Half-Year Accounts at 31 December 2023
Released
Released
Announcement PDF
Half Year Financial Report
Six Months Ended 31 December 2023
Half-Year Financial Report - 31 December 2023
Theta Gold Mines Limited
Corporate Directory
DIRECTORS
Bill Guy
Richie Yang
Brett Tang
Byron Dumpleton
Executive Chairman
Non-Executive Director
Non-Executive Director
Non-Executive Director
COMPANY SECRETARY
Brent Hofman
AUDITOR
Hall Chadwick (NSW)
40/2 Park Street
Sydney NSW 2000
Australia
STOCK EXCHANGE LISTINGS
ASX: TGM
REGISTERED OFFICE
Suite 80 Level 35
International Tower One
100 Barangaroo Avenue
Sydney NSW 2000
Australia
Tel: +61 2 8046 7584
Email: info@thetagoldmines.com
SHARE REGISTRY
Boardroom Pty Limited
Grosvenor Place
Level 12, 225 George Street
Sydney NSW 2000
Australia
Tel: 1300 737 760 (within Australia)
+61 2 9290 9600 (outside Australia)
Fax: +61 2 9290 9655
AUSTRALIAN BUSINESS NUMBER
30 131 758 177
INVESTOR RELATIONS
Australia: Ben Jarvis, Six Degrees Investor Relations:
+61 (0) 413 150 448
WEBSITE
www.thetagoldmines.com
INTERACTIVE INVESTOR HUB
http://investors.thetagoldmines.com
Half-Year Financial Report - 31 December 2023
2
Theta Gold Mines Limited
Directors’ Report
Your Directors present their report, together with the financial statements of Theta Gold Mines Limited and
its controlled entities (“Consolidated Entity”) for the half year ended 31 December 2023.
DIRECTORS
The names of the Directors of Theta Gold Mines Limited during the half year and up to the date of this
report are:
Charles William (Bill) Guy
Bill Richie Yang
Guyang (Brett) Tang
Yang (Simon) Liu
Byron Dumpleton
Executive Chairman
Non-Executive Director (Audit Committee Chair)
Non-Executive Director
Non-Executive Director (retired 14 May 2023)
Non-Executive Director
Executive Management Changes
No changes to the management of Theta Gold Mines Limited occurred during the half year ended 31
December 2023.
REVIEW OF OPERATIONS
Summary
During the last 6 months, the company has focused on funding packages, safety, operational readiness,
stakeholder engagement, environment, permitting, and identifying Engineering Procurement and
Construction (“EPC”) Builder.
On the 14 March 2024, the Company announced Mining Right (MR) 83 was now fully permitted for mining.
MR 83 includes the Beta Mine, CDM Mine, and Frankfort Mine, three of the four mines included in the
mining schedule of the Definitive Feasibility Study (see ASX release 14 March 2024).
Theta now has all the required approvals for MR 83 to start mining, including:
•
•
•
•
•
•
•
•
Atmospheric Emissions Licence (Gold Plant)
Explosive licence for transport and usage
Forrest Licence (Frankfort)
MR 83 Environmental Authorisation (EA)
Water Use Licence (WUL) (Tailings, Plant, Mining)
Environmental Rehabilitation guarantee for MR 83
Updated Social and Labour Plan for MR 83
Heritage Record of Decision.
A Memorandum of Understanding (MOU) was executed with Yellow River Co., Ltd (“YRC”), a subsidiary of
Power Construction Corporation of China (“PowerChina”) to build Theta’s Stage-one TGME Gold Plant
(estimated at 45kt/months RoM capacity) including its tailings storage facility and wastewater dams. The
MOU was signed post the half year on 14 February 2024.
Half-Year Financial Report - 31 December 2023
3
Theta Gold Mines Limited
“PowerChina is an engineering and construction group based out of China, ranked at #1573 in the Fortune
Global 500 List in 2023 with over 130,000 employees worldwide. It’s subsidiary YRC is well positioned
throughout the African Continent with both power, power storage, civil construction and mining build
contracts completed and on-going. YRC recently setup operations in Johannesburg to build a South
African base for both power and mining projects.
