Optimised Theta Project Delivers Additional 40,000 Oz Gold
Released
Released
Announcement PDF
20 April 2020
ASX ANNOUNCEMENT
OPTIMISED MINE SCHEDULE FOR THETA OPEN PIT STARTER PROJECT
DELIVERS SIGNIFICANT IMPROVEMENTS
(New Mine schedule adds 40 000 gold Ounces to May 2019
Feasibility Study for Theta Project)
Theta Gold Mines Limited (“Theta Gold” or “Company”) (ASX: TGM, TGMO | OTCQB: TGMGF) is
pleased to announce a new optimised mine schedule for its Theta Open Pit Starter Project that
adds 40,000 oz of gold over the Feasibility Study released in May 2019. The new Mine schedule
significantly improves the metrics of the project (see Table 1) over the May 2019 Feasibility Study
(May '19 FS), has a reduced environmental footprint, reflects an increase in the production rate
from 500 ktpa to 600 ktpa, includes the mining of several old mine waste rock dumps and
increases the overall mine operational flexibility.
HIGHLIGHTS
(All numbers in USD and financials based on USD 1 500/oz gold price and 16.00 ZAR/USD)
Pay-back period reduced to 8 months (May ’19 FS: 14 months payback period)
260 koz delivered to plant over Life of Mine (“LoM”) (May ’19 FS: 219 koz Au)
First year production of 49.5 koz (May ’19 FS: 46.3 koz)
Life of Mine (LoM) 6.5 years (May ’19 FS: 5 years)
US$150.2 million EBITDA over LoM (May ’19 FS: $99.6 million LoM)
Internal Rate of Return 123% (May ‘19 FS: 65.1%)
US$85 million Net Present Value (May ’19 FS: $50 million NPV)
US$855/oz all-in sustaining cost (AISC) LoM, bottom quartile for South Africa
producers (May ’19 FS: $760/oz cost (“AISC”) over the 5-year LoM)
Total Capital Cost US$31.4 million includes 20% plant throughput increase
and at 16.00 ZAR/USD (May ’19 FS: $34.3 million at 14.01 ZAR/USD)
There remains significant resource development upside from the contiguous southerly
extension of the Theta Hill mineralisation into Mining Right 341 and other open cut
resources nearby – this is no change from the May ’19 FS and, for clarity, these
additional resources have not been included in the May ’19 FS or this Optimised Study.
The Theta Open-pit Starter Project includes the Columbia Hill deposit and part of the Theta Hill
deposit within Mining Right 83 (“MR83”) (Figure 1) in the Pilgrims Rest area of South Africa.
Waste Rock dumps of various sizes and from four main areas which were sampled by Rand Mines
in the 1990’s are now included in the new mine schedule and add easy gold ounces for the
planned mine operations. The bulk of the waste rock dumps (75%) have been scheduled to be
processed in the last year of Mine Schedule and as such have limited effect on the payback period.
The payback period has been reduced from 14 months in the May ’19 FS to 8 months.
The optimized mine schedule has reduced initial overburden removal by mining smaller pits and
also has improved revenue streams as a result of increased ZAR gold prices.
The Optimised Study reflects strong project economics and commercial viability across a range of
gold prices. The new mine schedule significantly enhances all the project economics despite a
reduction in the LoM grade.
Table 1 below sets out the comparison of the initial May ’19 FS to the Optimised Study at various
gold price scenarios. Salient details between the Optimised Study run at $1 500/oz vs the May’19
FS base case at $1 257/oz include:
1.
2.
3.
4.
The IRR nearly doubling from 65% to 123%;
Mine life increases from 5 years to over 6.5 years;
EBITDA increases by $50 million over the LoM to $150 million; and
NPV increases by $35 million to $85 million.
