Quarterly Activities & Cashflow Report - 30 June 2026
Released
Released
Announcement PDF
Theta Gold Mines Limited ACN 131 758 177
Registered Office: Level 35, One International Towers, 100 Barangaroo Avenue
Sydney, NSW 2000, Australia
31 July 2026
ASX ANNOUNCEMENT AND MEDIA RELEASE
(ASX: TGM)
QUARTERLY REPORT
1 April 2026 to 30 June 2026
Theta Gold Mines Limited (“Theta”, “TGM” or the “Company”) (ASX: TGM) is pleased to report on its
activities for the quarter ended 30 June 2026.
During the June 2026 quarter, Theta made significant progress at its flagship gold project, the TGME Gold
Project (‘Project’), securing a US$90 million bond issue facility with Pareto Securities and raising a further
US$18.6 million in equity funding in early July 2026.
Bulk earthworks drawing to completion, civil works advancing, water infrastructure and gold room 55%
complete. Key delivery critical contracts were secured while the on-site workforce expanded with a
strong equipment installation focus.
Highlights:
During the June 2026 Quarter:
• US$90 million debt funding secured – Debt Funding Syndication process completed with TGM
securing US$90 million Bond Issue with Pareto Securities to complete construction and
commissioning of TGME Gold Mine Project.
• US$18.6 million equity raise – additional US$18.6 million equity and options exercise
completed as part of key bond drawdown conditions.
• Civil works transitioning to plant build - construction is now moving into plant build and
installation readiness with bulk earthworks close to completion, civil works, water infrastructure,
platforms and gold room foundations advancing across site.
• Structural steel, mechanical and piping contracts executed - with industry leaders PICM and RM
Process, supporting the next phase of plant construction.
• Manufacturing contract for crushing and screening plant awarded - to NMS Africa, securing a
critical long‑lead item.
• TGME project team - expanded as recruitment of operational staff ramps up.
• TGME remains on budget – with clear visibility to first gold and continued progress across critical
path activities.
2
Figure 1: TGME Gold Project Site - April 2026
Figure 2: TGME Gold Project – Time Lapse Construction Photos
TGME Site Construction Update
TGME moved through the June quarter from civil construction into visible plant build-up and
installation readiness. With bulk earthworks nearing completion, concrete works well advanced and
structural steel now rising across key areas, the project is increasingly shifting from ground preparation
to physical plant assembly.
The TGME Gold Project continues to deliver strong construction progress, with multiple work fronts
advancing simultaneously.
• Processing plant footprint well established, with gold room and mill structural steel erection
underway
• Civil works advanced across Crushing and Screening Plant, Carbon in Leach (CIL), milling,
thickener and elution circuits, with over 50% of total concrete volume poured
• Key infrastructure progressing well, including water management systems and processing ponds
3
• Active earthworks, access roads and material handling areas supporting site execution
• Critical long-lead equipment advanced off-site, including ball mill assembly nearing completion
and key plant components approaching delivery-ready status
• CIL tanks and process vessels in final fabrication and coating, aligned with installation schedule
• Groundworks started on the upgrading of the Tailings Storage Facilities
Figure 3: TGME Gold Project aerial view of the TSF (bottom: Laydown area ; middle: TSF; top right: new plant
under construction).
The TGME Gold Project continues to deliver strong construction progress, with multiple work fronts
advancing simultaneously.