The EPC Contract size (at cost-basis) is estimated to be US$30 million, with the majority to be paid via an
agreed-upon long-term payment schedule after construction completion and commissioning. The agreement
will be subject to the successful completion of Due Diligence and agreement on contract terms.
Half Year Events
The TGME mine site’s occupational health and safety remain our first priority, and 1160 Safe Return Shifts/
White Flag Days were achieved on 31 December 2023. A wellness program was set up that monitors the
general health of employees, with very positive results for staff health. All the required Occupational health
and safety policies and procedures have been drafted to comply with South African Mining Regulations.
The Frankfort commercial bulk sampling program was a clear demonstration of operational readiness. The
mining was completed safely, the inspector of mines came to site to view operations, the team trained 30
local miners and the Frankfort Mine performed as expected.
Environmental regulatory monitoring and reporting continued during the half year period. Under South
African Mine regulations, the TGME Mine site is treated as an operational mine. The environmental staff on
site conducted environmental sampling program each month to comply with the Mines Regulations half-year
period. Under South African Mine regulations, the TGME Mine site is treated as an operational mine. The
site's environmental staff conducted an environmental sampling program each month to comply with the
Mine Regulations.
Figure 1: Biomonitoring sampling
Our focus remains on working closely with our stakeholders and communities to strengthen existing
relationships and establish healthy and sustainable mutually beneficial relationships, sustainable, mutually
beneficial ones. The Transvaal Gold Mining Estates (“TGME”) Stakeholder Forum continues to gain
momentum with open and honest communications between all parties.
Commercial Bulk Sample Project Update
The Company advises that the mining of the commercial bulk sample (2200 tons) at Frankfort Mine is
completed. Mining of the fresh ore was completed successfully with no safety incidents. (Note 2000 tons of
sweeps also extracted).
Half-Year Financial Report - 31 December 2023
4
Theta Gold Mines Limited
The Bulk Sampling program commenced in May 2023 with labour recruitment and procurement process of
all mining and engineering requirements. All engineering labour was recruited by the end of May 2023.
Infrastructure was installed at Frankfort mine and mining commenced in July 2023.
Drill and blasting activities also commenced in July 2023 and blast design was done in conjunction with AECI,
who are the explosives manufacturers and suppliers. The design considered the density of the rock to be
blasted, the desired fragmentation, the planned cleaning method, the planned transport mode, and the cost
of the explosives. Emulsion explosives were chosen due to their intrinsic safety properties. The explosives
accessories included:
●
Shock-tubes
●
Reef masters
●
Electric detonators and
●
Tamping
Blast holes with an effective hole length of 80cm were drilled at an internal burden of 70cm this was
necessitated by the low Uniaxial Compressive Strength (UCS) of the reef. The blast holes needed to be drilled
at a certain angle to the hanging and footwall. This is required to avoid drilling into the hangingwall to
prevent developing poor hangingwall conditions which would pose a safety risk.
Figure 2 below indicates the mined area overlaid on the block model as per the JORC report.
Bulk Sample Mining Area
Following the completion of the Bulk Sampling program, Theta Gold will explore its options to expedite early
cash flow opportunities from the Frankfort Mine. The bulk sample will undergo metallurgical test work as
part of the marketing strategy for the ore.
Half-Year Financial Report - 31 December 2023
5
Theta Gold Mines Limited
Details of mining are attached below in Frankfort Gold Mine Bulk Sampling Safety and Background.
Figures 3 to 6: Pictures of Ore loading and transporting.
Half-Year Financial Report - 31 December 2023
6
Theta Gold Mines Limited
Figure 7: Drill and blast activity underway at Frankfort Gold Mine
Frankfort Gold Mine Bulk Sampling Safety and Background
Before the bulk sampling program could commence at Frankfort Mine in South Africa, it was necessary to
obtain permits and comply (See Table 1) with all current mining legislation. Safety measures, such as roof
supports, ventilation, and water management systems, were also installed in order to ensure the safety of
the mine.
