Pre-Feasibility Study for Initial Underground Projects
Released
Released
Announcement PDF
13 April 2021
ASX ANNOUNCEMENT
Pre-Feasibility Study for Initial Underground Projects
Theta Gold Mines Limited (“Theta Gold” or “Company”) (ASX: TGM| OTC: TGMGF) is pleased to
announce its Maiden Underground Prefeasibility Study (PFS) for the Beta, Frankfort, and CDM
mines, all of which form part of the Central Northern area and now collectively referred to as
TGME Underground (UG) Project.
HIGHLIGHTS: TGME Phase 1 Underground Project, which excludes the open pits. All numbers in
USD and financials based on forecast gold price of average USD$1,570/oz and ZAR/USD
exchange rate of 15.9.
Pay-back period from first gold 13 months
Pay-back period from start of mining 22 months
419,000 oz Au delivered to plant over initial Life of Mine (LoM)
By the third year, production over 60,000 oz Au/year (recovered)
LoM is 7.67 years
US$241.2 million EBITDA over LoM
Internal Rate of Return (IRR) 82%
US$91.2 million Net Present Value (NPV)
US$905/oz Au all-in sustaining cost (AISC) over LoM, bottom quartile for
South Africa producers
Total LoM Capital Expenditure (CAPEX) US$79 million includes o Peak CAPEX first 3 years US$37M – Oxide and Backfill Plant and Beta Mine
development
o Year 4 US$27M Sulphide Circuit and Frankfort and CDM Mine development
o US$15M of remaining capital to develop and sustain operations
The company continues to honor its commitment to improving the project economics and
expansion of the production profile. The team has delivered a Maiden Underground Prefeasibility
Study based on only 16% of the 4.5m oz Au underground gold resource, and incorporates only
three mines out of a total 43 historical mines across the project area. As well, it considered only
measured and indicated resources for initial inclusion in production and reserve conversion. The
inferred resources of these phase 1 mines, together with more than 40 historical mine sites under
management, will be systematically studied and incorporated into future production modelling.
This is a very positive early step to developing the goldfield.
The initial study focused on the easy access of 684,000 oz Au in the Measured and Indicated
categories of the TGME Underground Resource for the Beta, Frankfort and CDM areas. (Appendix
B). The team achieved a conversion factor of 63% from resource to mining reserve in those areas.
Theta Gold Mines Limited ABN 30 131 758 177
Suite 80, Level 35 (Servcorp), International Tower One, 100 Barangaroo Avenue, Sydney NSW 2000
Tel: +61 2 8046 7584 Email: info@thetagoldmines.com
www.thetagoldmines.com
A further 3.5m oz Au of inferred resources is available to be upgraded to the Measured and
Indicated resource category and potentially a portion could be converted into mining reserves.
Table 1 below sets out the Phase 1 UG results at various gold price scenarios:
Table 1 : TGME Phase 1 Underground Project
Base Case Gold price Gold price Gold price Gold price Gold price
US$1570/oz US$1500/oz US$1600/oz US$1700/oz US$1800/oz US$2000/oz
NPV @ 5%
USDm
91
81
98
115
132
166
Internal Rate of Return (IRR)
%
82%
75%
88%
100%
111%
134%
Total Oz in Mine Plan
oz
418,845
418,845
418,845
418,845
418,845
418,845
Total Oz Recovered
oz
353,012
353,012
353,012
353,012
353,012
353,012
Average Payback Period
(from Start of Mining)
Months
22
23
21
18
17
16
Peak Funding Requirement
USDm
36
36
36
36
36
36
EBITDA over LOM
(Undiscounted)
USDm
241
222
254
286
318
382
All-in Sustainable Costs
(AISC)
USD/oz
905
900
909
917
926
942
Gold Price
USD/oz
1,570
1,500
1,600
1,700
1,800
2,000
UG Operations
Exchange Rate
Unit
ZAR/USD
15.89
15.89
15.89
15.89
15.89
15.89
Figure 1: Surface Infrastructure TGME Underground Mine Layout
2
Theta Gold has demonstrated, through the first phase underground PFS, excellent project
economics for what it believes to be only a small portion of the underground resource and will
continue to build up its Mining Reserves during the year by progressing Rietfontein and other
mines through to PFS level, while concluding detailed designs for the Phase 1 UG Project.