• Processing plant footprint fully established, with structural steel erection underway
• Civil works advanced across CIL, milling, thickener and elution circuits
• Key infrastructure in progress, including water management systems and process ponds
• Active earthworks, access roads and material handling areas supporting construction execution
• Critical long-lead equipment well advanced off-site, including ball mill assembly and key plant
components nearing delivery-ready status
• CIL tanks and process vessels in final fabrication and coating, aligned with installation schedule
More detailed summaries are provided below:
Crushing and Screening Plant
• Civil foundations and structural support nearing completion
• Crushing Plant manufacturing progressing well
• Delivery expected towards the end of September 2026
Ball Mill and Milling Circuit
• Civil foundations and structural supports established, progressing to installation readiness
• Ball mill assembly nearing completion off-site, ready for delivery and installation towards the
end of July 2026
4
• Structural steel and platforms in place, supporting transition to mechanical installation
CIL Circuit
• Tank base construction advanced, with reinforced foundations and equipment pedestals
underway
• Structural integration progressing, aligned with tank delivery and installation schedule
• Circuit layout clearly defined within plant footprint
Tailings Thickener
• Foundations and support plinths completed, bund walls in progress and area advancing to be
ready for structural and tank installation
Elution Circuit and Pump Cells
• Civil works well advanced, supporting upcoming mechanical and piping installation
CIL Tanks and Process Vessels
• Fabrication well advanced, including:
o Tank shells installed with structural supports
o Nozzles, manways and lifting features fitted
• Multiple vessels in coating and finishing, nearing delivery-ready status
Structural Steel and Modular Build
• Significant structural steel fabricated and staged for deliveries
• Modular platforms and walkways manufactured, supporting efficient site erection
• Structural erection underway on site, progressing plant build-up
Tailings Storage Facilities (TSF)
• Contractors' mobilisation to the site completed
• TSF cut and fill groundworks are currently underway
• Orders placed on long lead items
Figure 4: TGME Gold Project Processing Plant (Plan View) Figure 5: Site aerial view highlighting plant
footprint and integrated construction progress
5
Figure 6: Elution circuit foundations Figure 7: Thickener tank/processing area
foundations
Figure 8: Gold Room construction continues - steel works Figure 9: CIL Tank fabrication
Figure 10: Ball Mill - complete shell, feed/discharge ends, drive interface
TGME construction has advanced across multiple work fronts during the quarter, with civil works
progressing across the broader plant footprint. More than 50% of total concrete volume has now been
poured, with foundations, platforms and structural elements advancing across the crushing, milling,
CIL, thickener, elution and gold room areas.
6
Structural steel erection also commenced, including works around the gold room and mill building,
supporting the project’s transition toward mechanical installation. Supporting infrastructure continued
to progress, including water infrastructure, process ponds, access roads and material handling areas.
Groundworks for the Tailings Storage Facility also commenced, adding another active construction
front during the quarter.
Figure 11: Concrete Pumping – Gold Room
Figure 12: Thickener Tank foundations in progress
Figure 13: West view of the plant – indicating the gold room and elution buildings
7
Figure 14: South view of the plant – indicating the civils for the crushing and screening plant
Figure 15: East view of the plant – indicating terrace walls and mill building
Permitting and Licences Update
The Company has secured a 15-year Water Use License (“WUL”) for Rietfontein. Now all four mines have
WUL, marking another significant regulatory milestone for the TGME Gold Mine Project.
The WUL authorises the water uses required for the redevelopment and operation of the mine, including
underground dewatering and water reuse, water storage, stream crossings, pollution control and waste
management infrastructure, and the rehabilitation of the historic Tailings Storage Facility following
remining activities.
The approval follows an extensive environmental assessment process supported by specialist studies,
engineering designs and technical investigations. Registered Interested and Affected Parties have been
notified of the decision, commencing the statutory 90-day appeal period.
The Environmental Authorisation application is in the final stages of review by the Department of Mineral
and Petroleum Resources, with a decision expected shortly. Once granted, the Company will have
secured all regulatory approvals required for the development of the Rietfontein Underground Mine, a
key component of the TGME Gold Project.
8
Funding and Finance Update
Settlement of US$90 Million Senior Secured Bond Facility and Completion of Debt Syndication
Theta Gold announced on 12 June 2026 it had achieved a major financing milestone with the successful
settlement of its US$90 million Senior Secured Bond Facility. The Company confirmed that all pre-
settlement conditions had been satisfied, the bonds were issued on 12 June 2026 (Oslo time), and the
net proceeds were deposited into a designated escrow account pending satisfaction of the remaining
drawdown conditions.
The bond financing represents the Company's primary debt funding for the development of the TGME
Gold Project. Funds held in escrow are to be released progressively in accordance with the facility's
drawdown conditions and will be applied towards construction and development of the project.