Table 1: Operation and Tasks completed in support of Frankfort Bulk Sample
Tasks
Successfully
Completed
Mine usage and storage Explosive Licence
✓
Explosive Transport Licence
Mine Induction and Competency training for all new employees
Electrical power and compressed air supply tender and contract award
Installation of surface critical infrastructure to support Mining activities
Safe-making activities and getting the Mine production-worthy
Drill and Blast Design with explosives manufacturer
Survey and Sampling of all intended Mining areas
Mining activities to create the required volumes
Earthmoving equipment tender and contract award
Earthworks and construction of Dense Media Separation and Crushing Plan
footprints
Construction of Water Management Systems and Return Water Dams
Rehabilitation and re-construction of 21km of gravel road
Designed, manufactured and commissioned a 25t/hour 2-stage crushing plant
Designed, manufactured and commissioned a 25t/hour Dense Media Separation
Plan
Gold-bearing Ore transport tender and contract award
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
✓
Half-Year Financial Report - 31 December 2023
7
Theta Gold Mines Limited
Additionally, 30 local miners underwent safety training, and all South African mining regulations were
implemented. Finally, the mine had to pass a safety inspection from the regional Mines inspector.
The Bulk Sampling project commenced in May 2023 with labour recruitment and procurement process of all
mining and engineering requirements. All engineering labour was recruited by the end of May 2023.
Infrastructure was installed at Frankfort mine and mining commenced in July 2023.
Drill and blasting activities also commenced in July 2023 and blast design was done in conjunction with AECI,
who are the explosives manufacturers and suppliers, the design considered the density of the rock to be
blasted, the desired fragmentation, the planned cleaning method, the planned transport mode, and the cost
of the explosives. Emulsion explosives were chosen due to their intrinsic safety properties. The explosives
accessories included, Shock-tubes, Reef masters, Electric detonators and Tamping.
Blast holes with an effective hole length of 80cm were drilled at an internal burden of 70cm this was
necessitated by the low UCS of the reef. The blast hole needed to be drilled at a certain angle to the hanging
and footwall to avoid drilling into the hangingwall and damaging it as this would have created bad
hangingwall conditions which would pose a safety risk. Furthermore, poor fragmentation would be the result
if the blast holes are not drilled according to the planned angles and directions.
The mine design was based on ledging both sides of the existing roadway for 4.5 m, the ledges were blasted
sequentially in a staggered pattern until they reached their limit to comply with the rock mechanics designs
and minimize the possibility of rockfalls or roof breaks. This is especially important in shallow mining areas
due to the lack of clamping forces.
The 1st blast was taken in July 2023, the length of the blasted panel was 30m, with a planned stoping width
of 09m and a planned advance of 0.8m, this generated about 80 tons. Blasting took place over a period of 9
weeks generating 4320 tons inclusive of old sweeping tons.
Once a panel is blasted, it would then be cleaned by means of the water jet, the water jet would move the
blasted rock into the roadway, from which it would then be cleaned by means of an LHD Scoop. The LHD
Scoop would transport the ore from the blasting area to a tipping point underground, from where the ore
would later be transported to the tipping point on the surface. After a panel has been cleaned, the crew
would then come and install temporary and permanent support units to get the panel ready for the next
blast.
From the surface tipping point, the blasted ore (run-of-mine) was loaded into a dump truck and transported
to the DMS area, where the ore was crushed and screened. The product was then put through the DMS to
separate the gold-bearing material from the waste material. This is done based on the difference in the
densities of the waste material and the gold-bearing material.
Half-Year Financial Report - 31 December 2023
8
Theta Gold Mines Limited
Figures 8 and 9 Show Drilling and Blasting Preparation at Frankfort Mine
Figure 10: DMS Arriving on-site at Frankfort.
Figure 11: DMS being offloaded on site.
Half-Year Financial Report - 31 December 2023
9
Theta Gold Mines Limited
Figure 12: Crusher offloaded into position.
Figure 13: Construction and commissioning of DMS.
