Feasibility Study Update for TGME Underground Gold Project
Released
Released
Announcement PDF
6 April 2022
ASX ANNOUNCEMENT
SIGNIFICANT PROGRESS MADE TO ADVANCE THE TGME
UNDERGROUND DEFINATIVE-FEASIBLITY STUDY
HIGHLIGHTS:
• Feasibility Study ~85% completed following progress across a number of
key workstreams
• Metallurgical test work conducted on Rietfontein ore samples reveal a gold
recovery rate of 89.5%
• Completion of metallurgical testing at Rietfontein finalises the
metallurgical work across all four mine sites forming part of the Feasibility
Study
• Rock engineering modelling completed at Rietfontein – supports the
completion of mine design and geotechnical studies
• Theta Gold advancing plant design and underground tailing work ahead of
anticipated completion of feasibility study in Q2 2022
Theta Gold Mines Limited (“Theta Gold” or “Company”) (ASX: TGM| OTC: TGMGF) is pleased
to provide an update on the progress made for the Feasibility Study (‘FS’) being undertaken
at the Company’s TGME Underground (UG) project which comprises the Beta, Frankfort,
CDM, and Rietfontein mines.
Commenced in September 2021, the Feasibility Study is now ~85% finalised following
considerable progress made on a number of key workstreams including the completion of
block models, mine scheduling, geotechnical, ventilation and engineering studies and
metallurgical test work (refer table 1).
The feasibility study is anticipated to be finalised in Q2, 2022, which will allow the Company
to progress towards mine build and project development financing. Post DFS the company
will advance discussions with several parties in relation to the larger develop CAPEX funding
1
options. The DFS will incorporate four mines and a shared metallurgical facility, designed
according to multiple detailed studies and test work that are now drawing towards a final
conclusion.
Metallurgical test completed for Rietfontein Mine
Metallurgical test work undertaken at the Rietfontein Mine has achieved an encouraging
89.5% gold recovery from simple leach testing (Free Milling Ore). 1.5-ton representative ore
samples were taken at various points along the 3.2km orebody strike length, with five
approximately equal samples collected by channel sampling across the gold reef system.
Samples were collected from both high and low-grade gold areas in the mine to get a
representative sample. The bulk sample was dispatched to “Ready Lead Assay Laboratory” for
Bottle Roll Leach Test. Testing confirming a free-milling ore with a head grade of 4.41g/t and
an overall ore recovery factor of 89.5%.
Figure 1: Rietfontein Mine Sample Points
M3
M4
M1
M5
M2
Table 1: Sample points locations
Sample
Grade
Location Number
See Figure 1
Met 63 Rietfontein Entrance
1.17 g/t
M1
Met 63 Rietfontein 13 -1
2.93 g/t
M2
Met 63 Rietfontein 3 Adit-1
8.07 g/t
M3
Met 63 Rietfontein 3 Adit- 2
7.48 g/t
M4
Met 63 Rietfontein Entrance
2.42 g/t
M5
2
Rock engineering modelling
Rock engineering modelling has also now been completed on the vertical gold reef system at
Rietfontein. The modelling was undertaken to assess the optimum rock support system,
indicating the size of the rib, crown, and sill pillars. Results from Rock Mechanics Laboratory
revealed that a 2.5m rib pillar, 5.0m crown, and sill pillar will be stable and the conditions
acceptable for shrinkage mining at Rietfontein.
In addition, the uniaxial, tensile, and compressive strength and deformation modulus of the
reef and surrounding rock was tested. The hanging wall and footwall are both more
competent rock than the reef with higher Uniaxial Compressive Strength (UCS) and elastic
modulus. The implication is that the reef can be blasted out without causing excessive
damage to the hanging wall and footwall. It also implies that the correct sized pillars will
intentionally crush without damaging the host rock.
Chairman Mr Bill Guy stated, “The completion of metallurgical test work and rock engineering
modelling moves the feasibility study one step closer to completion. With Rietfontein now
included in the TGME Underground project DFS alongside the Beta, CDM and Frankfurt mines,
the board hopes to extend the Life of Mine to approximately 10 years.
