Annual Report to shareholders
Released
Released
Announcement PDF
T HOT A
1
GOLD MINE· S
2021
ANNUAL
REPORT
Contents
Chairman’s Letter
Page
3
4
Environmental, Social &
Governance (ESG)
26
31
34
Directors’ Report
41
51
Directors’ Declaration
58
60
Financial Statements
62
101
Shareholders Information
Theta Gold Mines Limited
Ore Reserve and Mineral
Resource Statement
Corporate Governance
Statement
Remuneration Report
(Audited)
Auditor Independence
Declaration
Independent Auditor’s Report
107
110
2
OVERVIEW
FY 2021 HIGHLIGHTS
TGME UNDERGROUND PROJECT PRE-FEASIBILITY STUDY (PFS)
FINANCIAL SUMMARY
CAPITAL COSTS
ECONOMIC ANALYSIS
OPERATING COSTS
ORE RESERVE
ENVIRONMENTAL AUTHORISATIONS
20
ENVIRONMENTAL AND LICENSING
COMMUNITY RELATIONS
EXPLORATION & RESOURCES
FINANCIAL
CORPORATE
OUTLOOK
Mining Rights and
Applications for Mining Rights
Review of Operations
Corporate Directory
Chairman’s Letter
Dear Fellow Shareholders
On behalf of the Board of Directors, I am pleased to present the
2021 Annual Report for Theta Gold Mines Limited (ASX: TGM |
OTC: TGMGF). In the last twelve months, the company has changed
direction to underground mining initially to deliver a path to gold
production with the open pit mines pushed back in the mine schedule.
Underground mining will deliver higher-grade ore to the gold plant,
a smaller environmental footprint, access to the larger resource (4.5
Moz of underground mineral resources) and increased support from
the local community.
The company has 6.1 Moz of gold resources under management. The
new multi mine strategy delineated by the Board set a goal of 160,000
ounces per annum over 5 years, offering a clear growth profile in
production and share value.
Environment, Social and Governance (ESG) is enhanced by the TGME
Underground Project. The project is an extension of three existing
underground mines. There will be only minor new environmental
disturbance as infrastructure will be placed on the existing footprint,
and higher-grade ore will lead to reducing chemical consumption and
processing cost per ounce of gold. The social contract with the local
population will be further enhanced by mining underground which is
well understood in the area. The region has 150 years of underground
mining history.
The market capitalisation of the company sits in the top 150 resource
companies listed on the ASX. Theta has shown an ability to attract large
funds to its share register as the project has progressed. 2Invest AG
(controlled by Deutsche Balaton AG from Germany) has supported
the company with a debt (via issuance of a series of secured bonds)
and equity package post year end. This is the company’s first major
investment from a European fund. There was a steady re-positioning
of the company from exploration to development as the company looks
towards the next major transition to a gold producer, now focussed on
high-grade underground mining.
The company has adjusted its five-year plan which targets 6 underground
mine developments, TGME Underground Project (Frankfort, Beta,
CDM), Rietfontein, Vaalhoek and Glynn’s Lydenburg. The open-pit
mines will be pushed back in the mine schedule and will be added post
permitting, which is suffering from an elongated process. This 6-mine
strategy provides the company with a clear organic growth path for the
project with access to over 4.5 Moz of underground resources.
The maiden underground mine schedule showed strong project
metrics in the April 2021 Pre-feasibility Study and added further value
to shareholders. The key project metrics at US$1570 per ounce gold
price shows an increase in production to a peak of 70,000 oz per year,
extending the Life of Mine (LOM) to 7.6 years for stage one, with low
costs (all-in-Sustaining-Cost (AISC) US$905 per ounce), Internal
Rate of Return (IRR) 82% and EBITDA increased over US$60 million
from the open pit project to US$241.2 million; at current gold price
environment the start-up project would generate significantly more
profits. These numbers demonstrates that profitable underground
mining is achievable across the entire 620sq km goldfield currently
under management.