The successful settlement of the bond issue materially de-risked the Company's funding strategy and
marked the transition from project financing to execution. The Company subsequently focused on
satisfying the remaining drawdown conditions, including completion of the required equity funding
component, to enable release of the escrowed funds and commencement of full project development
activities.
The announcement of the secured Bond with Pareto Securities completes the previously announced
debt syndication process which received interest from several international debt financiers including a
non-binding term sheet with Nebari.
US$18.6 million (A$27 million) Combined Equity Raise and Options Exercise
On 29 June 20261
the Company announced it had secured firm commitments for a combined equity
raising and exercise of unlisted options, raising approximately US$18.6 million (A$27 million) before
costs. The funding transaction which was completed on 3 July 2026 satisfied the final equity funding
condition precedent required under the Company's US$90 million bond facility, representing a significant
milestone towards the development of the TGME Gold Mine Project.
The capital raising comprised:
• A placement of approximately 125.7 million fully paid ordinary shares at A$0.18 per share, raising
approximately US$15.6 million (A$22.6 million) before costs.
• The placement was cornerstoned by Chengtun Gold (Hong Kong) Limited, a subsidiary of
Shanghai Stock Exchange-listed Chengtun Mining Group Co. Ltd, which invested US$10 million.
• The exercise of approximately 21.7 million unlisted options at A$0.2002 per share, raising
approximately US$3.0 million (A$4.4 million) before costs from existing long-term strategic
investors.
New Placement Shares and Options Shares were issued to shareholders on 3 July 2026.
Following completion of the equity raising, the Company advised that it was well advanced in satisfying
the remaining drawdown conditions under the US$90 million bond facility announced on 12 June 2026.
1
Refer to ASX Release dated, 29 June 2026 titled, “US$18.6 million combined equity raise and options exercise
ahead of Bond Drawn”.
9
Funds raised from the placement, option exercises and bond facility will be applied towards the
continued construction and development of the TGME Gold Mine Project, including:
• processing plant construction;
• mine development;
• civil and infrastructure works;
• tailings storage facility construction;
• procurement and installation of plant and equipment;
• power infrastructure upgrades; and
• strengthening the Company's balance sheet and providing working capital to accelerate
development towards first gold production in 2027.
Chairman Bill Guy commented that completion of the equity component, together with the conditional
US$90 million bond issue, substantially de-risked the funding required to complete construction of the
processing plant and advance the TGME Gold Mine Project into production during 2027.
Executive Director Richie Yang noted that the cornerstone investment by Chengtun Mining and
continued support from existing long-term shareholders represented a strong endorsement of the
Company's progress and highlighted potential opportunities for future strategic collaboration.
Extension of At Call Facility
Theta Gold Mines is pleased to confirm that it has agreed with Acuity Capital to extend the maturity date
of its At-the-Market Subscription Agreement (“ATM”) to 31 July 2031.
As previously announced, the ATM was initially established with an expiry date of 31 July 2023 and
provided Theta Gold with an ATM limit of up to $15 million of standby equity capital. The initial ATM
expiry date was then extended to 31 July 2026. In addition, Acuity Capital holds 24,000,000 fully paid
ordinary TGM.ASX shares as security for the ATM (see previous announcements on 25 March 2021, 27
September 2021, and 31 July 2023).
Please note there is no requirement on Theta Gold to utilise the ATM and there were no fees associated
with the extension of the ATM. Further, no additional security has been provided or is requiredin relation
to the ATM extension.
Cash Position
As of 30 June 2026, the Group had US$13.3 million (A$19.3 million) in cash.
In accordance with ASX Listing Rules 5.3.1 and 5.3.2, the Company provides the following summary of
expenditures incurred during the Quarter:
Mining exploration costs (including exploration labour) US $ -
Mining Production and Development Costs US $ 7,832,464.18
Licence to Operate Costs US $ 37,962.13
Total US $ 7,870,426.31
The Company’s Quarterly Appendix 5B reported US$124,000 in payments to related parties and their
associates. As noted in Appendix 5B, these payments were for directors' fees and consulting fees.