“With the feasibility now moving to into its final stages we will continue to ramp up initiatives
in order remain on track for completion in Q2. I look forward to updating shareholders as
initiatives are completed and milestones hit.”
Description
Beta
Rietfontein
Frankfort
CDM
Geotechnical Studies
Mine Design Criteria
Mine Design
Mine Schedule
Ventilation Studies
Underground Tailing Deposition
RFQ
Mining OPEX
Engineering Infrastructure
Electrical Design
Hydrological Test Work
Hydrological Studies
Engineering Designs
Engineering OPEX
Engineering CAPEX
Metallurgical Test Work
Plant OPEX
Plant CAPEX
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
55%
✓
✓
✓
✓
✓
90%
✓
✓
✓
✓
✓
70%
70%
✓
65%
59%
✓
90%
✓
✓
✓
✓
✓
70%
70%
✓
65%
59%
✓
90%
✓
✓
✓
✓
✓
70%
70%
✓
94%
88%
✓
90%
✓
✓
✓
✓
✓
70%
70%
✓
94%
88%
92%
Table 2 – Progress on feasibility study activities.
3
Figure 2 – Rietfontein Mine underground section view
Figure 3 – Samples being extracted from the Rietfontein Mine
4
Figure 4 – Summary of rib pillar modelling results
[ENDS]
This announcement was approved for release by Theta Gold Mines Limited’s Board.
For more information, please visit www.thetagoldmines.com or contact:
Bill Guy, Chairman
Theta Gold Mines Limited
T: + 61 2 8046 7584 E: billg@thetagoldmines.com
Investor Relations
Australia: Ben Jarvis, Six Degrees Investor Relations: +61 (0) 431 271 538
United States: Michael Porter, Porter, LeVay & Rose Inc: +1 212 564 4700,
theta@plrinvest.com
Webpage: www.thetagoldmines.com
https://twitter.com/ThetaGoldMines
https://www.linkedin.com/company/thetagoldmines/
ABOUT THETA GOLD MINES LIMITED
Theta Gold Mines Limited (ASX: TGM | OTCQB: TGMGF) is a gold development company that holds a range
of prospective gold assets in a world-renowned South African gold mining region. These assets include
several surface and near-surface high-grade gold projects which provide cost advantages relative to other
gold producers in the region.
5
Theta Gold’s core project is located next to the historical gold mining town of Pilgrim’s Rest, in Mpumalanga
Province, some 370km northeast of Johannesburg by road or 95km north of Nelspruit (Capital City of
Mpumalanga Province). Following small scale production from 2011 – 2015, the Company is currently
focussing on the construction of a new gold processing plant within its approved footprint at the TGME
plant, and for the processing of the Theta Open Pit oxide gold ore. Nearby surface and underground mines
and prospects are expected to be further evaluated in the future.
The Company aims to build a solid production platform to over 160kozpa based primarily around shallow,
open-pit or adit-entry shallow underground hard rock mining sources. Theta Gold has access to over 43
historical mines and prospect areas that can be accessed and explored, with over 6.7Moz of historical
production recorded.
Theta Gold holds 100% issued capital of its South African subsidiary, Theta Gold SA (Pty) Ltd (“TGSA”). TGSA
holds a 74% shareholding in both Transvaal Gold Mining Estates Limited (“TGME”) and Sabie Mines (Pty)
Ltd (“Sabie Mines”). The balance of shareholding is held by Black Economic Empowerment (“BEE”) entities.
The South African Mining Charter requires a minimum of 26% meaningful economic participation by the
historically disadvantaged South Africans (“HDSAs”). The BEE shareholding in TGME and Sabie Mines is
comprised of a combination of local community trusts, an employee trust and a strategic entrepreneurial
partner.