Theta has significant advantages over its ASX peers with an ability to
deliver low-cost gold ounces (at less than US$12 per ounce discovery
cost), ownership of its own goldfield and a pipeline of projects which
can take Theta to a mid-tier producer. We expect an exciting 2022 as we
work towards delivering the stage one TGME Underground Project.
This year, the company achieved a tremendous amount, including
a new executive team appointed in South Africa with experienced
miners CEO Mitford Mundell and COO Jacques Duo Triou, both exHarmony candidates, a maiden underground mine schedule, resources
and reserves upgrades, and funding from new investors including a
recognisable European fund.
Over the next 12 months, the company will work on completing trail
mining at the TGME Underground Project, completing the Definitive
feasibility Study for the TGME Underground Project, a resource
upgrade with increases in the mine schedule to add more gold ounces
for shareholders, and early capital expenditure spends including long
lead items orders.
We appreciate the continued
support from our shareholders,
and we welcome new shareholders
to the share register. The company
looks forward to continuing to
deliver good news and positive
updates for shareholders in 2022.
Thank you for your continued
support.
Charles (Bill) Guy
Chairman
29 October 2021
Annual Report 2021
3
1
REVIEW OF OPERATIONS
4
Theta Gold Mines Limited
OVERVIEW
Theta Gold Mines Limited controls the Eastern Transvaal Gold
Fields, where South Africa’s gold mining industry began almost
130 years ago.
The Transvaal Gold System sits geological on the eastern side of
Bushveld Complex the largest igneous intrusion on earth (Figure
1), where 40-50% of world’s gold production came out of the
globally-known Witwatersrand Goldfield.
Incorporating only
6 of more than 40
previously
developed mines
Rapid production
ramp-up over the
next five years to
+160koz/a
Low initial
development
capital
Controls over
62,000 hectares of
gold mining rights
Initiating the
operationalisation
of its developmentready 6m oz initial
resource base
Can be selffunded due to
early net cash
generation
A high growth
investment
opportunity
Theta Gold Mines Limited (“the Company” or “Theta Gold”) is a gold exploration and development company that holds
a range of prospective gold assets in a world-renowned South African gold mining region. The Company’s shares are dual
listed on the Australian Securities Exchange (ASX: TGM) and the OTC Markets in the United States (OTC: TGMGF) with
Depository Trust & Clearing (DTC) Eligibility.
The Company’s TGME Underground Project consists of Beta, Frankfort, and the CDM Mines. The TGME Underground
Project is located next to the historical gold mining town of Pilgrim’s Rest, in the Mpumalanga Province, some 370km
northeast of Johannesburg by road or 95km north of Nelspruit (the Provincial Capital City).
The Company is currently focused on the big picture strategy to deliver long term organic growth, with projects focusing
on the evaluation and permitting of six mines, targeting 160,000 ounces per annum, with the TGME Underground Project
(Phase 1) incorporating the first three mines. In April 2021 Theta declared a maiden underground mining reserve of
419,000 oz @ 5.49 g/t Gold. This first Maiden Underground Prefeasibility Study and Mining Reserve is based on only 16%
of the 4.5m oz Au underground gold resource and incorporates only three mines out of a total of 43 historical mines across
the project area.
Annual Report 2021
5
*
~1"1pl1Pl o<J l\o; I~• • • O~lollr
*
A
N
.....::
-Goldo.,p;,,a
_,._.
-c.,,,_,.