Half-Year Financial Report - 31 December 2023
10
Theta Gold Mines Limited
Completion of Definitive Feasibility Study
Definitive Feasibility Study (TGME Underground Gold Mine Project)
The Company’s Feasibility Study (FS)1 for the TGME Project was delivered on 27 July 2022, confirming
Theta Gold’s potential to be a significant near-term, high-margin, low-cost gold producer with
opportunities for future growth. Based on the FS results, the Project will provide robust financial returns
from a long-life large underground mining operation for a modest capital investment given the scale of
operations envisaged.
The Project Life of Mine ‘LOM’ will initially comprise a 12.9-year mining operation starting in Q2, 2023
and delivering LOM production of 1.24 Moz of contained gold. The estimated peak development Capital
Expenditure (“Capex”) is US$77 million, (A$103 million), with the Project forecast to generate a pre-tax
NPV10% of US$324 million, (A$432 million) and pre-tax internal Rate of Return (IRR) of 65% at a forecast
average gold price of US$1,642, (A$2,189) per ounce. Based on these metrics, the Project has a projected
capital payback period of 31 months.
The FS paves the way for a Final Investment Decision (‘FID’) by the Theta Gold Board in respect to
funding negotiations and on-going discussions with financiers with respect to full/partial debt and equity
funding options. Theta Gold has appointed a debt funding advisor to manage this important process and
will provide updates in due course.
Feasibility Highlights:
•
TGME Feasibility Study2 delivers 1.24Moz contained gold production, underpinning an initial 12.9-year
mine life.
•
Strong financial return based on LOM plan (at average gold price of US$1,642, (A$2,189) /oz) with first
production targeted for Q2, 20243 including:
o
Undiscounted free cash flows of US$508m, (A$678m), pre-tax US$717m, (A$956m);
o
NPV (at a 10% discount rate) of US$219m, (A$292m), pre-tax US$324m, (A$432m);
o
Capital payback period of 31 months;
o
Pre-tax IRR of 65%; and
o
Peak production over 100,000 oz Gold.
•
All-in-sustaining Cost (AISC) of US$834/oz (A$1,112/oz) over LOM sits on the bottom quartile of South
Africa and Australian gold producers;
•
Peak Capital requirement is US$77m, (A$103m), total capital requirements US$174m, (A$232m);and
1 Refer to ASX Release dated 27 July 2022 titled “Theta’s TGME Project Definitive FS Confirms NPV(10%) of A$432 Million at US$1,642 / Oz Gold
Price”
2 Ref to ASX release dated 27 July 2022 titled “Theta’s TGME Project Definitive FS Confirms NPV10% of A$432 million at US$1,642 /Oz Gold price”
3 First gold produced timing will be subject to securing funding and obtaining all necessary regulatory permitting approvals.
Half-Year Financial Report - 31 December 2023
11
Theta Gold Mines Limited
•
Front-End Engineering Design (FEED) of the TGME gold plant completed, forming an important input
towards the finalisation of the FS of the TGME underground project4.
Table 2: Key Project Metrics
Description
Units
Base Case
Reserve Plan
Project Start Date5
Year
2024
2024
Commercial Production Start Date
Year
2025
2025
Production build up period
Months
14
14
Life of mine
years
12.9
7.3
Underground ore mined (LOM)
Mt
6.46
2.85
Mined Grade
g/t
5.95
6.09
Gold Mined (LOM)
Moz
1.24
0.56
Production Rate
Kt/a
540
540
Production Rate
Kt/m
45
45
Grind size
µ
106
106
Gold recovered (average LOM)
%
87
87
Gold recovered (LOM)
Moz
1.08
0.49
Project economics below shows the sensitivities to the various gold price estimates and demonstrates the
robust financial returns of the Project. The FS completed in July 2022 used an average gold price of US$1,642 /
Oz as a base case.
