TGM - Pre-Construction Activities Update
Released
Released
Announcement PDF
16 June 2025
ASX ANNOUNCEMENT
(ASX: TGM)
Pre-Construction Advancing - Old Plant Successfully
Decommissioned and Final Designs Complete
Theta Gold Mines Limited (“Theta Gold” or the “Company”) (ASX: TGM) is pleased to provide an
operational update regarding TGME Gold Processing Plant progress. Key pre-construction milestones are
progressing, with the old gold plant decommissioned and final design and engineering packages for the
new plant completed.
HIGHLIGHTS
•
•
•
•
•
•
Pre-development plant construction preparation completed
Earthworks and maintenance equipment now being delivered to site
Major deconstruction milestone: tanks, thickeners, and structures safely dismantled using
mobile cranes
Site cleared — bulk earthworks and civil works ready to commence
Electrical Installation to supply temporary power to plant
Debt advisors engaged to structure and secure commercial co-lenders to complement IDC loan
facility
Figure 1: Mobile Cranes and Flatbed Trucks assisting in deconstructing the old plant.
1
Pre-Development Works Completed — TGME Plant Site Ready for Construction
TGM is pleased to announce the successful completion of pre-development plant construction
preparation work in May and early 2025, achieved on time and within budget, including:
•
•
•
•
•
•
Safe completion of pre-development plant construction preparation work
Deconstruction of legacy infrastructure, including the Gold Room, Laboratory, Workshops, and
Stores
Replacement of the old underground electrical reticulation with a new temporary installation
Deconstruction and relocation of steel structures and the 1mtpa ball mill to the laydown area
Site readiness for bulk earthworks and civil construction
Delivery of Zoomlion equipment (excavator ZE335E and Telehandler ZTH3513) for the
construction phase
Figure 2: Removal of old mill civils and thickeners
2
Figure 3: Installation of temporary electrical plant supply
Figure 4: Breaking of old mill civils and loading of ball mill
3
Figure 5: Lifting and loading of the big ball mill for transport to the laydown area
Figure 6: Initial new bulk earth equipment delivered
As previously announced (10 June 2025 1), the Company has locked in a 13-year renewal of Mining Right
83 (“MR83”) through to 2038 — a key approval covering the Beta, CDM, and Frankfort mines, which
together account for over 75% of current FS mine schedule. This renewal cleared a key condition
1
Refer to ASX release dated 10 June 2025 titled, “TGM receives US$35 million loan facility funding agreement”.
4
precedent for project financing and marks a significant step toward full project execution. Notably, TGM’s
subsidiary has held this strategic ground for over 130 years (since 1895).
TGME Project Financing Update
As announced (10 June 20252), the Company has received agreed credit approved Loan Facility Agreement
(“Facility”) and indicative funding terms from the Industrial Development Corporation of South Africa
(“IDC”) for the joint funding of the TGME Underground Gold Mine Project in South Africa (the “Project”).
Finalisation of the Facility with IDC is subject to conditions precedent (which are to be fulfilled to the
Lenders’ satisfaction) including finalisation of definitive loan facility documentation.
Key terms include:
• IDC has approved a loan of up to US$35m3 (A$53.8m) which is expected to form part of the overall
Project debt funding
•
Debt term offered for 7 years from first drawdown, including an initial 18-month capital & interest
moratorium
•
Legal, Technical and Environmental Due Diligence completed
•
Discussions on-going with other potential co-lenders
•
With the IDC Loan Facility Agreement approved, TGM is now moving to secure an agreement with
co-lender’(s), following the appointment of a specialist South African debt advisor, Moore Debt
Advisory. This key financing milestone is expected to catalyse broader bank participation and
accelerate project funding momentum. Moore Debt Advisory are a specialist debt and equity
team based in South Africa.
Chairman, Bill Guy commented: “We are proud to have completed all pre-construction works at the
TGME project on time and within budget, with the old plant safely decommissioned and final engineering
designs now complete. This marks a major step forward as we transition to full-scale construction4.
With the renewal of Mining Right 83 secured and the IDC cornerstone loan facility approved, we are now
actively advancing commercial funding discussions with support from our newly appointed debt advisors.
Momentum is building, and we’re well-positioned to deliver on our long-term vision for Theta Gold. “
ENDS
This announcement was approved for release by Theta Gold Mines Limited’s Board.