-T-~p
--
*
1"-Gcld-L
Eastern Transvaal
Gold Fields
~W)
-~um-<>
r- --
- w"""'"""""$-:Pitgrim's Rest
Go!d Field
_..,_
Sabie Gold Field
Figure 1: Location of Theta Project
6
Theta Gold Mines Limited
FY 2021 HIGHLIGHTS
Resource Upgrade
New 419,000 oz @ 5.49 g/t Gold Maiden Underground
Mining Reserve declared
♦ TOTAL 580,000 oz @ 3.98 g/t Global Mining Reserve
(Open Pit & Underground)
♦ 63% Conversion factor for Maiden Underground
Mining Reserve
♦ 3.5 Moz of Underground resource (Inferred) remaining
for future conversion potentially into Mining Ore Reserve
♦
Prefeasibility Study for first 3 underground Mines (TGME
Underground Project)
Corporate
Theta Gold dual listed on ASX and Unites States OTC
Markets (OTC: TGMGF), with eligibility for electronic
trading (DTC Eligible)
♦ AU$8.93 million of capital raise completed
♦ Post year-end the Company successfully completed
in excess of A$10 million funding, introducing new,
cornerstone institutional investors to the register,
including our first large European fund.
♦ The Company undertook a modest investment, through
the issue of shares, in the Bullion Asset Management
company.
♦
Pay-back period from first gold pour of 13 months
By the third year, recovering over 60,000 oz Au per annum
♦ LOM is 7.67 years
♦ US$241.2 million EBITDA over LOM
♦ Internal Rate of Return (IRR) 82%
♦ US$91.2 million Net Present Value (NPV)
♦ US$905/oz Au all-in sustaining cost (AISC) over
LOM, bottom quartile for South Africa and Australian
producers
♦
♦
Annual Report 2021
7
TGME UNDERGROUND PROJECT
PRE-FEASIBILITY STUDY (PFS)
The initial study focused on the easy access of 684,000 oz Au in the Measured and Indicated categories of the TGME
Underground Resource for the Beta, Frankfort and CDM areas. (see Section 3). The team achieved a conversion factor of
63% from resource to mining reserve in those areas. A further 3.5Moz Au of inferred resources is available to be upgraded
to the Measured and Indicated resource category and potentially a portion could be converted into mining reserves.
UG Operations
Unit
Forecast
USD Au
Price
1,500
1,600
1700
1,800
2,000
NPV @ 5%
USDm
91
81
98
115
132
166
Internal Rate of Return (IRR)
%
82%
75%
88%
100%
111%
134%
Total Oz in Mine Plan
oz
418,845
418,845
418,845
418,845
418,845
418,845
Total Oz Recovered
oz
353,012
353,012
353,012
353,012
353,012
353,012
Average Payback Period (from
Start of Mining)
Months
22
23
21
18
17
16
Peak Funding Requirement
USDm
36
36
36
36
36
36
EBITDA over LOM
(Undiscounted)
USDm
241
222
254
286
318
382
All-in Sustainable Costs (AISC)
USD/oz
905
900
909
917
926
942
Gold Price
USD/oz
1,570
1,500
1,600
1,700
1,800
2,000
Exchange Rate
ZAR/USD
15.89
15.89
15.89
15.89
15.89
15.89
Table 1 : Phase 1 UG results at various gold price scenarios
Surface infrastructure plan Beta Underground
Mine and plant layout
8
Theta Gold Mines Limited
Figure 2: TGME Underground PFS
INITIAL 16 % OF
UNDERGROUND
MINERAL
RESOURCE
Pay-back period from first
gold 13 months
Pay-back period from
start of mining 22 months
419 Koz delivered to plant
over Life of Mine
By third year of
production, almost 70 koz
/ year (3 production units)
Life of Mine (LoM)
7.67 years
Internal Rate of
Return 82%
$ 905 / oz all-in sustaining
cost (AISC) over LoM
(bottom quartile SA
Producer)
Theta has demonstrated, through the first phase
underground PFS, excellent project economics (Figure
2) for what it believes to be only a small portion of the
underground resource and will continue to build up its
Mining Reserves during the year by progressing Rietfontein
through to PFS level, while concluding detailed designs for
the Phase 1 TGME Underground Project.
