Investor Presentation - Mines & Money African Opportunities
Released
Released
Announcement PDF
HIGH GROWTH,
LOW-COST GOLD DEVELOPER
6.1MOZ GOLD RESOURCE &
GROWING
CEO PRESENTATION – 10 MARCH 2022
DISCLAIMER
FORWARD LOOKING AND CAUTIONARY STATEMENTS
DISCLAIMER AND COMPETENT PERSONS STATEMENT
This presentation may refer to the intention of Theta Gold Mines regarding estimates or future events which could
be considered forward looking statements. Forward looking statements are typically preceded by words such as
“Forecast”, “Planned”, “Expected”, “Intends”, “Potential”, “Conceptual”, “Believes”, “Anticipates”, “Predicted”,
“Estimated” or similar expressions. Forward looking statements, opinions and estimates included in this
announcement are based on assumptions and contingencies which are subject to change without notice, and may
be influenced by such factors including but not limited to funding availability, market-related forces (commodity
prices, exchange rates, stock market indices and the like) and political, environmental or economic events (including
government or community issues, land owners, global or systemic events). Forward looking statements are provided
as a general reflection of the intention of the Company as at the date of release of the document, however are subject
to change without notice, and at any time. Future events are subject to risks and uncertainties, and as such results,
performance and achievements may in fact differ from those referred to in this announcement. Mining, by its nature,
and related activities including mineral exploration, are subject to a large number of variables and risks, many of
which cannot be adequately addressed, or be expected to be assessed, in this document. Work contained within or
referenced in this report may contain incorrect statements, errors, miscalculations, omissions and other mistakes.
For this reason, any conclusions, inferences, judgments, opinions, recommendations or other interpretations either
contained in this announcement, or referencing this announcement, cannot be relied upon. There can be no assurance
that future results or events will be consistent with any such opinions, forecasts or estimates. The Company believes
it has a reasonable basis for making the forward looking statements contained in this document, with respect to any
production targets, resource statements or financial estimates, however further work to define Mineral Resources or
Reserves, technical studies including feasibilities, and related investigations are required prior to commencement of
mining. No liability is accepted for any loss, cost or damage suffered or incurred by the reliance on the sufficiency or
completeness of the information, opinions or beliefs contained in this announcement.
DISCLAIMER
This announcement or presentation has been prepared by and issued by Theta Gold Mines Limited (ASX:TGM |
OTCQB: TGMGF) to assist in informing interested parties about the Company and should not be considered as an
offer or invitation to subscribe for or purchase any securities in the Company or as an inducement to make an offer
or invitation with respect to those securities. No agreement to subscribe for securities in the Company will be entered
into on the basis of this announcement.
The Feasibility Study referred to in this announcement is based on technical and economic assessments to support
the estimation of Ore Reserves. There is no assurance that the intended development referred to will proceed as
described, and will rely on access to future funding to implement. Theta Gold Mines believes it has reasonable grounds
the results of the Feasibility Study. At this stage there is no guarantee that funding will be available, and investors are
to be aware of any potential dilution of existing issued capital. The production targets and forward looking statements
referred to are based on information available to the Company at the time of release, and should not be solely relied
upon by investors when making investment decisions. Theta Gold cautions that mining and exploration are high
risk, and subject to change based on new information or interpretation, commodity prices or foreign exchange rates.
Actual results may differ materially from the results or production targets contained in this release. Further evaluation
is required prior to a decision to conduct mining being made. The estimated Mineral Resources quoted in this release
have been prepared by Competent Persons as required under the JORC Code (2012). Material assumptions and
other important information are contained in this release.
This announcement or presentation may contain forward looking statements. Whilst Theta Gold Mines has no reason
to believe that any such statements and projections are either false, misleading or incorrect, it does not warrant
or guarantee such statements. Nothing contained in this announcement constitutes investment, legal, tax or other
advice. This overview of Theta Gold Mines does not purport to be all inclusive or to contain all information which its
recipients may require in order to make an informed assessment of the Company’s prospects. Before making an
investment decision, you should consult your professional adviser, and perform your own analysis prior to making
any investment decision. To the maximum extent permitted by law, the Company makes no representation and gives
no assurance, guarantee or warranty, express or implied, as to, and take no responsibility and assume no liability for,
the authenticity, validity, accuracy, suitability or completeness of, or any errors in or omissions, from any information,
statement or opinion contained in this announcement. This announcement contains information, ideas and analysis
which are proprietary to Theta Gold.