Table 1 : Optimised Study compared May ‘19 FS
61
92.7%
259 607
234 063
Base
Case
$1 500/oz
85
123.0%
259 607
234 063
Stretch
Case
$1 600/oz
104
157.2%
259 607
234 063
Month
9
8
6
14
USDm
USD/oz
USDm
USDm
USD/oz
ZAR/USD
31.4
911
206%
108.5
1 369
14.64
31.4
855
350%
150.2
1 500
16.00
31.4
822
476%
181.4
1 600
17.00
34.3
760
182%
99.6
1 257
14.01
Real Discount Rate
Unit
Lower Case
$1 369/oz
NPV @ 5%
Internal Rate of Return (IRR)
Total ounces in Mine plan
Total Oz Recovered
Average Payback Period (From Start of
Production)
Total Capital Requirement
All In Sustaining Cost (AISC)
Return on investment
EBITDA over LOM
Gold Price
Exchange Rate
USDm
%
oz
oz
May ’19 FS
$1 257/oz
50
65.1%
219 425
200 905
The company continuous to honor its commitment to improving the project economics and
expansion of the production profile. The team has delivered a new optimized mine schedule,
completed a draft mining contract, delivered the mill to site and has initiated and received initial
feedback as part of the plant construction contract which is all a clear demonstration that the
project is moving forward.
The company has a five-year plan which targets 4 mine developments, Theta open-pit Starter
Project (MR83 only), Theta open pit extension (MR341) and the Rietfontein and Beta
2
underground mines. This 4-mine strategy provides the company with a clear growth strategy at a
combined open pit and underground resource of over 2.75 Moz with only the Theta Project
Starter Pit portion of this resource included in the Optimised Study. All ore is planned to be
processed within the permitted TGME plant footprint area with the new 600 ktpa CIL plant
designed to be readily expanded to cater for 1.2 Mtpa of oxide ore with a modest capital
expenditure and minimal operational down time. Expansions for the processing of underground
ore can also be readily achieved within the footprint and tied into the new 600 ktpa plant.
Chairman Mr Bill Guy stated, “The new optimised mine schedule is a credit to the team and the
work and energy put into the Theta Open pit Starter project has been rewarded. The new mine
schedule demonstrates clear robust project economics, with more gold extracted and greater
value for the shareholders.
At Theta Gold the resource pipeline into the future is strong, and the grandeur of resources and
geology in South Africa should not be underestimated. As gold is now finding favor again, the
Company is keen to be part of the South African mining industry that has produced in tonnage
terms of gold bullion more tons of gold than any other country. Over 40% of world gold has come
from the small corner of South Africa, we call home.
During this quarter, and while the team is restricted in movements due to the coronavirus lock
down, we will continue to progress the mining contract through to a final document with a
preferred contractor, amend the EIA and resubmit it so we can readily implement the expanded
mine schedule, progress discussion with five engineering firms tendering for the TGME gold plant
construction.
The Board’s eye is firmly on the near-term development into gold production and in the medium
term to grow the production profile as we develop and bring more mines on stream. We are
building a sustainable business for long term benefits for all shareholders and our local
community. “
Optimised Study Mine Schedule Summary
The optimized schedule allows for a life of mine (“LOM”) of 6.5 years and design takes into
consideration the company’s commitment to be an environmentally responsible miner.
The Ore Reserves estimated for the Theta Project represent the Iota section of Columbia Hill, and
approximately 35% of the Theta Hill and Browns Hill deposits within the MR83 boundary. The
Theta Hill and Browns Hill deposits extend to the south and into Mining Right 341 (“MR341”)
(Figure1). MR83 is fully permitted for underground mining and an amendment to include open
pit mining is in progress. There is an inclusion of a portion of historical waste rock dumps (inferred
resources) in the schedule, albeit that 75% of this material is processed at the end of the mining
schedule. The dumps are within a short trucking distances of the gold plant (average ~4 km).
Further expansion opportunity exists to extend the project to the south into MR341 and this will
be considered in future development work.