DISCLAIMER
This announcement has been prepared by and issued by Theta Gold Mines Limited to assist in
informing interested parties about the Company and should not be considered as an offer or
invitation to subscribe for or purchase any securities in the Company or as an inducement to make
an offer or invitation with respect to those securities. No agreement to subscribe for securities in the
Company will be entered into on the basis of this announcement.
This announcement may contain forward looking statements. Whilst Theta Gold has no reason to
believe that any such statements and projections are either false, misleading or incorrect, it does not
warrant or guarantee such statements. Nothing contained in this announcement constitutes
investment, legal, tax or other advice. This overview of Theta Gold does not purport to be all
inclusive or to contain all information which its recipients may require in order to make an informed
assessment of the Company’s prospects. Before making an investment decision, you should consult
your professional adviser, and perform your own analysis prior to making any investment decision.
To the maximum extent permitted by law, the Company makes no representation and gives no
assurance, guarantee or warranty, express or implied, as to, and take no responsibility and assume
no liability for, the authenticity, validity, accuracy, suitability or completeness of, or any errors in or
6
omissions, from any information, statement or opinion contained in this announcement. This
announcement contains information, ideas and analysis which are proprietary to Theta Gold.
COMPETENT PERSONS STATEMENT
Metallurgical Results:
The information in this press release relating to Metallurgical results is based on, and fairly
reflects, the information and supporting documentation compiled by Mr Rogan Roulstone, a
consultant to the Company and a member (No. 705817) of the South African Institute of Mining
and Metallurgy.
FORWARD LOOKING AND CAUTIONARY STATEMENTS
This announcement may refer to the intention of Theta Gold regarding estimates or future events
which could be considered forward looking statements. Forward looking statements are typically
preceded by words such as “Forecast”, “Planned”, “Expected”, “Intends”, “Potential”, “Conceptual”,
“Believes”, “Anticipates”, “Predicted”, “Estimated” or similar expressions. Forward looking
statements, opinions and estimates included in this announcement are based on assumptions and
contingencies which are subject to change without notice, and may be influenced by such factors as
funding availability, market-related forces (commodity prices, exchange rates, stock market indices
and the like) and political or economic events (including government or community issues, global or
systemic events). Forward looking statements are provided as a general reflection of the intention
of the Company as at the date of release of the document, however are subject to change without
notice, and at any time. Future events are subject to risks and uncertainties, and as such results,
performance and achievements may in fact differ from those referred to in this announcement.
Mining, by its nature, and related activities including mineral exploration, are subject to a large
number of variables and risks, many of which cannot be adequately addressed, or be expected to be
assessed, in this document. Work contained within or referenced in this report may contain
incorrect statements, errors, miscalculations, omissions and other mistakes. For this reason, any
conclusions, inferences, judgments, opinions, recommendations or other interpretations either
contained in this announcement, or referencing this announcement, cannot be relied upon. There
can be no assurance that future results or events will be consistent with any such opinions, forecasts
or estimates. The Company believes it has a reasonable basis for making the forward looking
statements contained in this document, with respect to any production targets, resource statements
or financial estimates, however further work to define Mineral Resources or Reserves, technical
studies including feasibilities, and related investigations are required prior to commencement of
mining. No liability is accepted for any loss, cost or damage suffered or incurred by the reliance on
the sufficiency or completeness of the information, opinions or beliefs contained in this
announcement.
7
The Feasibility Study referred to in this announcement is based on technical and economic
assessments to support the estimation of Ore Reserves. There is no assurance that the intended
development referred to will proceed as described, and will rely on access to future funding to
implement. Theta Gold Mines believes it has reasonable grounds the results of the Feasibility Study.
At this stage there is no guarantee that funding will be available, and investors are to be aware of
any potential dilution of existing issued capital. The production targets and forward looking
statements referred to are based on information available to the Company at the time of release,
and should not be solely relied upon by investors when making investment decisions. Theta Gold
cautions that mining and exploration are high risk, and subject to change based on new information
or interpretation, commodity prices or foreign exchange rates. Actual results may differ materially
from the results or production targets contained in this release. Further evaluation is required prior
to a decision to conduct mining being made. The estimated Mineral Resources quoted in this release
have been prepared by Competent Persons as required under the JORC Code (2012). Material
assumptions and other important information are contained in this release.