$241.2 million EBITDA
over LoM
$91.2 million Net
Present Value
Total Capital Expenditure (CAPEX)
$79 million LOM includes:
•
•
•
•
Peak CAPEX - $36M (Start-up Plant and Beta Mine
development )
Total Direct CAPEX - $54M
Total SIB CAPEX - $13.7M
Total contingent CAPEX - $10.8 M
The TGME Underground PFS shows that the narrow highgrade reefs system can be mined with modern mechanized
mining techniques (safer, increased productivity and
minimum dilution), and that the gold can be recovered
by utilizing modern metallurgical technologies (Ultrafine
grinding and Intense CIL).
Annual Report 2021
9
FINANCIAL SUMMARY
Financial modelling was completed over a range of gold prices. The forecasted price is considered the Base Case as per the
completed PFS.
Item
Unit
Forecast
$1,500/oz
$1,600/oz
$1,700/oz
$1800/oz
$2,000/oz
NPV @ 0%
USDm
122.9
109.0
131.5
153.1
174.7
218.2
NPV @ 2.5%
USDm
105.7
93.7
113.5
132.5
151.5
189.7
131.9
165.6
NPV @ 5%
USDm
91.2
80.8
98.3
115.1
NPV @ 7.5%
USDm
79.0
69.8
85.4
100.3
115.2
145.2
NPV @ 10%
USDm
68.6
60.5
74.4
87.7
101.0
127.8
NPV @ 12.5%
USDm
59.7
52.6
65.0
77.0
88.9
112.8
NPV @ 15%
USDm
52.1
45.7
57.0
67.7
78.4
99.9
Internal Rate of Return (IRR)
%
82%
75%
88%
100%
111%
134%
Total ounces in Mine plan (2)
oz
418,845
418,845
418,845
418,845
418,845
418,845
Total Oz Recovered (2)
oz
353,012
353,012
353,012
353,012
353,012
353,012
Average ounces recovered per month
oz
4,253
4,253
4,253
4,253
4,253
4,253
Average Grade to Plant
g/t
5.51
5.51
5.51
5.51
5.51
5.51
Benefit-Cost Ratio/Money on
Investment5.0
Ratio
5.8
5.4
6.2
6.9
7.7
9.3
Capital Gain5.0
%
483%
438%
516%
593%
671%
827%
Month
22
23
21
18
17
16
Average Payback Period (from First Gold)
Month
13
14
12
9
8
7
Total Capital (2)
USDm
79
79
79
79
79
79
Peak Funding Requirement (2)
USDm
36
36
36
36
36
36
Peak Funding Month
Month
23
23
23
23
23
23
Revenue over LoM (Undiscounted)
USDm
545
524
559
594
629
699
EBITDA over LOM (Undiscounted)
USDm
241
222
254
286
318
382
Net Cash Flow over LoM (Undiscounted)
Average Payback Period (from Start of
Mining)
USDm
123
109
131
153
175
218
Break-even Milled Grade
(Excluding Capex)
g/t
3.1
3.2
3.0
2.9
2.7
2.5
Break-even Milled Grade
(Including Capex)
g/t
3.9
4.0
3.8
3.6
3.4
3.1
Break-even Gold Price
(Excluding Capex)
USD/oz
866
861
870
879
887
903
Break-even Gold Price
(Including Capex)
USD/oz
1,089
1,083
1,092
1,101
1,109
1,125
Gold Price
USD/oz
1,570
1,500
1,600
1,700
1,800
2,000
Exchange Rate (1)
ZAR/USD
15.89
15.89
15.89
15.89
15.89
15.89
Table 2 : Key Aspects of UG Operations PFS
Note:
Money On Investment (MOI) is calculated as the present value of income flow over the present value of investment (5% discount rate); calculated in USD terms.
EBITDA = Earnings before interest, tax, depreciation and amortisation (excludes Capital)
Notes:
All values converted from ZAR to USD at the relevant exchange rate
Capital costs in the PFS Study were converted from ZAR.
10
Theta Gold Mines Limited
The project also demonstrates a robust NPV across a wide range of gold prices as can be seen in the graph below.