3
Figure 1 : MR83 Drilling and Upside Potential Expansion to MR341
A whole new CIL Plant has been planned and recently redesigned to treat ore at a rate of 600 ktpa
and increased by 20% from the May ’19 FS (see ASX release 28 Jan 2020 “Results of the
Independent Plant Design Optimisation Study”). Annual plant throughput and total deposition
volume is constrained by the current approved Tailings Storage Facility (“TSF”) at 600 ktpa and
2.5 Mt respectively. Future tailings dam expansions have also been considered in the study and
will require design and approvals before implementation.
All processing layouts were configured in and around the existing CIL Plant infrastructure to allow
for potential future plant expansions. The plant capital has allowed for all new equipment, except
for the mill (see ASX release 2 Oct 2019 : “Theta Agrees to Purchase Mill Operated by Glencore”)
An opportunity therefore exists to make use of further high-quality refurbished equipment which
may lead to further capital cost savings.
4
Figure 2 : TGME Plant Layout Showing 600 ktpa CIL Plant & Expansion to 1.2 Mtpa
Financial Summary
Financial modelling was completed over a range of gold and exchange rates to reflect low, mid
and high gold and exchange rate scenarios and are labelled Lower Case, Base Case and Stretch
case respectively. Unless otherwise stated, the company has considered the Base Case as its
primary financial model as it still reflects a conservative approach in the current market
environment. All the financial metrics are improved over the feasibility study released in May
2019 and at all scenarios modelled, and clearly demonstrate that modern mining methods being
applied to this field for the first time are certainly economically feasible.
5
Table 2 : Key Aspects of Optimised Study - Theta Project
Lower
Case
$1 369/oz
74
61
50
41
35
92.7%
259 607
234 063
3 040
2.09
3.1
Base
Case
$1 500/oz
104
85
71
60
51
123.0%
259 607
234 063
3 040
2.09
4.5
Stretch
Case
$1 600/oz
125
104
87
74
63
157.2%
259 607
234 063
3 040
2.09
5.8
206%
350%
476%
182%
Month
9
8
6
14
USDm
USDm
Month
USDm
USDm
USDm
g/t
g/t
31.4
28.5
9
321.7
108.5
74.3
1.4
1.6
31.4
26.7
9
350.4
150.2
103.7
1.2
1.4
31.4
25.1
9
373.8
181.4
125.4
1.1
1.2
34.3
29.2
21
252.6
99.6
65.7
1.6
2.0
USD/oz
911
855
822
760
USD/oz
USD/oz
ZAR/USD
1 058
1 369
14.64
989
1 500
16.00
948
1 600
17.00
933
1 257
14.01
Item
Unit
NPV @ 0%
NPV @ 5%
NPV @ 7.5%
NPV @ 10%
NPV @ 15%
Internal Rate of Return (IRR)
Total ounces in Mine plan (2)
Total Oz Recovered (2)
Average ounces recovered per month (2)
Average Grade to Plant (2)
Benefit-Cost Ratio/Money on Investment5.0
USDm
USDm
USDm
USDm
USDm
%
oz
oz
oz
g/t
Ratio
Return on Investment5.0
Average Payback Period (From Start of
Production)
Total Capital
Peak Funding Requirement (3)
Peak Funding Month
Revenue over LoM (Undiscounted)
EBITDA over LOM (Undiscounted)
Net Cash Flow over LoM (Undiscounted)
Break-even Milled Grade (Excluding Capex)
Break-even Milled Grade (Including Capex)
Break-even Gold Price (Excluding Capex AISC)
Break-even Gold Price (Including Capex)
Gold Price
Exchange Rate (1)
%
May ’19 FS
$1 257/oz
66
50
38
29
22
65.1%
219 425
200 905
3 348
2.71
2.8
Note:
Money On Investment (MOI) calculated as present value of income flow over present value of
investment (5% discount rate); calculated in USD terms.
