalanga Province). Following small scale production from 2011 – 2015, the Company is currently
focussing on the construction of a new gold processing plant within its approved footprint at the TGME
plant, and for the processing of the Theta Open Pit oxide gold ore. Nearby surface and underground mines
and prospects are expected to be further evaluated in the future.
The Company aims to build a solid production platform to over 160kozpa based primarily around shallow,
open-pit or adit-entry shallow underground hard rock mining sources. Theta Gold has access to over 43
historical mines and prospect areas that can be accessed and explored, with over 6.7Moz of historical
production recorded.
Theta Gold holds 100% issued capital of its South African subsidiary, Theta Gold SA (Pty) Ltd (“TGSA”). TGSA
holds a 74% shareholding in both Transvaal Gold Mining Estates Limited (“TGME”) and Sabie Mines (Pty)
Ltd (“Sabie Mines”). The balance of shareholding is held by Black Economic Empowerment (“BEE”) entities.
The South African Mining Charter requires a minimum of 26% meaningful economic participation by the
historically disadvantaged South Africans (“HDSAs”). The BEE shareholding in TGME and Sabie Mines is
comprised of a combination of local community trusts, an employee trust and a strategic entrepreneurial
partner.
DISCLAIMER
This announcement has been prepared by and issued by Theta Gold Mines Limited to assist in
informing interested parties about the Company and should not be considered as an offer or
invitation to subscribe for or purchase any securities in the Company or as an inducement to make
an offer or invitation with respect to those securities. No agreement to subscribe for securities in the
Company will be entered into on the basis of this announcement.
This announcement may contain forward looking statements. Whilst Theta Gold has no reason to
believe that any such statements and projections are either false, misleading or incorrect, it does not
warrant or guarantee such statements. Nothing contained in this announcement constitutes
investment, legal, tax or other advice. This overview of Theta Gold does not purport to be all
inclusive or to contain all information which its recipients may require in order to make an informed
assessment of the Company’s prospects. Before making an investment decision, you should consult
your professional adviser, and perform your own analysis prior to making any investment decision.
To the maximum extent permitted by law, the Company makes no representation and gives no
assurance, guarantee or warranty, express or implied, as to, and take no responsibility and assume
no liability for, the authenticity, validity, accuracy, suitability or completeness of, or any errors in or
omissions, from any information, statement or opinion contained in this announcement. This
announcement contains information, ideas and analysis which are proprietary to Theta Gold.
5
FORWARD LOOKING AND CAUTIONARY STATEMENTS
This announcement may refer to the intention of Theta Gold regarding estimates or future events
which could be considered forward looking statements. Forward looking statements are typically
preceded by words such as “Forecast”, “Planned”, “Expected”, “Intends”, “Potential”, “Conceptual”,
“Believes”, “Anticipates”, “Predicted”, “Estimated” or similar expressions. Forward looking
statements, opinions and estimates included in this announcement are based on assumptions and
contingencies which are subject to change without notice, and may be influenced by such factors as
funding availability, market-related forces (commodity prices, exchange rates, stock market indices
and the like) and political or economic events (including government or community issues, global or
systemic events). Forward looking statements are provided as a general reflection of the intention
of the Company as at the date of release of the document, however are subject to change without
notice, and at any time. Future events are subject to risks and uncertainties, and as such results,
performance and achievements may in fact differ from those referred to in this announcement.
Mining, by its nature, and related activities including mineral exploration, are subject to a large
number of variables and risks, many of which cannot be adequately addressed, or be expected to be
assessed, in this document. Work contained within or referenced in this report may contain
incorrect statements, errors, miscalculations, omissions and other mistakes. For this reason, any
conclusions, inferences, judgments, opinions, recommendations or other interpretations either
contained in this announcement, or referencing this announcement, cannot be relied upon. There
can be no assurance that future results or events will be consistent with any such opinions, forecasts
or estimates. The Company believes it has a reasonable basis for making the forward looking
statements contained in this document, with respect to any production targets, resource statements
or financial estimates, however further work to define Mineral Resources or Reserves, technical
studies including feasibilities, and related investigations are required prior to commencement of
mining. No liability is accepted for any loss, cost or damage suffered or incurred by the reliance on
the sufficiency or completeness of the information, opinions or beliefs contained in this
announcement.
The Feasibility Study referred to in this announcement is based on technical and economic
assessments to support the estimation of Ore Reserves. There is no assurance that the intended
development referred to will proceed as described, and will rely on access to future funding to
implement. Theta Gold Mines believes it has reasonable grounds the results of the Feasibility Study.
At this stage there is no guarantee that funding will be available, and investors are to be aware of
any potential dilution of existing issued capital. The production targets and forward looking
statements referred to are based on information available to the Company at the time of release,
and should not be solely relied upon by investors when making investment decisions. Theta Gold
cautions that mining and exploration are high risk, and subject to change based on new information
or interpretation, commodity prices or foreign exchange rates. Actual results may differ materially
from the results or production targets contained in this release. Further evaluation is required prior
to a decision to conduct mining being made. The estimated Mineral Resources quoted in this release
have been prepared by Competent Persons as required under the JORC Code (2012). Material
assumptions and other important information are contained in this release.