Previously the company announced a five-year plan, which targets four (4) mine developments,
Theta open-pit Starter Project (MR83 only), Theta open pit extension (MR341) and the Rietfontein
and Beta underground mines. This 4-mine strategy provided the company with a clear growth
plan with a combined open pit and underground resource of over 2.75 Moz. The recent detailed
work that was done on Frankfort, Beta and CDM UG mines, together with Theta Phase 1 OP, has
further enhanced this strategy. The Company will expand further regarding this wider scope
during Q2 2021.
The TGME Underground PFS shows that the narrow high-grade reefs system can be mined with
modern mechanized mining techniques (safer, increased productivity and minimum dilution), and
that the gold can be recovered by utilizing modern metallurgical technologies (Ultrafine grinding
and Intense CIL). This proof of concept is part of de-risking the underground projects. The “New
CEO’s Development Strategy” later in April will review how the underground and open pit mines
will be combined to organically grow the production profile.
Chairman Mr Bill Guy stated, “The TGME Underground Prefeasibility Study clearly demonstrates
that the extensive flat high-grade narrow reef systems of East Transvaal Goldfield can be mined
economically, and modern mechanized mining and metallurgy can deliver strong project
economics.
Now that the company has generated a PFS for the TGME Underground Project, we can optimize
our development strategy based on confident numbers. At a 63% conversion ratio, Theta Gold
still has 3.5 million oz Au of underground resources to develop in order to extend LoM and
increase production into the future.
Due to the shallow, high grade and on-reef development characteristics of the ore, our AISC of
US$905 per ounce of gold sits in the bottom quartile of costs for South Africa. At a forecasted
average US$1,570 gold price, EBITA is US$241m from revenue of US$545m and the NPV is
US$91m; all based on a very small proportion of the overall project area. The CAPEX is modest
and staged and production peaks at 70,000 oz Au per annum. This PFS clearly demonstrates very
strong project economics for the underground mines. In real terms, we have only completed the
study on 16% of the total of 4.5m ounces of gold in the underground mineral resource. The team
will complete the Rietfontein PFS in Q3 of this year. The Mining Reserve from Rietfontein can
then be brought into the updated PFS to further increase the production profile.
At Theta Gold, the resource pipeline into the future is strong, and the scale of the potential
resources and the geology in South Africa should not be underestimated. The Company will soon
be a key player in the South African mining industry, a sector that has produced more tons of gold
than any other country when measuring gold bullion tonnage. Over 40% of the world’s gold has
come from the small corner of South Africa that we call home.”
Financial Summary
Financial modelling was completed over a range of gold price environments, using all of forecast
prices and constant prices of US$1,500/oz, US$1,600/oz, US$1,700/oz, US$1,800/oz and
US$2,000/oz. The forecast prices are considered the Base Case as per the completed PFS.
3
Table 2 : Key Aspects of UG Operations PFS
Item
Unit
NPV @ 0%
NPV @ 2.5%
NPV @ 5%
NPV @ 7.5%
NPV @ 10%
NPV @ 12.5%
NPV @ 15%
Internal Rate of
Return (IRR)
Total ounces in
Mine plan (2)
Total Oz Recovered
USDm
USDm
USDm
USDm
USDm
USDm
USDm
(2)
Average ounces
recovered per
month
Average Grade to
Plant
Benefit-Cost
Ratio/Money on
Investment5.0
Capital Gain5.0
Average Payback
Period (from Start
of Mining)
Average Payback
Period (from First
Gold)
Total Capital (2)
Peak Funding
Requirement (2)
Peak Funding
Month
Revenue over LoM
(Undiscounted)
EBITDA over LOM
(Undiscounted)
Net Cash Flow over
LoM
(Undiscounted)
Break-even Milled
Grade (Excluding
Capex)
Break-even Milled
Grade (Including
Capex)
Break-even Gold
Price (Excluding
Capex)
Break-even Gold
Price (Including
Capex)
Gold Price
Exchange Rate (1)
Base Case
US$1,500/oz US$1,600/oz US$1,700/oz US$1800/oz US$2,000/oz
US$1,570/oz
122.9
109.0
131.5
153.1
174.7
218.2
105.7
93.7
113.5
132.5
151.5
189.7
91.2
80.8
98.3
115.1
131.9
165.6
79.0
69.8
85.4
100.3
115.2
145.2
68.6
60.5
74.4
87.7
101.0
127.8
59.7
52.6
65.0
77.0
88.9
112.8
52.1
45.7
57.0
67.7
78.4
99.9
%
82%
75%
88%
100%
111%
134%
oz
418,845
418,845
418,845
418,845
418,845
418,845
oz
353,012
353,012
353,012
353,012
353,012
353,012
oz
4,253
4,253
4,253
4,253
4,253
4,253
g/t
5.51
5.51
5.51
5.51
5.51
5.51
Ratio
5.8
5.4
6.2
6.9
7.7
9.3
%
483%
438%
516%
593%
671%
827%
Month
22
23
21
18
17
16
Month
13
14
12
9
8
7
USDm
79
79
79
79
79
79
USDm
36
36
36
36
36
36
Month
23
23
23
23
23
23
USDm
545
524
559
594
629
699
USDm
241
222
254
286
318
382
USDm
123
109
131
153
175
218
g/t
3.1
3.2
3.0
2.9
2.7
2.5
g/t
3.9
4.0
3.8
3.6
3.4
3.1
USD/oz
866
861
870
879
887
903
USD/oz
1,089
1,083
1,092
1,101
1,109
1,125
USD/oz
ZAR/USD
1,570
15.89
1,500
15.89
1,600
15.89
1,700
15.89
1,800
15.89
2,000
15.89
4
Note:
Money On Investment (MOI) calculated as present value of income flow over present value of
investment (5% discount rate); calculated in USD terms.