EBITDA = Earnings before interest, tax, depreciation and amortisation (excludes Capital)
C1 represents the cash cost incurred at each processing stage, from mining through to
recoverable metal delivered to market
Notes:
1. All values converted from ZAR to USD at relevant exchange rate
2. Including 25% Inferred Mineral Resources (Au content) in Optimised Study only
3. Capital costs in Optimised Study were converted from ZAR
6
The project also demonstrates a robust NPV across a wide range of gold prices as can be seen in
the graph below.
Figure 3 : NPV Sensitivity to Gold Price
The AISC costs for the Optimised Study continue to reflect a project that is at the bottom quartile
when compared to South African peer mines
Figure 4 : South African Miners AISC Costs 2018: Minxcon 2018
7
5,000
5.00
4,500
4.50
4,000
4.00
3,500
3.50
3,000
3.00
2,500
2.50
2,000
2.00
1,500
1.50
1,000
1.00
500
0.50
-
Grade (g/t)
Recovered Oz
The optimised schedule has been developed to ensure higher volumes of ounces produced in
the early months to ensure further de-risking of the project
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76 79 82 85
Months
Recovered Gold
Grade to Plant
Recovered Grade
Figure 5 : Optimised Study Monthly Gold Production (oz)
NEW PRODUCTION TARGET
The Optimised Study mine schedule for the Theta Open Pit Starter Project considers the following
Mineral Resources in the LoM plan. Appropriate modifying factors were applied to various
Mineral Resource categories as with a Reserve Calculation. Where Inferred Mineral Resources
were included, more conservative modifying factors were applied to reflect the added risk of
including Inferred Mineral Resources in the financial analysis.
8
Table 3 : Production Target - Theta Project
Mineral Resource
Category in LoM
Plan
Indicated
Inferred
Subtotal
Indicated
Inferred
Subtotal
Indicated
Inferred
Subtotal
Indicated
Inferred
Subtotal
Total Indicated
Total Inferred
Total
Pit
Browns Hill
Iota section of
Columbia Hill
Theta Hill
Dumps
Grade
g/t
2.30
2.03
2.23
2.38
5.53
2.53
1.60
1.32
1.48
1.49
1.49
2.21
1.81
2.09
Reef
Tonnes
kt
489
181
670
1 696
83
1 778
557
438
995
418
418
2 741
1 119
3 861
Au Content
kg
1 124
368
1 492
4 033
457
4 490
891
579
1 470
622
622
6 049
2 026
8 075
oz
36 135
11 831
47 967
129 673
14 694
144 367
28 662
18 604
47 266
20 007
20 007
194 470
65 137
259 607
The production target includes 25% of Inferred ounces.
ORE RESERVE
The Ore Reserve statement from the May ‘19 FS is presented below. The Ore Reserve calculation
considered Mineral Resources in the Indicated category as the Theta Project does not contain any
Measured Mineral Resources (Table 4). The graph below (Figure 3) illustrates the effect of the
modifying factors on the diluted scheduled tonnes for the Theta Project. Pit designs are provided
in Appendix A.
Table 4 : Ore Reserves – Theta Project
Ore Reserve
Pit
Category in LoM Plan
Probable
Browns Hill
Probable
Iota section of Columbia Hill
Probable
Theta Hill
Total
Grade
Reef Tonnes
g/t
kt
3.24
564
2.54
1 253
2.76
493
2.76
2 310
Au Content
kg
oz
1 826 58 699
3 189 102 513
1 362 43 798
6 377 205 010
Notes:
The Ore Reserve cut-off grade is 0.4 g/t.
Totals in the Ore Reserve may not add-up due to rounding.
No Inferred Mineral Resources have been included in the Ore Reserve.
Gold price of USD 1 300/oz used to provide the LoM optimised pits converting 61% of the 358 koz Indicated
Mineral Resource to Probable Ore Reserves.
All Ore Reserves reported are delivered to the plant.