Table 3: Project Economics at Various Gold Prices – Base Case (USD)
Project Economics at gold price
NPV @ 10% (real) Pre-tax
NPV @ 10% (real) Post-tax
IRR (%) Pre-tax
IRR (%) Post-tax
AISC
EBITDA annual average
EBIT annual average
Free Cash Flow (Pre-tax)
Free Cash Flow (Post-tax)
Development Capital – Peak
Funding
Capital Sustaining
Payback post-tax
Capital Efficiency (Pre-Tax
NPV/Dev Capital
Capital Efficiency (Post-Tax
NPV/Dev Capital
Forecast
USD1,600/ USD1,800/ USD2,000/ USD2,200/
(USD1,642/ USD1,500/oz
oz
oz
oz
oz
oz Avg)
USDm
324
255
304
402
501
601
USDm
219
174
206
269
335
400
%
65%
57%
64%
77%
90%
102%
%
57%
50%
56%
67%
78%
87%
USD/oz
834
822
831
847
862
876
USDm
69
58
66
81
96
111
USDm
60
49
57
72
87
102
USDm
717
576
673
869
1066
1264
USDm
508
412
478
611
747
881
Unit
USDm
77
77
77
77
77
77
USDm
Months
37
31
37
33
37
31
37
28
37
25
37
24
%
422%
332%
395%
524%
653%
783%
%
285%
226%
268%
351%
437%
521%
4 Refer to ASX release dated 20 June 2022 titled “TGME Gold Project Update”
5 Project start date will be dependent on the Company securing the necessary funding and permitting approvals.
Half-Year Financial Report - 31 December 2023
12
Theta Gold Mines Limited
Table 4: Project Economics at Various Gold Prices – Base Case (AUD)
Project Economics at gold price
NPV @ 10% (real) Pre-tax
NPV @ 10% (real) Post-tax
IRR (%) Pre-tax
IRR (%) Post-tax
AISC
EBITDA annual average
EBIT annual average
Free Cash Flow (Pre-tax)
Free Cash Flow (Post-tax)
Development Capital – Peak
Funding
Capital Sustaining
Payback post-tax
Capital Efficiency (Pre-Tax
NPV/Dev Capital
Capital Efficiency (Post-Tax
NPV/Dev Capital
NOTES:
1.
2.
Unit
AUDm
AUDm
%
%
AUD/oz
AUDm
AUDm
AUDm
AUDm
Forecast
USD1,600/ USD1,800/ USD2,000/ USD2,200/
(USD1,642/ USD1,500/oz
oz
oz
oz
oz
oz Avg)
432
339
405
536
669
802
292
232
274
359
447
533
65%
57%
64%
77%
90%
102%
57%
50%
56%
67%
78%
87%
1,112
1,096
1,107
1,129
1,149
1,167
92
77
87
107
128
148
80
66
76
96
116
136
956
768
897
1,158
1,421
1,686
678
550
638
814
996
1,175
AUDm
102
102
102
102
102
102
AUDm
Months
49
31
49
33
49
31
49
28
49
25
49
24
%
422%
332%
395%
524%
653%
783%
%
285%
226%
268%
351%
437%
521%
Converted to AUD from USD using AUD:USD exchange rate of 1.333 used in the FS.
Due to rounding, numbers presented throughout this document may not add up precisely to the totals, provided and percentages may
not precisely reflect the absolute figures.
Figure 14: Annual Gold Production – Base Case
Half-Year Financial Report - 31 December 2023
13
Theta Gold Mines Limited
Figure 15: Annual and Cumulative Cash Flow (Post-Tax) – Base Case (AUD)
NOTES:1. Forecast Prices averaging USD1,642/oz over LOM.
2. Converted to AUD from USD at exchange rate of 1.333 AUD:USD.
Historical Project Summary
The TGME Project targets to restart historical underground gold mines located in a historically prolific gold mining
region in the Mpumalanga Province of South Africa. The Project Areas are centred in the town of Pilgrims Rest,
some 370 km due northeast of Johannesburg, and vast majority of the tenements were under TGME’s ownership
since the late 1800s.
The Project targets the Beta (including the Beta North, Beta Central and Beta South sections), Rietfontein,
Frankfort and Clewer-Dukes Hill-Morgenzon (“CDM”) mines. A significant amount of gold resources remain
underground which were not mined historically due to technological limitations or limiting ore characteristics.
Beta is scheduled as the first operation to commence production, followed by Rietfontein, and finally CDM and
Frankfort simultaneously. In comparison to CDM and Frankfort, Beta and Rietfontein are higher-grade mines.