10
Capital Structure
The current capital structure of the Company as at 30 June 2026 is as follows:
Number
Fully paid ordinary shares (ASX: TGM) 1,156,766,199
Listed /Unlisted options and performance rights (see “Annexure C”) 283,607,306
The estimated market capitalisation of TGM was A$231.35 million2
(US$160 million) as at 30 June 2026.
Revised Definitive Feasibility Highlights (released 3 February 2026)
Key operational results of the Revised Feasibility Study (FS):
❖ Production Start: Q1 2027 (TGME Gold Plant currently under construction)
❖ Head Grade LoM: 4.96g/t Base Case
❖ Base Case - Production: 871 Koz @ 4.28 g/t recovered grade (86.2% recovery)
❖ Base Case - Production: 1.06 Moz @ 4.40 g/t mined grade
❖ Production Ramp-up: Peak Production over 115 koz
❖ Ore Reserve Plan: 514 koz @ 4.11 g/t recovered grade (85.2% recovery)
❖ Gold plant: Plant construction underway
❖ Infrastructure: Existing surface/underground works, permitting in place
Robust Base Case Financials: (Gold price (avg) US$2,884/oz, (A$4,3653
/oz)) (Update 7 October
2025)
❖ Free Cash Flow: US$0.9 billion, (A$1.4 billion)
❖ Post-tax NPV10%: (at a 10% discount rate) of US$455 m, (A$689 m)
❖ Revenue: US$2.5 billion, (A$3.8 billion)
❖ Post-tax IRR: 77%
❖ Life of Mine (LOM): 13.1 years
❖ All-in sustaining cost: US$1,181/oz, (A$1,787/oz)
❖ Project payback: 29 months (from start of mining)
❖ Peak funding: US$77 m, (A$116 m)
2 Calculated as 1,156,766,199 fully-paid ordinary shares on issue at the closing price of AU$0.20 cents per share as at 30 June 2026 converted
at the RBA exchange rate of AUD:USD of 0.6896.
3 Exchange rate USD:AUD applied in relation to revised DFS was 0.6606.
11
Table 1: Project Economics at Various Gold Prices – Base Case (AUD)
Project Economics at AU$
Gold Price
Unit
Forecast
(USD2,884 /
oz Avg)
USD
2,500/oz
USD
3,000/oz
USD
3,500/oz
USD
4,000/oz
USD
4,500/oz*
USD
5,000/oz
Gold Price AUD / oz4
AUD/oz 4,365 3,784 4,541 5,298 6,055 6,812 7,568
NPV @ 10% (real) Pre-tax AUDm 991 758 1,070 1,382 1,695 2,008 2,321
NPV @ 10% (real) Post-tax AUDm 689 526 742 954 1,166 1,379 1,591
IRR (%) Pre-tax % 84% 69% 86% 102% 117% 131% 146%
IRR (%) Post-tax % 77% 63% 78% 92% 105% 118% 130%
AISC AUD/oz 1,787 1,750 1,800 1,848 1,896 1,943 1,990
EBITDA annual average AUDm 163 131 175 219 263 307 351
EBIT annual average AUDm 148 116 160 204 248 292 336
Free Cash Flow (Post-tax) AUDm 1,413 1,102 1,525 1,941 2,358 2,775 3,193
Development Capital – Peak
Funding
AUDm 116 131 116 116 116 116 116
Capital Sustaining AUDm 65 65 65 65 65 65 65
Payback post-tax Months 29 34 30 27 25 24 23
Capital Efficiency (Pre-Tax
NPV/Dev Capital
% 855% 580% 924% 1,194% 1,463% 1,734% 2,004%
Capital Efficiency (Post-Tax
NPV/Dev Capital
% 595% 403% 641% 824% 1,007% 1,190% 1,374%
* Note: at the time of release of this study, Spot Gold Price was trading in excess of US$4,000 / oz.
The Base Case Production Target and forecast financial information shown above and disclosed in this study are based
on Mineral Resources that include a proportion of Inferred Mineral Resources and the realisation of the full potential of
the Base Case as presented cannot be guaranteed. Inferred Mineral Resources are considered too speculative
geologically to have the economic considerations applied to them that would enable them to be classified as Ore
Reserves. There is no certainty that further exploration workor evaluation studies will result in the conversionofInferred
Mineral Resources to Indicated or Measured Mineral Resources or Ore Reserves.