The Mineral Resource to Ore Reserve conversion requires application of appropriate factors
which would account for any changes to the Mineral Resources (Figure 6) in the life of mine plan
as a result of mining the ore. As part of the technical studies the potential ore loss and dilution to
the Mineral Resources was determined and applied to the resources available for conversion to
Ore Reserves. The ore loss reduces the tonnage and content, while the dilution would add
9
additional tonnage with no gold content. Note ore reserve included previously undiscovered reefs
(Bevetts and Shale Reef).
Notes:
1. RIMP = Mineral Resources in Life of Mine Plan.
2. RARC = Mineral Resources available for Ore Reserve conversion.
Figure 6 : Mineral Resources to Ore Reserves
CAPITAL COSTS
Mining capital has taken into consideration best environmental practices in an effort to minimise
the impact of operations. This has resulted in some additional capital expenditure which has been
offset by the reduced price paid for the new mill. The mining capital also considers the
construction of haul roads, site water management and site establishment of mining contractor.
Some additional capital has been allowed for to install shared infrastructure such as change
houses and additional office space, albeit that this expenditure is small in the overall capex
requirement.
The largest component of the project capital is the new processing plant and the numbers have
been updated to reflect the increased throughput study which has also included the integration
of the second hand mill purchased in October 2019 (see ASX release 28 Jan 2020 “Results of the
Independent Plant Design Optimisation Study).
The plant cost includes the installation of a new crushing, milling (including integration of
secondhand mill purchased), gravity, CIL, elution, gold room, cyanide destruction and tailings
filtration circuits. 46% of the tailings will need to be filtered in order to produce a product to
10
assist in constructing a stable tailings dam that can accommodate the deposition volumes on the
dam. Without this tailings filtration circuit the tailings dam would not be able to accommodate
the full volumes for the project.
Some additional capital has also been included to upgrade the incoming power supply system for
the increased power requirement. The total available power supply at the main ESKOM
substation is sufficient for the project requirements.
The positioning and design of the plant has been carefully considered to allow for future
expansion opportunities and organic growth (Figure 7).
Figure 7 : TGME Plant Layout Showing 600 ktpa CIL Plant & Expansion to 1.2 Mtpa
The capital costs have all been developed in ZAR and then converted to USD at the exchange rate
relative to the model. In the Base Case an exchange rate of 16.00 ZAR/USD was used and is
reflected in the table below.
11
Table 5 : Optimised Study Capital Summary
Capital Expenditure
Mining Capital
Total Direct Mining Capital
Mining Capital Contingency
Total Mining Capital
Plant Capital
Total Plant
TSF 1 Phase 1
Plant Capital Contingency
Total Plant Capital
Other Non-Direct Capital
Total Other Non-Direct Capital
Other Capital Contingency
Total Other Non-Direct Capital
Total Capital (excl. Contingencies)
Total Capital Contingencies
Total Capital
Exchange Rate ZAR/USD
Total Capital
USDm
To Peak Funding
USDm
4.8
0.7
5.5
2.7
0.4
3.1
20.0
2.3
1.3
23.5
20.0
0.9
1.1
22.1
2.2
0.2
2.4
29.2
2.2
31.4
16.00
1.4
0.1
1.5
25.0
1.7
26.7
16.00
Notes:
ZAR/USD exchange rate of 16.00 used for conversion.
Financial Summary (LoM Average Gold Price of $1 500/oz)
Total capital requirement $31.4 million
Peak Funding is defined as capital required to first gold being produced and sold (i.e. first revenue)
The capital schedule over the life of the project is illustrated below and reflects the exchange
rate used in the Base Case scenario at 16.00 ZAR/USD. The capital in ZAR terms has increased
slightly over the May ’19 FS due to increases in plant and mine throughput however this has
been mitigated by the weaker ZAR/USD exchange rate.
12
Figure 8 : Monthly Capital Schedule (USD)
ECONOMIC ANALYSIS
Minxcon performed an independent economic analysis on the Project’s Mineral Resources and
at three gold price and exchange rate scenarios; low, mid and high and labelled as Lower Case,
Base Case and Stretch Case respectively. The financial results all show significant improvements
over the May ’19 FS and continue demonstrate a robust mining project.