A gold plant, which acts as the central processing plant for all the historical operations, is situated in close
proximity with a maximum distance to operations of approximately 40km. A new facility will be established on
this footprint to treat all the ore from the surrounding operations.
Two scheduling strategies have been investigated in the FS. The Base Case considers a LOM plan targeting the
total Mineral Resources (Measured, Indicated and Inferred). The Ore Reserve Case considers a LOM plan
targeting only Measured and Indicated Mineral Resources.
This FS demonstrates the ability to achieve optimised cash flows by scheduling production from the operations.
The mine designs and associated costs per operational element feed into a combined operations financial model.
The Ore Reserve Case supports the declaration of compliant JORC Code 2012 Ore Reserves.
Half-Year Financial Report - 31 December 2023
14
Theta Gold Mines Limited
TGME Underground Gold Mine Development
As part of the preparation for the installation of the first phase new gold plant, TGME had appointed the services
of Jet Demolition to remove the redundant plant equipment. The process started in the second week of January
2022. Specialised equipment was utilised for demolition, after which it was reduced in size and made ready for
transport to scrap merchants. The project to remove the old plant is now complete6.
Processing consultants Met63 was contracted to do a detailed design and costing of a processing plant designed
for a feed capacity of 45,000 tons per month which is equivalent to 67 tons per hour at 92% availability. A flow
schematic is shown in Figure 16.
Figure 16: Process Flow Schematic Phase 1
The FS has been split into three phases, allowing for various processing scenarios aligned with the mining
development program. The design of each phase is based on a stand-alone processing facility aligned with the
mining plan of the ore body.
•
Phase 1 – Carbon-in-Leach (CIL) Plant (Free-milling ore is process for the first 7 Years, see figure 16).
The design and costing of a 45,000 tons per month oxide ore processing plant including crushing, milling,
CIL and elution with gold Doré produced on site. Testwork undertaken on various “free-milling” ores has
indicated high undissolved gold losses, indicating the presence of small amounts of sulphidic
constituents. This was particularly evident when completing standard cyanidation bottle roll trials on the
CDM mine samples. Subsequent additional testwork supports this. As a result, the Phase 1 circuit will
include a flash flotation stage post-milling to remove sulphide associated materials before conventional
cyanidation. This flotation mass pull will join the concentrator (production scheduled in Phase 2).
6 Ref to ASX release dated 4 March 2022 titled “DFS Update and High-Grade Ore Sweeped from New Historical Mines”.
Half-Year Financial Report - 31 December 2023
15
Theta Gold Mines Limited
•
Phase 2 – Gold Concentrator Plant
The design and cost of a 20,000 tons per month concentrating plant including crushing, milling, Density
Media separation (DMS) and flotation. The final products consist of a combined carbon and sulphide
flotation concentrate. The carbon flotation concentrate being processed through the CIL plant #3 and
the sulphide flotation concentrate is processed through the CIL plant #1.
•
Phase 3 – Oxidative Leaching of Sulphide Concentrate
The Phase 3 plant includes a 45,000 tons per month Leach-ox processing plant that was designed and
costed, including crushing, milling and carbon/sulphide flotation. The phase 3 plant consists of both the
gold concentrator plant as well as the CIL plant as described in Phase 1 and Phase 2. The carbon flotation
concentrate processed in a dedicated CIL circuit (CIL plant #3), sulphide flotation concentrate oxidized
under atmospheric conditions with liquid oxygen injection and high shear reactors. Oxidised product to
be treated in a separate batch CIL process (CIL #1) with the tails treated in a larger CIL (CIL plant #2), that
also processes the flotation tails as well as “free-milling” ore feed. This option allows for all recovered
gold to be produced as Doré on-site with no concentrate produced.
Although there are some shared infrastructure and processing equipment between the phases, for the purposes
of this FS the phase-one plant will be constructed first to treat Beta, Rietfontein and CDM ore with phase-three
being constructed at a later stage before mining of Frankfort ore commences.
The plant will be developed by an Engineering, Procurement and Construction (EPC) contractor. The Company
will run a tender process to evaluate contracts for the construction and upgrade of existing infrastructure
including detailed engineering for the plant, procurement, fabrication and delivery to site of plant, equipment
and materials and construction of the process plant facilities.