8
JORC Checklist – Table 1 Assessment and Reporting Criteria
SECTION 1: SAMPLING TECHNIQUES AND DATA
Criteria
Explanation
Detail
Nature and quality Sampling types discussed in this section mainly pertain to historical
of sampling (e.g. data with the exception of the Theta Project subsequent to the
cut channels,
2017-2019 drilling campaign. Drilling data sampling types include
random chips, or diamond, reverse circulation (“RC”), percussion and auger drilling.
specific specialised Other sampling data types include underground channel chip
industry standard sampling (as individual sample section composite data points on
measurement
plans or as development or stope face composite stretch values),
tools appropriate grab sampling as well as trench and sample pit sampling for bulk
to the minerals
sampling for the purposes of size fraction analysis.
under
investigation, such
as down hole
The table below outlines the types of sampling data collected or
gamma sondes, or utilised in the Mineral Resource or Exploration Target estimates for
handheld XRF
each of the Project Areas.
instruments, etc.).
These examples
should not be
Project Area Reef
Sampling Data Types
taken as limiting
Drillhole Data
the broad
Sampling
techniques
meaning of
sampling.
Rietfontein
Rietfontein
Channel Chip Sample
Data
Drillhole Data
Beta
Beta
Channel Chip Sample
Data
Drillhole Data
Frankfort
Clewer,
Dukes Hill &
Morgenzon
Bevetts and Theta
Channel Chip Sample
Data
Drillhole Data
Rho
Channel Chip Sample
Data
Drillhole Data
Olifantsgera
amte
Vaalhoek
Olifantsgeraamte
Channel Chip Sample
Data
Drillhole Data
9
SECTION 1: SAMPLING TECHNIQUES AND DATA
Criteria
Explanation
Detail
Vaalhoek and
Thelma Leaders
Channel Chip Sample
Data
Stretch Values
Drillhole Data
Glynn’s
Lydenburg
Glynn's
Channel Chip Sample
Data
Stretch Values
Theta
Project
(Theta Hill,
Browns Hills
and Iota
section of
Columbia
Hill)
Drillhole Data
Beta, Shale,
Lower Theta,
Upper Theta,
Lower Rho, Upper
Rho and Bevetts
Trench Sampling Data
Channel Chip Sample
Data
Drillhole Data
Columbia Hill Rho, Shale and
(remaining)
Shale Leaders
Channel Chip Sample
Data
Hermansbur
g
Eluvial
RC Drillhole Data
DG1
Eluvial
RC Drillhole Data
DG2
Eluvial
RC Drillhole Data
DG5
Eluvial
Grab Samples
RC Drillhole Data
Glynn’s
Lydenburg
TSF
Tailings
Auger Drillhole Data
Blyde TSFs
(1, 2, 3, 3a,
4, 5)
Tailings
Auger Drillhole Data
TGM Plant
Tailings
Auger Drillhole Data
Vaalhoek,
South East
(DGs), Peach
Rock Dump
Bulk Sampling Data
Trench Sampling Data
10
SECTION 1: SAMPLING TECHNIQUES AND DATA
Criteria
Explanation
Detail
Tree,
Ponieskrantz
, Dukes
Clewer
Sampling Pit Data
Channel Chip Sampling Data:Historical (Pre-1946) chip sample values were captured in
‘pennyweight’ (dwt) units for gold content and in inches for
channel width. The quality of the chip samples could not be
ascertained due to the historical nature there-of; however, it
should be noted chip sampling is a well-established sampling
method in the underground South African mining industry. The
sampling activity on the mines was usually managed by each
mine’s survey department and were usually conducted to specific
company-wide standards.
More recent chip sample values were captured as cm.g/t content
values and channel widths were recorded in centimetres as is the
case at Frankfort while under ownership of Simmer & Jack Mines
Limited. During 2008, Minxcon audited the chip sampling
procedure as employed by Simmer & Jack and found the
procedures employed to be of industry standard.