EBITDA = Earnings before interest, tax, depreciation and amortisation (excludes Capital)
Notes:
1. All values converted from ZAR to USD at relevant exchange rate
2. Capital costs in PFS Study were converted from ZAR
The project also demonstrates a robust NPV across a wide range of gold prices as can be seen in
the graph below.
Figure 2 : NPV Sensitivity to Gold Price
The AISC costs for the UG PFS continue to reflect a project that is at the bottom quartile when
compared to South African peer mines.
Figure 3 : South African Miners AISC Costs 2019: Minxcon 2020
5
By the third year of production, over 60,000oz per year of gold is being recovered as
demonstrated in the graph below. Years 7 and 8 is only a reflection of the limitation of excluding
current inferred resources. Plant capacity will be filled by either current inferred resources or
from the large stockpiles of old surface dumps, which will have a significant upside to this base
case.
Figure 4 : Annual TGME Underground Project Gold Production (oz)
CAPITAL COSTS
In order to draft a capital cost estimation for the three underground operations various
quotations and pricing were sourced. Where new quotations could not be sourced, older
quotations and projects of a similar size and nature were used to benchmark costs. These costs
were escalated to align with the current financial year. The final capital estimation is dated
February 2021.
The capital estimations are based on items that fall within the capital footprint of the Project.
The capital footprint is defined by the battery limits for the engineering and infrastructure design
within three main areas. These areas include: Beta underground operation and associated surface facilities;
Frankfort underground operation and associated surface facilities;
CDM underground operation and associated surface facilities; and
Bill of quantities (“BoQs”) were drafted for these areas on which costing has been done. Where
BoQs for work breakdown structure items are not applicable, batch costing has been done per
unit volume.
The main capital cost drivers for the underground operations include the establishment of the
underground conveyor systems, mining and ancillary fleet not leased and the establishment of
the surface mine sites at each of the operations.
The capital costs have all been developed in ZAR and then converted to USD at the exchange rate
relative to the model forecast. The average exchange rate over the LoM is 15.89 ZAR/USD, while
the total capital requirement is USD78.5m. The peak funding requirement is USD36m, with the
remaining capital funded from cash flow. Total capital is demonstrated in the table below.
6
Table 3 : UG PFS Capital Summary
Description
Mining Capital
Total Direct Mining Capital
Stay in Business Mining Capital
Mining Capital Contingency
Total Mining Capital
Plant Capital
Total Direct Plant Capital
Stay in Business Plant Capital
Plant Capital Contingency
Total Plant Capital
Other Capital
Total Other Non-Direct Capital
Stay in Business Other Capital
Other Capital Contingency
Total Other Capital
Total Capital
Total Direct Capital
Total SIB Capital
Total Capital Contingencies
Total Capital
Notes:
TGME UG Project
USDm
27.1
13.7
5.4
46.2
22.6
0.0
4.5
27.1
4.2
0.0
0.8
5.1
54.0
13.7
10.8
78.5
ZAR/USD exchange rate of 15.89 used for conversion.
Total capital requirement $78.5 million
The capital schedule over the life of the project is illustrated below and reflects the appropriate
exchange rate as per the forecast period over the LoM.