250
200
c 150
~
o 100
V>
2.
~
z
50
0
·SO
1,000
1,100
1,200
1,300
1,400
1,500
1,600
1,700
1,800
1,900
2,000
2,100
2,200
Gold Price (USO/oz)
Figure 3: NPV Sensitivity to Gold Price
The AISC costs for the UG PFS Study continue to reflect a project that is at the bottom quartile when compared to South
African peer mines.
By the third year of production, over 60,000 oz Au per year of gold is modelled to be recovered as demonstrated in the
graph below. Years 7 and 8 is only a reflection of the limitation of excluding current inferred resources. Plant capacity will
be filled by either current inferred resources or from the large stockpiles of old surface dumps, which will have a significant
upside to this base case.
Annual Report 2021
11
CAPITAL COSTS
In order to draft a capital cost estimation for the three
underground operations, various quotations and pricing
were sourced. Where new quotations could not be sourced,
older quotations and projects of a similar size and nature
were used to benchmark costs. These costs were escalated
to align with the current financial year. The final capital
estimation is dated February 2021.
The capital estimations are based on items that fall within the
capital footprint of the Project. The capital footprint is defined
by the battery limits for the engineering and infrastructure
design within three main areas. These areas include:♦ Beta underground operation and associated surface facilities;
♦ Frankfort underground operation and associated surface
facilities;
♦ CDM underground operation and associated surface
facilities; and
Bill of Quantitites (BoQ’s) were drafted for these areas
on which costing has been done. Where BoQ’s for work
breakdown structure items are not applicable, batch costing
has been done per unit volume.
The main capital cost drivers for the underground operations
include the establishment of the underground conveyor
systems, mining and ancillary fleet not leased and the
establishment of the surface mine sites at each of the operations.
The capital costs have all been developed in ZAR and
then converted to USD at the exchange rate relative to the
model forecast. The average exchange rate over the LOM
is 15.89 ZAR/USD, while the total capital requirement is
US$78.5m. The peak funding requirement is US$36m, with
the remaining capital-funded from cash flow. Total capital is
demonstrated in the table below.
Description
TGME UG Ops
USDm
Mining Capital
Total Direct Mining Capital
27.1
Stay in Business Mining Capital
13.7
Mining Capital Contingency
5.4
Total Mining Capital
46.2
Plant Capital
Total Direct Plant Capital
22.6
Stay in Business Plant Capital
0.0
Plant Capital Contingency
4.5
Total Plant Capital
27.1
Other Capital
Total Other Non-Direct Capital
4.2
Stay in Business Other Capital
0.0
Other Capital Contingency
0.8
Total Other Capital
5.1
Total Capital
Total Direct Capital
54.0
Total SIB Capital
13.7
Total Capital Contingencies
10.8
Total Capital
78.5
Note:
ZAR/USD exchange rate of 15.89 used for conversion | Total capital requirement $78.5 million
12
Theta Gold Mines Limited
Table 3: UG PFS Study Capital Summary
The capital schedule over the life of the project is illustrated below and reflects the appropriate exchange rate as per the
forecast period over the LoM.
30
90
27
§ 25
E
0
20
Ill
70
·e
60
VI
50,
2
I§ 15
~
2
....