The Lower Case scenario used price and exchange rate forecasts based on the median of various
banks, brokers and analyst forecasts, converted to real terms and based on a forecast in February
2020. Given the rapid increase in gold price and exchange rates (ZAR/USD), it was considered
prudent to use a forecast developed during a reasonably stable period.
Beyond 2024, a constant long-term forecast is applied for the remaining LoM. The inflation rate
was sourced from Investec.
The table below illustrates the forecasts for the first five years as well as the long-term forecast
used in the financial model.
Table 6 : Macro-economic Forecasts & Commodity Prices Used in Lower Case Scenario
Item
Unit
2020
2021
2022
2023
2024
Gold Price (Real)
Exchange Rate
(Real)
Gold Price
Gold Price
USD/oz
ZAR:USD
1 514
14.96
1 456
15.17
1 420
14.81
1 341
14.48
1 308
14.48
Longterm
1 350
14.48
ZAR/oz
ZAR/kg
22 649
728 196
22 088
710 130
21 030
676 136
19 418
624 292
18 940
608 930
19 548
628 482
Source: Median of various Banks and Broker forecasts (Minxcon), Investec as at February 2020.
13
For the Base and Stretch Cases scenarios, the company and Minxcon took a view on reasonable
gold and exchange rates that were not too conservative, in the Base Case scenario, and not too
aggressive in the Stretch Case Scenario.
The NPV is derived from post-royalties and tax, pre-debt real cash flows, after taking into account
operating costs, capital expenditures for the mining operations and the processing plant and
using forecast macro-economic parameters. The DCF valuation was set up in months, but also
subsequently converted to calendar years ending December. The annual ZAR cash flow was
converted to USD using the relevant exchange rates determined for each scenario.
The mine plan includes predominantly Probable Mineral Reserve with a portion of Inferred
Mineral Resources (approximately 25% on gold content basis), which will be practically required
to be mined in order to extract the Indicated Mineral Resources, except for the waste rock dump
material which has been scheduled as a small up front volume and the remainder at the back end
of the processing schedule.
The Project NPVs are shown in Table 7 below and continue to reflect a financially robust project.
Table 7 : NPVs at Various Discount Rates (Real Terms)
Item
Unit
NPV @ 0%
NPV @ 5%
NPV @ 7.5%
NPV @ 10%
NPV @ 15%
Internal Rate of Return (IRR)
USDm
USDm
USDm
USDm
USDm
%
Lower
Case
$1 369/oz
74
61
50
41
35
92.7%
Base
Case
$1 500/oz
104
85
71
60
51
123.0%
Stretch
Case
$1 600/oz
125
104
87
74
63
157.2%
May ’19
FS
$1 257/oz
66
50
38
29
22
65.1%
45
150
30
100
15
50
0
0
(15)
(50)
1 3 5 7 9 1113151719212325272931333537394143454749515355575961636567697173757779818385
Cash Flow
Months
Cumul ative Ca sh Flow (USD million)
Ca s h Flow (USD million)
The monthly and cumulative cash flow over the life of mine for the Base Case Scenario is shown
in the figure below in USD terms. The operation has a peak funding requirement of $27.0 million
and a payback period from start of production is 8 months.
Cumulative Cash Flow
Figure 9 : Monthly and Cumulative Cash Flow USD (Undiscounted) Base Case 16.00 ZAR/USD
14
Minxcon performed single-parameter sensitivity analyses based on the real cash flow to ascertain
the impact on the NPV. For the DCF, the commodity prices, exchange rate and grade have the
most significant impact on the sensitivity of the project followed by the mining and plant
operating cost. The project is least sensitive to capital non-direct costs.