Figure 5 : Monthly Capital Schedule (USD)
Notes
•
•
Capital in Year 1:▫ Oxide Plant Circuit 30 ktpm
▫ Paste Backfill Plant
▫ Beta Infrastructure
Capital in Year 2 and Year 3:▫ Mostly Beta Infrastructure and Tail-end of Plant Capital
7
•
•
Capital in Year 4:▫ CDM and Frankfort Infrastructure
▫ Sulphide Plant Circuit 15ktpm
Capital Post Year 5:▫ Mostly CDM and Frankfort Infrastructure
ECONOMIC ANALYSIS
Minxcon performed an independent economic analysis on the Project’s Mineral Resources to
determine the economic viability of the Project to declare Ore Reserves. The Base Case utilises
the price and exchange rate forecasts based on the median of various banks, brokers and
analysts, converted to real terms and based on a forecast in January 2021. The long-term gold
price was calculated as the average between the maximum and minimum real-term gold price
over the past ten years. Minxcon also completed a gold price sensitivity at the request of TGM
to demonstrate results at various price environments. The price scenarios considered are
constant prices of US$1,500/oz, US$1,600/oz, US$1,700/oz, US$1,800/oz and US$2,000/oz.
The table below illustrates the forecasts for the first five years as well as the long-term forecast
used in the financial model.
Table 4 : Macro-economic Forecasts & Commodity Prices Used in Base Case
Item
Unit
2021
2022
2023
2024
2025
Longterm
Gold Price (Real)
Exchange Rate
(Real)
USD/oz
ZARUSD
1,892
1,786
1,587
1,502
1,469
1,600
15.39
15.57
15.93
16.00
16.00
16.00
Source: Median of various Banks and Broker forecasts (Minxcon), IMF.
The NPV is derived from post-royalties and tax, pre-debt real cash flows, after taking into account
operating costs, capital expenditures for the mining operations and the processing plant and
using forecast macro-economic parameters. The DCF evaluation was set up in months, but also
subsequently converted to calendar years ending December. The annual ZAR cash flow was
converted to USD using the relevant exchange rates as per the forecast.
The mine plan includes predominantly Probable Mineral Reserve. No Inferred Mineral Resources
have been included in the economic analysis.
The Project NPVs are shown in Table 5 below and reflect a financially robust project.
Table 5 : NPVs at Various Discount Rates (Real Terms)
Item
Unit
NPV @ 0%
NPV @ 2.5%
NPV @ 5%
NPV @ 7.5%
NPV @ 10%
NPV @ 12.5%
NPV @ 15%
Internal Rate of
Return (IRR)
USDm
USDm
USDm
USDm
USDm
USDm
USDm
%
Base Case
US$1,500/oz US$1,600/oz US$1,700/oz US$1,800/oz US$2,000/oz
US$1,570/oz
122.9
109.0
131.5
153.1
174.7
218.2
105.7
93.7
113.5
132.5
151.5
189.7
91.2
80.8
98.3
115.1
131.9
165.6
79.0
69.8
85.4
100.3
115.2
145.2
68.6
60.5
74.4
87.7
101.0
127.8
59.7
52.6
65.0
77.0
88.9
112.8
52.1
45.7
57.0
67.7
78.4
99.9
82%
75%
88%
100%
111%
134%
8
The monthly and annual cumulative cash flow along with the cumulative cash flow over the life
of mine for the Base Case Scenario is shown in the figures below in USD terms. The underground
operations have a peak funding requirement of US$36.1 million and a payback period from start
of mining is 22 months. The payback period from first gold production is 13 months.
Figure 6 : Annual Cumulative Cash Flow USD (Undiscounted) TGM Underground Project Base Case
Minxcon performed single-parameter sensitivity analyses based on the real cash flow to ascertain
the impact on the NPV. For the DCF, the commodity prices, exchange rate and grade have the
most significant impact on the sensitivity of the project followed by the mining and plant
operating cost. The project is least sensitive to capital and non-direct costs.
Figure 7 : NPV Sensitivity to Gold Price at Base Case
9
The PFS has an AISC cost below the forecast gold price from start of production as illustrated in
the graph below.
Figure 8 : ASIC cost on Yearly Basis TGME Underground Project
The table below reflects the operating data for the project.