Ill
RI
::,
5
0
l
2
-
30,
20
4
I
3
s
4
v,· ars
lnirtia l Mining
Exp. Plant
Sust ini !'IS Other
-~
9
-
u 10
-
0
40 ·a
·a
C
C
«(
c
so, ~
24
C
Initial P1ant
EJ:p. Other
6
2
7
1
0
8
9
10
V
~
'i
:i
E
::,
u
Exp. Mini1ng
Sustaining Pla11t
Co11ti f'lge,ncfe s
Figure 4: Monthly Capital Schedule (USD)
Notes
»
»
»
»
»
»
»
»
»
»
»
Capital in Year 1:Oxide Plant Circuit 30 ktpm
Paste Backfill Plant
Beta Infrastructure
Capital in Year 2 and Year 3:Mostly Beta Infrastructure and Tail-end of Plant Capital
Capital in Year 4:CDM and Frankfort Infrastructure
Sulphide Plant Circuit 15ktpm
Capital Post Year 5:Mostly CDM and Frankfort Infrastructure
Annual Report 2021
13
ECONOMIC ANALYSIS
1,892
USD/oz
ZARUSD
Gold Price (Real)
Exchange Rate (Real)
USDm
NPV @ 15%
82%
52.1
59.7
68.6
79.0
16.00
1,502
2024
16.00
1,469
2025
16.00
1,600
Long-term
75%
45.7
52.6
60.5
69.8
80.8
93.7
109.0
$1,500/oz
100%
67.7
77.0
87.7
100.3
115.1
132.5
153.1
$1,700/oz
111%
78.4
88.9
101.0
115.2
131.9
151.5
174.7
$1800/oz
134%
99.9
112.8
127.8
145.2
165.6
189.7
218.2
$2,000/oz
Table 5: NPVs at Various Discount Rates (Real Terms)
88%
57.0
65.0
74.4
85.4
98.3
113.5
131.5
$1,600/oz
The Project NPVs are shown in Table 5 below and reflect
a financially robust project. The discount rate utilised is the
company’s internal hurdle rate, with a sensitivity to various
discount rates included.
The mine plan includes predominantly Probable Mineral
Reserve. No Inferred Mineral Resources have been included
in the economic analysis.
14
Theta Gold Mines Limited
The monthly and annual cumulative cash flow along with the cumulative cash flow over the life of mine for the Base Case
Scenario is shown in the figures below in USD terms. The underground operations have a peak funding requirement of
$36.1 million and a payback period from the start of mining is 22 months. The payback period from first gold production
is 13 months.
%
USDm
NPV @ 12.5%
Internal Rate of
Return (IRR)
USDm
NPV @ 10%
91.2
USDm
USDm
NPV @ 5%
NPV @ 7.5%
105.7
USDm
NPV @ 2.5%
122.9
USDm
NPV @ 0%
Forecast
Unit
Item
15.93
1,587
2023
Table 4: Macro-economic Forecasts & Commodity Prices Used in Base Case
15.57
1,786
2022
The NPV is derived from post-royalties and tax, pre-debt real
cash flows, after taking into account operating costs, capital
expenditures for the mining operations and the processing
plant and using forecast macro-economic parameters. The
DCF evaluation was set up in months, but also subsequently
converted to calendar years ending December. The annual
ZAR cash flow was converted to USD using the relevant
exchange rates as per the forecast.
Source:
Median of various Banks and Broker forecasts (Minxcon), IMF.
15.39
2021
Unit
Item
Minxcon performed an independent economic analysis on the Project’s Mineral Resources to determine the economic
viability of the Project to declare Ore Reserves. The Base Case utilises the price and exchange rate forecasts based on the
median of various banks, brokers and analyst forecasts, converted to real terms and based on a forecast in January 2021.
The long-term gold price was calculated as the average between the maximum and minimum real-term gold price over the
past ten years. Minxcon also completed a gold price sensitivity at the request of TGM to demonstrate results at various price
environments. The price scenarios considered are constant prices of $1,500/oz, $1,600/oz, $1,700/oz, $1,800/oz and $2,000/
oz. The table below illustrates the forecasts for the first five years as well as the long-term forecast used in the financial model.
~
140
120
c
·~e
Q
......
"'...
-...
7
8
9
"'
100
80
60
V>
2.
~
40
u:
20
.t:
0
~
u'"
"'
:,
C:
C:
-,:
(20)
(40)
0
1
2
3
s
4
6
Years
-
capital Expenditure
-
Annual Cash How Excluding CAPEX _.,_Cumulative Cash Flow
Figure 5: Annual Cumulative Cash Flow USD (Undiscounted) TGM Underground Project Base Case
Minxcon performed single-parameter sensitivity analyses based on the real cash flow to ascertain the impact on the NPV.