Key FS Economic Results:
Under average gold prices of US$2,884 / oz (A$4,3655
/ oz), the Base Case scenario of FS demonstrates
strong financial returns6
(based on LOM plan), including:
o Undiscounted free cash flows of US$0.9 billion (A$1.4 billion), pre-tax US$1.3 billion (A$2.0
billion);
o NPV (at a 10% discount rate) of US$455 million (A$689 million), pre-tax US$654 million
(A$991 million);
o Capital payback period of 29 months;
o Post-tax IRR of 77%; pre-tax IRR of 84%
o Combined Underground Projects have an AISC of US$1,181/oz (A$1,787/oz); and
o Peak Capital requirement is US$77 million (A$116 million)7
, total initial capital US$102
million (A$154 million)8
.
4
Exchange rate USD:AUD applied throughout this document relating to the revised feasibility study is 0.6606.
5 Exchange rate USD:AUD applied throughout this document in relation to the revised DFS is 0.6606.
6 Financial returns applying the ‘Base Case’ scenario statistics.
7 TGM is currently in discussion with debt financiers and has engaged an experienced debt adviser to assist in the negotiation of term sheets for
funding of the Project. Further equity raises are also planned to fund working capital and part of the project capital if required, which may lead
to dilution of existing shareholders.
8 The FS demonstrates that post to Peak Funding, the balance of Total Capital requirement will be self-funded from project cashflow. The board
may however, consider external funding solutions such as via equity, debt, gold pre-sales, gold-streaming or a mixture of these methods.
12
Table 2: Key Project Metrics
Description Units Base Case Reserve Plan
Project Start Date1
Qtr/Year Q4 2025 Q4 2025
Commercial Production Date Qtr/Year Q1 2027 Q1 2027
Life of mine years 13.1 8.8
Underground ore mined (LOM) Mt 4.69 2.71
Surface ore remined (LoM) Mt 1.65 1.19
Mined Grade g/t 4.96 4.82
Gold Mined (LOM) Moz 1.01 0.60
Production Rate Kt/a 540 540
Production Rate Kt/m 45 45
Gold recovered (average LOM) % 86.2 85.2
Gold recovered (LOM) Moz 0.87 0.51
Table 3: Comparison of Base Case Financial Metrics – Feasibility Studies 2022 vs 2026
Project Economics at Gold Price US$
(Base Case)
Unit FS - Jul’ 229
FS - *Feb’ 26 % or Absolute
Life of Mine years 12.9 13.1 flat
Revenue USDbn 1.75 2.49 42%
Gold Price USD/oz 1,642 2,884 +1,242/oz
NPV @ 10% (real) Pre-tax USDm 324 654 102%
NPV @ 10% (real) Post-tax USDm 219 455 108%
IRR (%) Pre-tax % 65% 84% 29%
IRR (%) Post-tax % 57% 77% 35%
All In Sustaining Cost (AISC) USD/oz 834 1,181 42%
EBITDA (LoM) USDm 891 1,508 69%
EBITDA annual average USDm 69 115 67%
Free Cash Flow (Post-tax) USDm 508 933 84%
Development Capital – Peak Funding USDm 77 77 flat
Capital Sustaining USDm 37 44 7
Payback Post-tax Months 31 28 flat
Due to rounding, numbers presented throughout this document may not add up precisely to the totals provided and percentages may not
precisely reflect the absolute figures.
* - Mine Plan revised
Cost Control/Value Focus:
TGM continues to deliver strong project execution and disciplined cost management. The TGME Project’s
post-tax value has surged to US$455 million—an impressive US$236 million uplift over the 2022 FS—
driven largely by higher gold prices. This pricing strength has unlocked the ability to profitably mine
lower-grade ore.
Project Summary:
The TGME Gold project, located in the Mpumalanga province of South Africa, is shown below.