Table 6 : Production Data
Description
Waste Tonnes Mined
Ore Tonnes Mined
Total Tonnes Mined
Average Mined Grade
Total Oz in Mine Plan
Gold Recovered
Average ounces recovered per month
Average ounces recovered per annum
Grade Delivered to Plant
Recovered grade
Yield/Recovery
All in Sustaining Costs ("AISC" base case)
All in Costs ("AIC" base case)1
Life of Mine
Life of Project (Processing)
Notes:
1. AISC + non-sustaining capital expenditure.
unit
kt
kt
kt
g/t
oz
oz
oz
oz
g/t
g/t
%
USD per oz
USD per oz
Months
Months
Base Case
1,221
2,366
3,587
5.51
418,845
353,012
4,253
51,038
5.51
4.64
84%
905
1,089
92
83
10
MINING METHOD
Long hole drilling as applied to flat dipping, narrow vain orebodies, will be utilised for stoping.
The method has successfully been applied at mines like Sibanye-Stillwater and Anglo Platinum.
Long-hole drilling is seen as a continuous operation allowing blocks to be pre-drilled and blasting
to take place as and when required (Figure 9).
Step 1 in the mining cycle is to pre-develop the mining grid. The mining grid consist of two drilling
drives on each side of the intended pillar to be mined. The drilling drives are blasted from the
cleaning roadway/advanced strike drive and connected to the next advanced strike drive. This
grid development will be done by a development drill rig with a planned daily advance of 3m.
Figure 9 : Underground Development Design
Step 2 in the mining cycle, once the mining grid has been pre-developed, 15m long blast holes
are drilled with a long hole drill rig from the drill drive down-dip of the mining pillar and holed
into the up-dip drill drive. A single operator drills 120–150 meters in a 12-hour shift (Figure 11).
Five holes are blasted at a time, advancing 3m. Stope cleaning is done by waterjet or low profile
scrapers. Personnel are not required to enter the stoping area as all work is done from the safety
of the well supported drives.
LHDs load and transport the ore from drives to underground belts, from where it goes to surface.
11
Figure 11 : Example of Long Hole stoping layout
The method allows for ultra-narrow stoping widths, with drastic reduction in waste dilution. The
lowest widths planned is 60cm, although the method proved capable under 50cm.
Figure 12 : Long Hole Narrow Reef Stoping
OPERATING COSTS
The mining operating cost estimations were completed utilising the Minxcon first-principles
activity-based cost model. The cost model utilises the mine and engineering design criteria as
well as production schedule inputs to derive cost rates for the mining and engineering activities.
12
The underground mining costs for labour, equipment, consumables, services and utilities have
been sourced from quotations, actual industry stores costs, industry rates and utility rates.
Where costs could not be obtained from these sources, benchmarking with similar-sized projects
and operations was conducted and historical costs escalated.
A ZAR/USD exchange rate of 15.89 as of 1 February 2021 has been used to convert costs to USD
terms for reference purposes.
Table 7 : Operating Costs USD/t milled
Item
Net Turnover
Mine Cost
Processing Costs
On-Site Other Costs
Royalties
Operating Costs
SIB Capex
Reclamation
Off-Mine Overheads
All-in Sustaining Costs
(AISC)
Non-Sustaining Capital
All-in Costs (AIC)
All-in Cost Margin
EBITDA
EBITDA Margin
Gold in Mine Plan
Gold Recovered
Base Case
US$1,500/oz US$1,600/oz US$1,700/oz US$1,800/oz US$2,000/oz
US$1,570/oz
232
223
238
253
268
297
72
72
72
72
72
72
31
31
31
31
31
31
14
14
14
14
14
14
7
6
8
9
10
12
124
123
124
126
127
129
6
6
6
6
6
6
0
0
0
0
0
0
5
5
5
5
5
5
135
27
162
30%
103
44%
418,845
353,012
134
27
162
28%
95
42%
418,845
353,012
136
27
163
31%
108
45%
418,845
353,012
137
27
164
35%
122
48%
418,845
353,012
138
27
166
38%
135
51%
418,845
353,012
141
27
168
44%
163
55%
418,845
353,012
Table 8 : Operating Costs USD/oz recovered
Item
Net Turnover
Mine Cost
Processing Costs
On-Site Other Costs
Royalties
Operating Costs
SIB Capex
Reclamation
Off-Mine Overheads
All-in Sustaining
Costs (AISC)
Non-Sustaining
Capital
All-in Costs (AIC)
All-in Cost Margin
EBITDA
EBITDA Margin
Gold in Mine Plan
Gold Recovered
Base Case
US$1,500/oz US$1,600/oz US$1,700/oz US$1,800/oz US$2,000/oz
US$1,570/oz
1,555
1,495
1,594
1,694
1,794
1,993
484
484
484
484
484
484
206
206
206
206
206
206
92
92
93
94
94
96
48
43
51
59
66
81
830
825
834
843
851
867
39
39
39
39
39
39
0
0
0
0
0
0
36
36
36
36
36
36
905
900
909
917
926
942
184
1,089
30%
688
44%
418,845
353,012
184
1,083
28%
634
42%
418,845
353,012
184
1,092
31%
724
45%
418,845
353,012
184
1,101
35%
815
48%
418,845
353,012
184
1,109
38%
907
51%
418,845
353,012
184
1,125
44%
1,090
55%
418,845
353,012
13
ENVIRONMENTAL AUTHORISATIONS
Underground mining is less impactful on the environment than open pit mining. Although the
Phase 1 UG mines are already authorised in most aspects, an amended mine works programme
will be submitted, and associated environmental approvals will be obtained.