Figure 10 : NPV Sensitivity to Gold Price (Base Case $1 500/oz and 16.00 ZAR/USD)
The graph below reflects the project sensitives to various input costs
Figure 11 : Project Sensitivity USD (NPV5.0%) at Base Case of $1 500/oz and 16.00 ZAR/USD
15
The Optimised Study has allowed for the lower AISC material to be mined and processed at the
start of the schedule and has resulted in further de-risking of the project.
1,800
1,600
1,400
USD/oz)
1,200
1,000
800
600
400
200
-
1
6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
Months in Production
Other Costs (AIC)
Off-Mine Overheads (AISC)
Reclamation
SIB (AISC)
Royalties (Operating)
Other Cost (Operating)
Plant Cost (Operating)
Mining Cost (Operating)
Realised Gold Price
Figure 12 : AISC cost on Monthly Basis
The table below reflects the operating data for the project and the improvements in several areas
as a result of increasing the annual throughput by 20% from 500 ktpa to 600 ktpa in the plant. In
addition, by optimizing the mine schedule and starting the mining on a smaller pit with pushbacks
throughout the LOM and further optimization of mining benches in the lower sections of the pits,
the economic metrics are significantly improved.
The decrease in grade in the mine schedule is a reflection of the company making adjustments
to the mining areas to take into consideration environmental improvements to the project. These
improvement opportunities have been identified through the comprehensive reviews by the
environmental specialists as part of the environmental authorization amendment process.
16
Table 8 : Production Data
unit
Base
Case
$1 500/oz
May ’19 FS
$1 257/oz
tonnes/month
50 802
42 215
tonnes/month
50 000
42 028
kt
kt
kt
Tonnes w: tonnes ore
Tonnes w: tonnes ore
3 861
45 750
49 611
11.8
8.2
2 520
33 677
36 198
13.4
kt
2 741
2 310
oz
kt
194 470
1 119
205 010
211
oz
65 137
14 414
g/t
oz
oz
oz
oz
g/t
g/t
%
2.09
259 607
234 063
3 080
36 957
2.09
1.88
90.2%
2.71
219 425
200 905
3 348
40 176
2.71
2.48
91.6%
USD per oz
855
760
USD per oz
Months
Months
989
76
80
933
57
60
Description
Monthly Mining Production Rate
(Average)
Monthly Plant Feed Production Rate
(Max)
Total Ore Tonnes Mined
Waste Tonnes Mined
Total Tonnes Mined
Strip Ratio
Backfill Ratio
Total Ore Indicated Resource Tonnes
Mined
Total Ore Indicated Resource Content
Total Inferred Mineral Resources Mined
Total Inferred Mineral Resources
Content
Average Mined Grade
Total Oz in Mine Plan
Gold Recovered
Average ounces recovered per month
Average ounces recovered per annum
Grade Delivered to Plant
Recovered grade
Yield/Recovery
All in Sustaining Costs ("AISC" base
case)
All in Costs ("AIC" base case)1
Life of Mine
Life of Project (Processing)
Notes:
1. AISC + non-sustaining capital expenditure.
The recoveries used in the Optimised Study are a continuation of the work completed for the FS.
Over 200 laboratory bottle rolls were done on the Reverse Circulation chip samples during the
drilling campaign to ensure that the material being sampled would continue to demonstrate the
oxidised nature of the ore and return > 90% leach recoveries.
For the feasibility study a selection of samples were identified by Minxcon that provided a fair
representation of the various reefs. These samples were then composited and sent to SGS
Laboratories for a metallurgical test work campaign. The results from this campaign were used
for the process plant design as well as for the gold production model that flowed through into
the financial model.
All the results continue to support a metallurgical recovery in a standard CIL plant of > 90%.