For more information, please visit www.thetagoldmines.com or contact:
Bill Guy, Chairman
Theta Gold Mines Limited
T: + 61 2 8046 7584 E: billg@thetagoldmines.com
2
Refer to ASX Release dated 10 June 2025, titled “TGM receives US$35 million loan facility agreement”
OFX quoted exchange rate of 17.78 for USD:ZAR on 8 June 2025
4
Subject to completion of funding packages for construction CAPEX requirements.
3
5
The Industrial Development Corporation of South Africa (IDC):
The Industrial Development Corporation of South Africa is a state-owned institution that
provides financial support to promote economic growth and development in South Africa. IDC
funds viable businesses to enhance industrial capacity and contribute to the economic growth
of South Africa and the African continent. IDC emphasizes on labour-intensive industrialization,
whether it is created directly through its funding of companies or by enabling downstream
activities. IDC supports businesses to drive key development outcomes that ultimately lead to
equitable economic growth, creating and sustaining jobs.
Investor Relations
We’re committed to keeping you informed and involved. Download the Engage IR App today and
join the conversation.
Webpage: www.thetagoldmines.com
https://twitter.com/ThetaGoldMines
https://www.linkedin.com/company/thetagoldmines/
6
ANNEXURE A
Mineral Resource and Mining Reserves
Combined Mineral Resource as at 1 February 2021
Combined Mineral Resource
Resource
Classification
Measured
Type of Operation
Tonnage
Gold Grade
Mt
g/t
Underground
Open pit
Tailings
Total Measured
Indicated
Underground
Open Pit
Tailings
Total Indicated
Inferred
Underground
Open pit
Tailings
Rock Dump
Total Inferred
Grand Total
Notes:
1.
2.
3.
4.
5.
6.
Gold Content
Kg
koz
0.091
5.37
489
15.7
0.091
4.774
8.109
5.244
18.128
21.452
4.907
0.023
0.885
27.267
45.485
5.37
6.21
2.14
0.83
2.84
5.22
5.11
0.57
1.20
5.06
4.17
489
29 661
17 364
4 373
51 398
111 880
25 057
13
1 059
138,009
189,896
15.7
953.7
558.2
140.6
1,652.5
3597.0
805.6
0.4
34.0
4,437.0
6,105.2
Columns may not add up due to rounding.
Gold price used for the cut-off calculations is USD1,500/oz.
UG Mineral Resources are reported at a cut-off of 160 cm.g/t, open pit at 0.5 g/t and 0.35 g/t, tailings and rock dumps at 0.35
g/t.
Fault losses of 5% for Measured and Indicated, 10% for Inferred Mineral Resources.
Mineral Resources are stated as inclusive of Ore Reserves.
Mineral Resources are reported as total Mineral Resources and are not attributed.
Mineral Resources for the TGM Tailings Dams as at 1 February 2021
Mineral Resource
Classification
Surface Operation
Indicated
Glynn’s Lydenburg
Blyde 1
Blyde 2
Blyde 3
Blyde 4
Blyde 5
TGM Plant
Reef
Tailings
Tailings
Tailings
Tailings
Tailings
Tailings
Tailings
Total Indicated
Mineral Resource
Classification
Inferred
Total Inferred
Notes:1.
2.
3.
4.
5.
Surface Operation
Blyde 3a
Reef
Tailings
Tonnage
Mt
1.211
0.590
0.280
0.316
0.164
0.022
2.661
5.244
Gold
Grade
g/t
0.80
0.73
0.83
0.87
0.72
0.61
0.87
0.83
Gold Content
kg
koz
972
31.3
434
14.0
234
7.5
275
8.8
119
3.8
14
0.4
2,325
74.8
4,373
140.6
Tonnage
Mt
0.023
0.023
Gold
Grade
g/t
0.57
0.57
Gold Content
kg
koz
13
0.4
13
0.4
Mineral Resource cut-off of 0.35 g/t applied.
TGM Plant tailings: 10% discount applied for volume uncertainty.
Gold price used for the cut-off calculations is USD1,500/oz.
Mineral Resources are stated as inclusive of Ore Reserves.
Mineral Resources are reported as total Mineral Resources and are not attributed.
7
Mineral Resources for the TGM Rock Dumps as at 1 February 2021
Mineral Resource
Classification
Inferred
Inferred
Inferred
Inferred
Inferred
Total Inferred
Notes:1.
2.
3.
4.