The company has assembled a highly competent team to deal with all “licence to operate”
aspects, who is pro-actively project managing the various approval aspects associated with the
growing number of mine development projects.
Mineral Resources and Energy Minister, Honorable Gwede Mantashe, recently expressed
renewed commitment to enhance the Government processes to expedite approval processes in
the South African mining industry. The department is working closely with the Minerals Council
on these aspects. The President of South Africa has also announced mining to be a key
component of post-Covid economic recovery and job creation. The Company is therefore
confident that all approvals will be obtained.
The company is committed to “zero harm” and will add significant value to the communities and
the environment. Informal mining and unsustainable land use practises have caused
environmental damage in the area, and TGME will work with the community and authorities to
improve it as part of its ESG commitments. The local communities are highly supportive of the
Company’s projects.
METALLURGY SECTION
The UG-Plant will be able to accommodate a variety of ore sources, incorporating different
streams that require different treatment solutions, while sharing front-end (crushing) and backend (CIL, elution, gold room, tailings) infrastructure. It will also be further expandable with
modular additions, and the CIL section will also be shared with the 50kt/m Theta Open Pit plant
(oxide ore plant).
The existing Process Plant will be upgraded and refurbished to treat ore from Beta. The process
will follow a conventional Carbon-in-Leach (“CIL”) configuration at a rate up to 30 ktpm.
Figure 10: 3D view of refurbished Process Plant superimposed on current Plant footprint
Source: MET63
14
Frankfort ore will be concentrated via Dense Media Separation (“DMS”) at the shaft and only the
concentrate will be trucked to the Process Plant. The DMS will process up to 15 000 tpm, and
the discards will be stockpiled at the shaft. The DMS concentrate will be processed with a
specialized circuit that will remove the carbonaceous preg-robbers and oxidize the sulphide
minerals (figure 13). The ore from CDM mines will also follow the same process route as
Frankfort ore.
Figure 13: Block Flow Diagram for Beta, Frankfort and CDM ore
DMS Discards
Floats
Carbon Tails
Floats
CDM
DMS
Sinks
Carbon
Flotation
Sinks Milling
Coarse
Frankfort
Crush and
Screen
Fines
Sulphide
Flotation
Floats
Fines Milling
Carbon
Flotation
Ultrafine
Grinding
Intensive CIL
Conventional
CIL
Beta
Crush and
Screen
CIL Tails
Oxide Milling
The existing tailings facility will be re-commissioned for the first phase, while for subsequent
phases the CIL Tailings will be pumped into the mined-out workings of the Beta mine adjacent to
the Process Plant as backfill.
Potential upgrading of mined ore from Beta and CDM via XRT or DMS is under investigation and
not factored in. This, however, could potentially further increase gold production.
Detailed metallurgical testwork has been concluded for the more complex Frankfort ore,
confirming the above solution. Initial testwork on Beta ore indicates a simpler design, where e.g.
carbon floatation will be excluded from the stream. More detailed studies will be conducted to
refine the design. The planned recovery rate of 84% is based on the testwork to date.
A highly competent team of experts (inhouse capacity and consultants) are working on the plant
solutions, and assurance checks have been put in place. The company will employ reputable
EPCM partners for detailed design and construction of the project, with track records of
successful project delivery.