Rietfontein Metallurgical samples
Face channel sampling conducted by hand tools horizontally across
vertical quartz sulphide gold reef. All reef material collected with
no crushing or sieving onsite.
300 kg collected at each sample site and 5 samples collected in
total for 1.5 tons of bulk sample.
All samples dispatched to Ready Lead Assay Laboratory SA
Stretch Values:In some instances (such as at Vaalhoek and Glynn’s Lydenburg) in
areas where original sample plans were not available, stretch value
plans recording a composite content and channel width value for a
stope length or development end were available and included in
the database. The integrity of these plans as a source of grade
information has been proven in other areas on the same mines
where both chip sample plans and stretch value plans were
11
SECTION 1: SAMPLING TECHNIQUES AND DATA
Criteria
Explanation
Detail
available and were compared. It was found that the correlation to
old sampling has been representative of the stretch values in these
areas.
Drillhole Data:Historical (pre-2007/8) drillhole data (inclusive of diamond, RC, and
auger) exists on many of the operations. However very little
backing data is available for many of these older holes and it must
be assumed that QAQC was not included in the process. Minxcon
has however reviewed the general quality of the survey data for
these drillholes. For the most part, collar data has been found to
agree well with local topography and is considered to be
acceptable for modelling purposes.
Downhole survey data with respect to diamond and RC drilling is
also often absent from the older holes; however, it should be
noted that over 98% of these holes were seldom drilled to depths
in excess of 150 m and were vertically collared. Only 1.40% of all
the drillholes on all the properties were drilled as inclined
drillholes, thus it is Minxcon’s view that the holes and their relative
reef intercept points would be spatially acceptable for modelling
purposes.
The historical drillhole data has no accompanying assay QAQC,
however this fact is considered in allocation of Mineral Resource
classification during modelling.
More recent drillhole data (inclusive of diamond, RC and auger)
from 2008 onward is considered to be of high quality as it was
conducted to updated industry standards with the incorporation of
drillhole collar survey as well as assay QAQC where blanks and
certified reference material were inserted for monitoring purposes,
with the inclusion of coarse duplicate samples. These later drilling
programmes were also either monitored, audited or managed by
Minxcon personnel under Minxcon previous sister company Agere
Project Management (“Agere”).
Trench, Sample Pit and Bulk Sampling (Vaalhoek Rock Dump):12
SECTION 1: SAMPLING TECHNIQUES AND DATA
Criteria
Explanation
Detail
In order to evaluate the Vaalhoek Rock Dump, trenches and sample
pits were dug. The trenches and pits were surveyed by a Mine
Surveyor and were sampled in sections down to a depth 1.2 m,
each sample representing a composite of 40 cm down the wall of
the trench or pit. These samples were then assayed. The discard
material from the trenches and pits was then composited to form a
bulk sample of 50 tonnes for conducting size fraction analysis. The
nature and quality of the sampling in question has been considered
in the Mineral Resource classification for the Vaalhoek Dump,
which is Inferred.
Bulk Sampling (South East (DGs), Peach Tree, Ponieskrantz, Dukes
Clewer):Bulk sampling was done through a triple deck screening plant (bulk
samples were between 20t and maximum 520t per waste rock
dump).
Trench Sampling (Theta Project Browns Hill):Trenching was conducted on Browns Hill during the 2017-2019
drilling campaign to assist in locating the Lower Theta Reef
outcrop. Trenches were dug in roughly an east-west orientation to
a depth of between 1.0 m to 2.1 m. A total of 10 trenches were dug
with an approximate spacing of approximately 30 to 35 m. The
trenches were sampled near to vertical at 2 m intervals, due to the
very shallow dip of the reef, where full side-wall composite
samples were taken. Samples were dispatched to SGS Laboratory
in Barberton for analysis. The trench sampling was not used in any
evaluation as its only purpose was to locate reef outcrops.