Project Finance
Theta Gold signed a non-binding Term Sheet with Sprott Resource Streaming and Royalty Corporation (“Sprott
Streaming”) under which Sprott Streaming is to advance US$70 million (~A$110 million) cash in return for a
gold stream on Theta’s TGME Gold Project (the “Project”). A debt funding advisor was engaged to assist in
negotiations for the required Capex requirements of the A$103 million peak capital. The Company is expected
to complete negotiations with debt financing within 2024 calendar year.
The Company is also in negotiation with other investment parties with respect to the equity portion of the
funding requirements and is expected to complete those discussions and secure terms in 2024.
Project Permits and Approvals
Mining Right (MR) 83 is now fully permitted for mining. MR 83 includes the Beta Mine, CDM Mine, and Frankfort
Mine, three of the four mines included in the mining schedule of the Definitive Feasibility Study7.
Theta now has all the required approvals for MR 83 to start mining:
•
Atmospheric Emissions Licence (Gold Plant)
•
Explosive licence for transport and usage
7 ASX release 27 July 2022 “Theta Gold’s TGME Project DFS confirms NPV of AUD432 million”.
Half-Year Financial Report - 31 December 2023
16
Theta Gold Mines Limited
•
Forrest Licence (Frankfort)
•
MR 83 Environmental Authorisation (EA)
•
Water Use Licence (WUL) (Tailings, Plant, Mining)
•
Environmental Rehabilitation guarantee for MR 83
•
Updated Social and Labour Plan for MR 83
•
Heritage Record of Decision.
MR 83 had an objection lodged against its environmental approvals as part of a 90-day public review period8 by
one individual back in September 2023. That objection was rejected by the Department of Forest Fishery and
Environment (DFFE) and all other related departments. The main condition imposed in lifting the objection was
quarterly borehole and downstream water testing (A summary of the DFFE decision is in Appendix A)
Over 20 studies have been completed as part of the EIA process. The findings from the EIA/EMPr and specialist
studies have not identified any fatal flaw, unaddressed objection, or significantly high impact ratings. The
requisite mitigation measures are all imminently feasible and this should give all interested and affected parties
the confidence that the impacts of our proposed activities will not threaten the environment.
A comprehensive stakeholder engagement process was undertaken before the submission of the applications. A
very successful open day was held in Pilgrims Rest.. Feedbacks from the open day was very positive and the
community is very excited about the job opportunities and economic upliftment that will be created by the
project. With the good turnout at the open day and various other stakeholder meetings it can be concluded that
the procedural requirement to consult during the EIA phase is satisfied.
The Company is confident that it can successfully implement its mining operations to better protect the strategic
water source and biodiversity area. It is of great concern to the local community and downstream farmers that
environmental degradation is accelerating in this catchment area. A positive response on the request to the
Minister will therefore be welcomed by stakeholders in the light of current challenges in the catchment, the
manageable environmental impacts from the proposed MR83 underground project, and the significant value
offering of the proposed Ecological Compensation Programme to support DFFE’s wider Environmental, Social
and Governance (“ESG”) objectives in the region.
Gold Plant Front-End Engineering Design (Feed) Complete
Front-End Engineering Design (FEED) of the TGME gold plant has been completed, forming an important input
towards the finalisation of the TGME Project.
Theta Gold provides an update on the MR83 gold processing plant advising that it had appointed MET63, which
specialises in the design and construction of advanced modular processing plants, to undertake and complete
the plant design, based on a thorough metallurgical testwork program, and with multi-tier internal and
independent oversight.
Key Features of the Gold Process Plant:
•
The new gold processing plant is designed to have a milling capacity of 540,000 tons per annum. The
plant design consists of two individual processing streams, capable of processing free-milling and
sulphide ore separately.
8 ASX release 11 September 2023 “ENVIRONMENTAL AUTHORISATION UPDATE FOR MR83”.
Half-Year Financial Report - 31 December 2023
17
Theta Gold Mines Limited
•
•
•
•
•
•
•
•
•
The new gold processing plant is designed to fit into the current plant footpri