17
STRESS TEST FOR PRODUCTION TARGET
The Optimised Study has included a portion of Inferred Mineral Resources as summarized in the
table below. See Production Target in Table 3 for more detail. In order to provide a stress test to
the project economics a model was run which excluded all the inferred resources from the
schedule. The results are shown below
Table 9 : Production Target Summary
LoM Production Summary
Total Indicated Ore
Total Inferred Ore
Total Ore
Total Waste Tonnes (kt)
Stripping Ratio Including Dumps
Stripping Ratio Excluding Dumps
Grade
g/t
2.21
1.81
2.09
Reef Tonnes
kt
2 741
1 119
3 861
Au Content
kg
oz
6 049
194 470
2 026
65 137
8 075
259 607
45 750
11.8
13.3
The company has also completed an economic evaluation of the optimized mine schedule
without the inferred resources and the project continues to demonstrate strong economic
performance.
Table 10 : Stress Test Financials - Optimised Study Mine Schedule Exc. Inferred Resources
Base Case May ’19 FS
$1 500/oz $1 257/oz
73
66
Item
Unit
NPV @ 0%
USDm
NPV @ 5%
USDm
62
50
NPV @ 7.5%
USDm
52
38
NPV @ 10%
NPV @ 15%
Internal Rate of Return (IRR)
Total ounces in Mine plan
Total Oz Recovered
Average ounces recovered per month
Average Grade to Plant
Benefit-Cost Ratio/Money on Investment5.0
Return on Investment5.0
Average Payback Period (From Start of Production)
Total Capital Requirement
Peak Funding Requirement
Peak Funding Month
Revenue over LoM (Undiscounted)
EBITDA over LOM (Undiscounted)
Net Cash Flow over LoM (Undiscounted)
Break-even Milled Grade (Excluding Capex)
Break-even Milled Grade (Including Capex)
Break-even Gold Price (Excluding Capex)
Break-even Gold Price (Including Capex)
USDm
USDm
%
oz
oz
oz
g/t
Ratio
%
Month
USDm
USDm
Month
USDm
USDm
USDm
g/t
g/t
USD/oz
USD/oz
45
38
106.4%
194 470
177 049
2 766
2.21
3.4
237%
9
31.4
26.7
9
265.0
108.1
73.0
1.3
1.6
886
1 064
29
22
65.1%
219 425
200 905
3 348
2.71
2.8
182%
14
34.3
29.2
21
252.6
99.6
65.7
1.6
2.0
760
933
Exchange Rate
ZAR/USD
16.00
14.01
18
Table 11 : Stress Test Cost per Ton - Optimised Study Mine Schedule Exc. Inferred Resources
Item
Net Turnover
Mine Cost
Processing Costs
On-Site Other Costs
Royalties
Operating Costs
SIB Capex
Reclamation
Off-Mine Overheads
All-in Sustainable Costs (AISC)
Capital
All-in Costs (AIC)
All-in Cost Margin
EBITDA*
EBITDA Margin
Exchange Rate (ZAR/USD)
ZAR/Milled USD/Milled
tonne
tonne
1 547
96.7
364
22.7
342
21.4
138
8.6
37
2.3
881
55.1
0
0.0
17
1.1
18
1.1
916
57.2
183
11.5
1 099
68.7
29%
29%
631
39.4
41%
41%
16.00
16.00
Table 12 : Stress Test Cost per Ounce - Optimised Study Mine Schedule Exc. Inferred Resources
Item
Net Turnover
Mine Cost
Processing Costs
On-Site Other Costs
Royalties
Operating Costs
SIB Capex
Reclamation
Off-Mine Overheads
All-in Sustainable Costs (AISC)
Capital
All-in Costs (AIC)
EBITDA*
Exchange Rate (ZAR/USD)
Note: * Excludes Capex
ZAR/Gold oz
23 952
5 631
5 296
2 137
580
13 645
0
263
272
14 179
2 841
17 019
9 773
16.00
USD/Gold oz
1 497
352
331
134
36
853
0
16
17
886
178
1 064
611
16.00
MINING METHOD
The mining method selected for this project is modified terrace mining (Figure 13) and is suited
to the mountainous profile of the current topography.
The orebodies are considered stratified and on an inclined mountain. The ore will be extracted
on a flat surface whereby all the ore is extracted on the horizontal plane via ripping, loading and
hauling.
Th