For the DCF, the commodity prices, exchange rate and grade have the most significant impact on the sensitivity of the
project followed by the mining and plant operating cost. The project is least sensitive to capital and non-direct costs.
The PFS study has an AISC cost below the forecast gold price from the start of production as illustrated in the graph below.
1,800
1,600
1,400
1,200
1,000
N
0
~
V>
800
:)
600
400
200
0
Years
-
._ -
Plant Cost (Oper•ting)
Other Costs (Operating)
Rovahies (Operatini)
Capital Development (AISC)
Renewals and Replacements (AISC)
Redaimation (AISC)
Other Costs (AISC)
Mining Cost ((Jper•ti~)
-
__________________
-
•lised Gold Price
Figure 6: ASIC cost on Yearly Basis TGME Underground Project
Annual Report 2021
15
OPERATING COSTS
The mining operating cost estimations were completed
utilising the Minxcon first-principles activity-based cost
model. The cost model utilises the mine and engineering
design criteria as well as production schedule inputs to
derive cost rates for the mining and engineering activities.
The underground mining costs for labour, equipment,
consumables, services and utilities have been sourced from
Item
quotations, actual industry stores costs, industry rates and
utility rates. Where costs could not be obtained from these
sources, benchmarking with similar-sized projects and
operations was conducted and historical costs escalated.
A ZAR/USD exchange rate of 15.06 as of 1 February 2021
has been used to convert costs to USD terms for reference
purposes.
Forecast
1,500
1,600
1,700
1,800
2,000
Net Turnover
232
223
238
253
268
297
Mine Cost
72
72
72
72
72
72
Processing Costs
31
31
31
31
31
31
On-Site Other Costs
14
14
14
14
14
14
Royalties
7
6
8
9
10
12
Operating Costs
124
123
124
126
127
129
SIB Capex
6
6
6
6
6
6
Reclamation
0
0
0
0
0
0
Off-Mine Overheads
5
5
5
5
5
5
All-in Sustainable Costs (AISC)
135
134
136
137
138
141
Non-Sustaining Capital
27
27
27
27
27
27
All-in Costs (AIC)
162
162
163
164
166
168
All-in Cost Margin
30%
28%
31%
35%
38%
44%
EBITDA *
103
95
108
122
135
163
EBITDA Margin
44%
42%
45%
48%
51%
55%
Gold in Mine Plan
418,845
418,845
418,845
418,845
418,845
418,845
Gold Recovered
353,012
353,012
353,012
353,012
353,012
353,012
Table 6 : Operating Costs USD/t milled
Note:
* Excludes Capex
16
Theta Gold Mines Limited
Item
Forecast
1,500
1,600
1,700
1,800
2,000
Net Turnover
1,555
1,495
1,594
1,694
1,794
1,993
Mine Cost
484
484
484
484
484
484
Processing Costs
206
206
206
206
206
206
On-Site Other Costs
92
92
93
94
94
96
Royalties
48
43
51
59
66
81
Operating Costs
830
825
834
843
851
867
SIB Capex
39
39
39
39
39
39
Reclamation
0
0
0
0
0
0
Off-Mine Overheads
36
36
36
36
36
36
All-in Sustainable Costs (AISC)
905
900
909
917
926
942
Non-Sustaining Capital
184
184
184
184
184
184
All-in Costs (AIC)
1,089
1,083
1,092
1,101
1,109
1,125
All-in Cost Margin
30%
28%
31%
35%
38%
44%
EBITDA *
688
634
724
815
907
1,090
EBITDA Margin
44%
42%
45%
48%
51%
55%
Gold in Mine Plan
418,845
418,845
418,845
418,845
418,845
418,845
Gold Recovered
353,012
353,012
353,012
353,012
353,012
353,012
Table 7 : Operating Costs USD/oz recovered
Note:
* Excludes Capex
Annual Report 2021
17
ORE RESERVE
2.74
3.98
Open Pit (MR83)
Total
4,530
2,164
385
319
579.46
160.61
28.58
42.33
347.94
koz
Table 8: Ore Reserves – Theta Project
18,023
4,996
889
1,317
10,822
kg
Au Content
18
Theta Gold Mines Limited
The Mineral Resource to Ore Reserve conversion requires the application of appropriate factors which would account for any
changes to the Mineral Resources in the life of mine plan as a result of mining the ore. As part of the technical studies, the
potential ore loss and dilution to the Mineral Resources was determined and applied to the resources available for conversion
to Ore Reserves. The ore loss reduces the tonnage and content, while the dilution would add additional tonnage with no gold
content. Note ore reserve included previously undiscovered reefs (Bevetts and Shale Reef).