Include reference Chip Sampling:to measures taken
In concordant reef underground projects chip samples were taken
to ensure sample
normal to the reef dip and calculated to give a composited value
representivity and
for a true reef thickness. In the case of cross-reefs such as that at
the appropriate
Rietfontein, chip sample positions were plotted on the
calibration of any
development centre lines indicating face sampling normal to the
measurement
reef dip. Scatter plots were also generated to examine the data set
tools or systems
for errors introduced while capturing the data. All values were
used.
converted using factors of 2.54 cm for 1 inch and 1.714285 g/t for
1 dwt.
13
SECTION 1: SAMPLING TECHNIQUES AND DATA
Criteria
Explanation
Detail
The older underground sampling took place at approximately 6 m
spacing along on-reef development, whilst in newer mining areas
this spacing was reduced to approximately 2 to 3 m along on-reef
development. In the stoping areas a grid was targeted on an
approximate 5 m by 5 m grid where applicable, which is a historical
grid (Pre-1946). This grid was put in place due to the nugget effect
of the reef. The minimum size of the samples was 20 cm to obtain
a minimum weight of 500 g.
Trench, Sample pit and Bulk Sampling (Vaalhoek Rock Dump):The trenches at Vaalhoek Rock Dump were located and spread as
evenly as possible on the top of the dump, while pits were located
on the sides of the dump and these were sampled in sections down
to a depth 1.2 m, each sample representing a composite of 40 cm
down the wall of the trench or pit. The discard material from the
trenches and pits was then composited to form a bulk sample of 50
tonnes for conducting size fraction analysis and screened at -10
mm, +40 mm and -75 mm. The nature and quality of the sampling
in question has been considered in the Mineral Resource
classification for the Vaalhoek Dump, which is Inferred.
Trench, Sample pit and Bulk Sampling (Theta Project):The trenches were dug in roughly an east-west orientation to a
depth of between 1.0 m to 2.1 m. A total of 10 trenches were dug
with an approximate spacing of approximately 30 m to 35 m. The
trenches were sampled near to vertical at 2 m intervals, due to the
very shallow dip of the reef, where full side-wall composite
samples were taken. The trench sampling was not used in any
evaluation as its only purpose was to locate reef outcrops.
Aspects of the
Samples presented in the historical database represent full reef
determination of composites for both diamond drilling as well as chip sampling. The
mineralisation
historical nature of the data and the high grades encountered
that are Material implies the use of fire assay as an assay technique. Sample
to the Public
preparation and aspects regarding sample submission for assay are
Report. In cases not known due to the historical nature of the sampling data.
where ‘industry
standard’ work
has been done this Underground sampling, for metallurgical purposes, was
would be
undertaken at the northern Neck section of Vaalhoek during
relatively simple February, 2018. Two samples weighing approximately 4kg were
(e.g. ‘reverse
14
SECTION 1: SAMPLING TECHNIQUES AND DATA
Criteria
Explanation
Detail
circulation drilling taken from exposed faces of the Vaalhoek Reef, in two separate
was used to
underground localities of previous mining. Two samples were also
obtain 1 m
taken of Thelma Leader mineralisation located in underground
samples from
exposures adjacent to the Vaalhoek Dyke. These samples also
which 3 kg was
weighed approximately 4 kg each. All samples were composites of
pulverised to
rock chipped over the reef width. The four samples were
produce a 30 g
submitted for Bottle Roll testwork at SGS Barberton, which is
charge for fire
discussed under the Metallurgical section.
assay’). In other
cases more
explanation may The smallest split drillcore sample taken was 15 cm in length. After
be required, such crushing and pulverising the core sample, a 30 g cupel was utilised
as where there is for analysis. Low core recoveries resulted in reverting to RC drilling
coarse gold that for evaluation purposes. For the RC drilling conducted at the Theta
has inherent
Project, the mass of recovered sample obtained was recorded on a
sampling
per metre drilled basis, with approximately 3 kg of sample per
problems. Unusual metre run, being split off by means of a 3-tier riffle splitter for
commodities or submission to SGS Laboratories in Barberton. Assays pertaining to
mineralisation
the Theta Project were conducted by means of gold by fire assay
types (e.g.
with a gravimetric and/or flame atomic absorption spectrometry
submarine
(“AAS”) utilising a 30 g cupel.
nodules) may
warrant disclosure
of detailed
information.