Surface Operation
Vaalhoek
South East (DGs)
Peach Tree
Ponieskrantz
Dukes Clewer
Reef
Rock Dump
Rock Dump
Rock Dump
Rock Dump
Rock Dump
Tonnage
Mt
0.121
0.408
0.092
0.129
0.134
0.885
Gold
Grade
g/t
1.64
0.93
1.23
1.63
1.16
1.20
Gold Content
kg
koz
199
6.4
379
12.2
114
3.7
211
6.8
156
5.0
1,059
34.0
Mineral Resource cut-off of 0.35 g/t applied.
Gold price used for the cut-off calculations is USD1,500/oz.
Mineral Resources are stated as inclusive of Ore Reserves.
Mineral Resources are reported as total Mineral Resources and are not attributed.
Combined Underground and Open Pit Ore Reserves as at 1 February 2021
Operation
Beta
Frankfort
CDM
Open Pit (MR83)
Total
Notes:
1.
Grade
g/t
Tonnes
kt
6.51
4.13
2.31
2.74
3.98
Au Content
kg
1,662
319
385
2,164
4,530
10,822
1,317
889
4,996
18,023
koz
347.94
42.33
28.58
160.61
579.46
The information pertaining to the Ore Reserve estimation is detailed in the notes of the Ore Reserve tabulation for the
individual operations.
8
ABOUT THETA GOLD MINES LIMITED
Theta Gold Mines Limited (ASX: TGM) is an advanced gold development company focused on unlocking
value from its extensive suite of projects in South Africa’s renowned Eastern Transvaal goldfields. The
Company’s flagship TGME Gold Project offers near-surface and shallow underground ore bodies with
compelling cost advantages.
TGM’s core project is located next to the historical gold mining town of Pilgrim’s Rest, in Mpumalanga
Province, some 370km northeast of Johannesburg by road or 95km north of Nelspruit (Capital City of
Mpumalanga Province). Following small scale production from 2011 – 2015, the Company is currently
focussing on the construction and financing of a new gold processing plant.
TGM has completed a Feasibility Study (FS) released to ASX on 27 July 2022, for the first four mines Beta,
CDM, Frankfort and Rietfontein (TGME Underground Project). The Base Case LOM plan comprises a 12.9year mining operation starting in 2023 and delivering production of 1.24 million ounces of contained gold.
The estimated development capital or peak funding requirement is USD77 million (AUD102 million), with
the Project forecast to generate a pre-tax NPV10% of USD324 million (AUD432 million) and pre-tax Internal
Rate of Return (IRR) of 65% at the forecast gold price of averaging USD1,642/oz over the LOM.
TGM aims to build a solid production platform to over next 5 years to 160kozpa based primarily around
shallow, open-pit or adit-entry shallow underground hard rock mining sources. Theta Gold has access to
over 43 historical mines and prospect areas that can be accessed and explored, with over 6.7Moz of
historical production recorded.
TGM holds 100% of Theta Gold SA (Pty) Ltd, which in turn owns 74% of TGME and Sabie Mines, meeting
Black Economic Empowerment (BEE) ownership standards as per South African Mining Charter
requirements.
DISCLAIMER
This announcement has been prepared by and issued by Theta Gold Mines Limited to assist in informing
interested parties about the Company and should not be considered as an offer or invitation to subscribe
for or purchase any securities in the Company or as an inducement to make an offer or invitation with
respect to those securities. No agreement to subscribe for securities in the Company will be entered into
on the basis of this announcement.
This announcement may contain forward looking statements. Whilst Theta Gold has no reason to believe
that any such statements and projections are either false, misleading or incorrect, it does not warrant or
guarantee such statements. Nothing contained in this announcement constitutes investment, legal, tax
or other advice. This overview of Theta Gold does not purport to be all inclusive or to contain all
information which its recipients may require in order to make an informed assessment of the Company’s
prospects. Before making an investment decision, you should consult your professional adviser, and
perform your own analysis prior to making any investment decision. To the maximum extent permitted
9
by law, the Company makes no representation and gives no assurance, guarantee or warranty, express or
implied, as to, and take no responsibility and assume no liability for, the authenticity, validity, accuracy,
suitability or completeness of, or any errors in or omissions, from any information, statement or opinion
contained in this announcement. This announcement contains information, ideas and analysis which are
proprietary to Theta Gold.
The Company confirms that all material assumptions underpinning the production target, or the forecast
financial information derived from the production target continue to apply and have not materially
changed from those previously released to ASX in a Feasibility Study dated 27 July 2022.