9 Ref to ASX Release dated 27 July 2022 titled, “Theta Gold’s TGME Project DFS confirms NPV of AUD432 Million”.
Key Assumptions: Long term average spot gold price of US$2,884 applied in Base Case scenario over LOM / AISC estimation of US$1,181/oz at
+/- 15% level of accuracy.
13
Figure 16: TGME Gold Project Location Map
14
Two mine scheduling strategies have been investigated, namely:
• Base Case: LOM Plan includes a Production Target of 1.01 Moz targeting Measured, Indicated and
Inferred Mineral Resources; and
• Ore Reserve Plan: LOM Plan includes a Production Target of 604 koz targeting Measured and
Indicated Mineral Resources only.
Table 4: Key Project Metrics
Description Units Base Case Reserve Plan
Project Start Date1
Qtr/Year Q4 2025 Q4 2025
Commercial Production Date Qtr/Year Q1 2027 Q1 2027
Life of mine years 13.1 8.8
Underground ore mined (LOM) Mt 4.69 2.71
Surface ore remined (LoM) Mt 1.65 1.19
Mined Grade g/t 4.96 4.82
Gold Mined (LOM) Moz 1.01 0.60
Production Rate Kt/a 540 540
Production Rate Kt/m 45 45
Gold recovered (average LOM) % 86.2 85.2
Gold recovered (LOM) Moz 0.87 0.51
Strong Upside options:
• Phase 2 unlocks scale: 7 mines, 90 ktpm processing, and up to 160 koz/year gold output within
five years.
• Growth runway secured: 40 nearby historical mines and defined exploration targets offer
substantial resource upside.
• Low-cost mining advantage: All current reserves and LOM material hosted in shallow orebodies
(<400m).
• Cost discipline embedded: Competitive pricing achieved through active tendering of mine
services across South Africa.
• Built for sustainability: ESG-focused design reduces energy use, broadens workforce diversity,
and attracts green-aligned suppliers.
Project Execution Strategy and Plan:
The project will ramp up in phases, targeting an initial Phase 1 Run-Of-Mine (RoM) output of 45 ktpm from
multiple underground mines. This staged approach is underpinned by the FS Base Case, leveraging
Measured, Indicated, and Inferred Resources to maximise early production and flexibility.
In order to achieve this, mining operations are planned to commence as follows:
• Beta Mine - Beta Mine will kick off with 18 months of pre-development, followed by stoping from
month 19. In the Base Case, the mine is expected to deliver around 30 ktpm of stoping ore for
8.5 years, within a total Life of Mine of 10.1 years.
• Rietfontein Mine - Rietfontein Mine will start mining in 18 months after Beta, stoping after eight
months of pre-development. Stoping begins in month 27, with plans to produce 15 ktpm of ore.
• Frankfort and CDM Mines - Frankfort and CDM Mines will begin mining in months 104 and 90,
with 16 and 19 months of pre-development planned, respectively. Frankfort is set to produce 15
ktpm, feeding a DMS plant that delivers 9.5 ktpm. CDM will also produce 15 ktpm at steady state.
15
Mining of the historic rock dumps and TGM Plant TSF will beginin months 7 and 16, respectively, following
the start of operations. The Waste Rock Dump will be mined over 10 months at 45 ktpm, enabling a
smooth ramp-up of Beta’s operations. TSF material will feed the plant for 4 months during ramp-up and
continue as needed, with a total retreatment life of 79 months.
Figure 17: Annual and Cumulative Cash Flow (Post-Tax) – Base Case (AUD)
NOTES:
1. Forecast Prices averaging US$2,884/oz over LOM.
2. Converted to AUD from USD at exchange rate of 1.514 AUD:USD.
16
[ENDS]
This announcement was approved for release by Theta Gold Mines Limited’s Board.
For more information, please visit www.thetagoldmines.com or contact:
Bill Guy, Chairman
Theta Gold Mines Limited
T: +61 2 8046 7584 E: billg@thetagoldmines.com
Investor Relations and Media Communications
We’re committed to keeping you informed and involved. Sign up for the Engage IR App and
Investor Hub today and join the conversation.