Drilling
techniques
Drill type (e.g.
Underground/Hard Rock Projects:core, reverse
All historic (pre 2007/2008) Mineral Resource evaluation drilling
circulation, openfor the underground projects was conducted in the form of
hole hammer,
diamond drilling. Information regarding drilling diameter, drill tube
rotary air blast,
type and core orientation is not available or discernible for the
auger, Bangka,
earlier 1995/1996 drilling as the core is no longer available. Only
sonic, etc.) and
core loss, intersection length and grade (g/t) are recorded with
details (e.g. core
various levels of geological lithological information. Due to the age
diameter, triple or
of the data in question and the non-availability of the historical drill
standard tube,
core, information regarding drilling diameter, drill tube type, core
depth of diamond
orientation is not available. More recent drillhole data (inclusive of
tails, facediamond, RC and auger) from 2008 onward is considered to be
sampling bit or
high quality as it was conducted to updated industry standards
other type,
with the incorporation of assay QAQC where blanks and certified
whether core is
reference material (“CRM”) were inserted for monitoring purposes.
oriented and if so,
Core drilling utilised an NQ (47.6 mm) drill bit. Details pertaining to
by what method,
earlier drilling programs’ core orientation are not available. Due to
etc.).
15
SECTION 1: SAMPLING TECHNIQUES AND DATA
Criteria
Explanation
Detail
poor diamond drillcore recoveries during the 2017-2019 drilling
campaign, core orientation was not conducted.
Open Pit or Eluvial Projects:Drilling on the eluvial deposits took place under the auspices of
Horizon Blue Resources and is regarded as being of high quality
due to good survey control and inclusion of QAQC practices. The
main drilling method (95% of drillholes) utilised to evaluate these
projects was reverse circulation (4.5 inch (115 mm) and 6 inch (150
mm) diameter) drilling, vertical reverse circulation drillholes, with
or without temporary casing depending on ground condition in the
vicinity of the various drill sites. Rotary core drilling (NQ size with
75.7 mm outside diameter and 47.6 mm inside diameter) was
utilised in 5% of the drillholes on these projects. More recent
drillhole data (inclusive of diamond, RC and auger) from 2008
onward is considered to be of high quality as it was conducted to
updated industry standards with the incorporation of assay QAQC
where blanks and certified reference material (“CRM”) were
inserted for monitoring purposes. Core drilling utilised an NQ (47.6
mm) drill bit. Details pertaining to earlier drilling programs’ core
orientation are not available. Due to poor diamond drillcore
recoveries during the 2017-2019 drilling campaign, core
orientation was not conducted.
Tailings Projects:Drilling on the tailings projects was conducted by means of small
diameter (45 mm and 50 mm) auger drilling. Drillhole positions
have been surveyed by TGM utilising a GPS based Total station. All
holes were drilled vertically.
Diamond Drilling:Method of
Information regarding the 1995/1996 recoveries is not available.
recording and
However, during the 2008 and 2012/2013 drilling campaigns the
Drill sample assessing core and
recoveries were recorded.
recovery
chip sample
recoveries and
results assessed.
Diamond drill core recoveries were recorded during the 2013
drilling programmes, which was managed by Minxcon Exploration
16
SECTION 1: SAMPLING TECHNIQUES AND DATA
Criteria
Explanation
Detail
(Pty) Ltd. Core recovery percentage was calculated for each drill
run. Sample recoveries were maximised through drilling techniques
(diamond drilling), however drilling recoveries versus grade
relationships were not assessed.
During the 2017-2019 drilling campaign consistent and accurate
records relating to core and RC drill sample recovery were
maintained on a per sample basis. Diamond drill s
Share your feedback
Discover