ORE RESERVE
The Ore Reserve statement from the March 21 release is presented below. The Ore Reserve
calculation considered Mineral Resources in the Indicated category as the Theta Project does not
contain any Measured Mineral Resources (Table 4). The graph below (Figure 14) illustrates the
effect of the modifying factors on the diluted scheduled tonnes for the Theta Project. Pit designs
are provided in Appendix A.
15
Table 9: Ore Reserves
Grade
Tonnes
g/t
kt
Au Content
Operation
kg
koz
Beta
6.51
1,662
10,822
347.94
Frankfort
4.13
319
1,317
42.33
CDM
2.31
385
889
28.58
Open Pit (MR83)
2.74
2,164
4,996
160.61
Total
3.98
4,530
18,023
579.46
Notes:
1.
2.
3.
4.
5.
An Ore Reserve cut-off of 170 cm.g/t has been applied for Beta
An Ore Reserve cut-off of 150 cm.g/t has been applied for Frankfort
An Ore Reserve cut-off of 121 cm.g/t has been applied for CDM
An Ore Reserve cut – off of 0.4 g/t was applied. For the open pit.
A gold price of USD 1,465 / oz and exchange rate of 16 ZAR / USD was used for the cut-off
calculation for Beta, Frankfort and CDM
6. A gold price of USD 1,300 / oz was used for the cut - off calculation for the open pit operation
7. Ore Reserves are reported as total Ore Reserves and are not attributed.
The Mineral Resource to Ore Reserve conversion requires application of appropriate factors
which would account for any changes to the Mineral Resources (Figure 6) in the life of mine plan
as a result of mining the ore. As part of the technical studies the potential ore loss and dilution
to the Mineral Resources was determined and applied to the resources available for conversion
to Ore Reserves. The ore loss reduces the tonnage and content, while the dilution would add
additional tonnage with no gold content. Note ore reserve included previously undiscovered
reefs (Bevetts and Shale Reef).
Figure 14: Resources to Ore Reserves Beta Mine
16
Figure 15 : Mineral Resources to Ore Reserves Frankfort Mine
Figure 16: Mineral Resource to Ore Reserve CDM Mine
17
STUDY INPUTS AND DERIVATION
The Pre-Feasibility Study for Initial Underground Projects is based on the following key input
parameters: The Mineral Resources were estimated and compiled by Minxcon (Johannesburg);
The Project mine plan and detailed monthly mining and processing schedule, derived
from primarily Indicated Mineral Resources was produced by Minxcon after the
application of mining parameters, mining and processing costs from in-country
contractors, processing inputs and geotechnical design considerations.
A small portion of Inferred Mineral Resources was included in the LoM plan since it is
unavoidable to exclude it. This Inferred Mineral Resource was excluded from the Ore
Reserves and economic analysis.
Maiden Probable Reserve has been stated by Minxcon after excluding the Inferred
Mineral Resources and confirming the economic viability.
Geotechnical inputs and parameters for underground mine designs by Mr. Mark Grave,
independent rock engineer;
Process engineering design, capital and operating costs by MET63 South Africa (Pty) Ltd
(Johannesburg) and Minxcon;
Metallurgical recovery inputs based on test work by Maelgwyn South Africa and
interpreted by MET63 South Africa (Pty) Ltd.
Tailings storage facility design, capital and operating costs by Tailex Management Services
(Pty) Ltd (“Tailex”) and Minxcon.
This announcement was approved for release by Mr Bill Guy, Chairman.
For more information please visit www.thetagoldmines.com or contact:
Bill Guy, Chairman
Theta Gold Mines Limited
T: + 61 2 8046 7584
billg@thetagoldmines.com
Investor Relations
Australia: Ben Jarvis, Six Degrees Investor Relations: +61 (0) 431 271 538
United States: Michael Porter, Porter, LeVay & Rose Inc: +1 212 564 4700, theta@plrinvest.com
https://twitter.com/ThetaGoldMines
https://www.linkedin.com/company/thetagoldmines/
18
ABOUT THETA GOLD MINES LIMITED
Theta Gold Mines Limited (ASX: TGM | OTCQB: TGMGF) is a gold development company that holds a range of
prospective gold assets in a world-renowned South African gold mining region. These assets include several
surface and near-surface high-grade gold projects which provide cost advantages relative to other gold
producers in the region.
Theta Gold’s core project is located next to the historical gold mining town of Pilgrim’s Rest, in Mpumalanga
Pro
Share your feedback
Discover