Webpage: www.thetagoldmines.com
https://twitter.com/ThetaGoldMines
https://www.linkedin.com/company/thetagoldmines/
17
Figure 18: Stationary Crane now fixed in place at site for construction and maintenance
18
Competent Persons Statement
MINERAL RESOURCES
Mr. Uwe Engelmann confirms that he is the Competent Person for the TGM Mineral Resources as
reported on TGM’s Mineral Resources which is extracted from TGM’s ASX announcement dated 8 April
2021 (Initial Maiden Underground Mining Reserve) available to view at www.asx.com.au and was
prepared in accordance with the guidelines of the 2012 Edition of the Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves (JORC Code, 2012). Mr. Engelmann has read
and understood the requirements of the JORC Code (2012).
Mr. Engelmann is a Competent Person as defined by the JORC Code, 2012, having more than five years’
experience that is relevant to the style of mineralisation and type of deposit described in this report and
to the activity for which he is accepting responsibility. Mr. Engelmann (BSc (Zoo. & Bot.), BSc Hons (Geol.),
Pr.Sci.Nat. No. 400058/08, FGSSA), is a director of Minxcon (Pty) Ltd and a member of the South African
Council for Natural Scientific Professions. Mr. Engelmann is a full-time employee of Minxcon (Pty) Ltd
and has reviewed this report and consents to the inclusion of the matters based on his supporting
information in the form and context in which it appears.
METALLURGICAL RESULTS
Mr. Rogan Roulstone confirms that he is the Competent Person in terms of Mineral Resources and Ore
Reserves (JORC Code, 2012). Mr. Roulstone has read and understood the requirements of the JORC Code
(2012).
Mr. Roulstone is a Competent Person as defined by the JORC Code, 2012, having more than five years’
experience that is relevant to gold extraction and in particular gold extraction from a refractory ore body.
Mr Roulstone holds a National Higher Diploma in Chemical Engineering and graduated in 1993 and is
member of the SAIMM (705817). Mr Roulstone is the managing director of RM Process and has over nine
years’ experience on the TGME process plant design.
The information in this announcement that relates to TGM’s Mineral Resources is extracted from TGM’s
ASX announcement dated 8 April 2021 (Initial Maiden Underground Mining Reserve) available to view at
www.asx.com.au and was prepared in accordance with the guidelines of the JORC Code (2012). TGM
confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcement and that all material assumptions and technical
parameters underpinning the Mineral Resources estimates in the relevant market announcement
continue to apply and have not materially changed other than as disclosed in TGM’s ASX announcement
dated 25 October 2021 regarding the TGME Project Permitting Update. TGM confirms that the form and
content in which the Competent Person’s findings are presented have not been materially modified from
the original market announcement.
ORE RESERVES
The information in this report relating to Ore Reserves is based on, and fairly reflects, the information
and supporting documentation compiled by Mr. Daniel van Heerden (B.Eng (Mining), M.Com (Business
Management), member of Engineering Council of South Africa (Pr.Eng. Reg. No. 20050318)), a director
of Minxcon (Pty) Ltd and a fellow of the South African Institute of Mining and Metallurgy (FSAIMM Reg.
No. 37309).
Mr Van Heerden has sufficient experience that is relevant to the style of mineralisation under
consideration and to the activity being undertaken to qualify as a Competent Person as defined in the
JORC Code (2012). Mr van Heerden consents to the inclusion in the report of the matters based on his
information in the form and context in which it appears.
The information in this announcement that relates to TGM’s Ore Reserves is extracted from TGM’s ASX
announcement dated 8 April 2021 (Initial Maiden Underground Mining Reserve) available to view at
www.asx.com.au and was prepared in accordance with the guidelines of the JORC Code (2012). TGM
confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcement and that all material assumptions and technical
19
parameters underpinning the Ore Reserve estimates in the relevant market announcement continue to
apply and have not materially changed other than as disclosed in TGM’s ASX announcement dated 25
October 2021 regarding the TGME Project Permitting Update. TGM confirms that the form and content
in which the Competent Person’s findings are presented have not been materially modified from the
original market announcement.
About Theta Gold Mines Limited
Theta Gold Mines Limited (ASX: TGM) is an advanced gold development company focused on unlocking