An Ore Reserve cut-off of 170 cm g/t has been applied for Beta
An Ore Reserve cut-off of 150 cm.g/t has been applied for Frankfort
An Ore Reserve cut-off of 121 cm.g/t has been applied for CDM
An Ore Reserve cut–off of 0.4 g/t was applied. For the open pit.
A gold price of US$ 1,465 / Oz and an exchange rate of 16 ZAR / USD was used for the cut-off calculation for Beta, Frankfort and CDM
A gold price of US$ 1,300 / oz was used for the cut-off calculation for the open-pit operation
Ore Reserves are reported as total Ore Reserves and are not attributed.
2.31
CDM
Note:
»
»
»
»
»
»
»
4.13
Frankfort
1,662
kt
g/t
6.51
Tonnes
Grade
Beta
Operation
The Ore Reserve statement from the March 21 release is presented below. The Ore Reserve calculation considered Mineral
Resources in the Indicated category as the Theta Project does not contain any Measured Mineral Resources.
~:cfl
ENVIRONMENTAL
AUTHORISATIONS
Theta holds nine (9) mining rights spanning thousands
of hectares. These are MR10167 and MR340 in the North;
MR83, MR341 and MR330 surrounding the central
processing facility in Pilgrims Rest; and MR433, MR10161,
MR358 and MR198 near Sabie in the South.
The Company continues to keep all its Mining Rights in good
standing by ensuring that the various licence conditions
continue to be met.
While environmental authorisations are in place for the
Frankfort, Clewer, Dukes Hill, Morgenzon and Beta Mines
(MR83), Rietfontein (MR358) and Glynn’s Lydenburg
(MR433) mines; this permitting will be amplified for the
optimised methods and increased volumes contemplated in
the revised development strategy, which initially envisages
the re-prioritisation of historically operated underground
mines supported by an upgraded gold processing plant and
tailings backfill.
Since the majority of existing surface gold bearing dumps
were created by the company in the past, these will be
reprocessed with zero additional waste development costs.
This forms part of the company’s general commitment to
concurrent rehabilitation and minimal new surface impacts.
A multi-level proactive stakeholder engagement strategy is
being implemented to ensure that regulators, landowners,
host communities and environmental conservation
organisations are well briefed and supportive of the
company’s development plans.
The purpose of this programme is to reduce the negative
impacts of primary threats to the catchment, thereby
securing the Strategic Water Source Area by facilitating the
establishment of native grasslands and forests, ecological
connectivity and optimisation of the hydrological
functioning of the Blyde River catchment, in which both
the Theta operations are located. The area has 130 years of
mining history demonstrating that mining can operated in
this environment.
The implementation of Theta’s development strategy will
have a dramatic impact on the lives of its host communities
by creating much needed jobs and downstream economic
development; thereby assisting in accelerating the South
African government’s post-COVID economic recovery plan
which would otherwise continue to deteriorate at the mercy
of alien invasive vegetation and illegal miners.
It has come to Theta’s attention post-financial reporting
period via the SA Government Gazette that the Minister
of Forestry, Fisheries and the Environment (“DFFE”) has
declared a fore