COMPETENT PERSONS STATEMENT
The information in this report relating to mineral resources and ore reserves is based on, and fairly reflects, the
information and supporting documentation compiled by Mr Uwe Engelmann (BSc (Zoo. & Bot.), BSc Hons (Geol.),
Pr.Sci.Nat. No. 400058/08, MGSSA), a director of Minxcon (Pty) Ltd and a member of the South African Council for
Natural Scientific Professions and Mr Daniel van Heerden (B.Ing (Mining M.Com (Business Management), member
of Engineering Council of South Africa (Pr.Eng. Reg. No. 20050318)), a director of Minxcon (Pty) Ltd and a fellow of
the South African Institute of Mining and Metallurgy (FSAIMM Reg. No. 37309).
The original reports titled “Theta Gold Increases Mineral Resource to over 6Moz” dated 16 May 2019, “Optimised
Mine Schedule for Theta Open Pit Starter Project Delivers Significant Improvements” dated 20 April 2020 and “Initial
Maiden Underground Mining Reserve 419,000 oz Gold” dated 8 April 2021 were released to the Australian Securities
Exchange (ASX) on those dates. The Company confirms that:
•
•
it is not aware of any new information or data that materially affects the information included in the ASX
announcements; and
all material assumptions and technical parameters underpinning the estimates in the ASX announcements
continue to apply and have not materially changed.
NOTE BUSINESS ARRANGEMENT
Theta Gold Mines holds 100% issued capital of its South African subsidiary Theta Gold SA (Pty) Ltd (“TGSA”).
TGSA holds a 74% shareholding in both Transvaal Gold Mining Estates Limited (“TGME”) and Sabie Mines (Pty)
Ltd (“Sabie Mines”). TGME holds the various exploration and mining permits. The balance of shareholding is held
by Black Economic Empowerment (“BEE”) entities. The South African Mining Charter requires a minimum of 26%
meaningful economic participation by the historically disadvantaged South Africans (“HDSAs”). The BEE shareholding
in TGME and Sabie Mines is comprised of a combination of local community trusts, an employee trust and a strategic
entrepreneurial partner.
AUTHORISATION
This announcement was authorised for release by the Board of Theta Gold Mines Limited.
2
COMPELLING INVESTMENT RATIONALE
INVESTMENT CASE
SIZE
INVESTOR
VALUE
POTENTIAL
GROWTH
LOW-COST
PRODUCER
EXPERIENCED
TEAM
FLEXIBILITY
POSITIVE
SOCIO-ECONOMIC
IMPACT
+6.1Moz of Gold
Resources and
continuously
expanding
Reserves, a top 3
undeveloped gold
resource on the ASX
not owned by majors
Undervalued
compared to similar
size peers Bellevue
(ASX: BGL); Nova
(ASX: NVA); DRD
Gold (NYSE/JSE:
DRD)
Low-cost expansion
based on >130years
data (+40 old
mines) and recent
exploration success
+160koz pa (within
5 years) from
pre-developed
near-surface gold
resources
Production costs
significantly lower
than current gold
price (AISC)
Resource
optimisation
specialists with over
250 years’ combine
experience
Multiple entry points
provide optionality
in the development
strategy
1,500 jobs created
over 5 years,
revitalization of
Piligrim’s Rest
tourism, knock-on
positive effect on
host community
economy
3
TEAM OF EXPERTS
BILL GUY
MITFORD MUNDELL
JACQUES DU TRIOU
CHAIRMAN
CEO
COO
Ex-Jupiter Mines Ltd (ASX: JMS)
Chief Exploration Manager. (Jupiter
was/is controlled by London based
Pallinghurst Group, Chairman
Mr. Brian Gilbertson was former
Chairman/CEO BHP Billiton).
Over 25yrs exploration & resource
development experience.
Former CEO of Namakwa
Diamonds, commissioned and
expanded profitable production,
extended a 3-year LoM to +20
years. 12 years at Harmony
Gold, and 5 years at De Beers.
Specialises in asset optimisation
and large-scale change
execution.
Over 16 years at Harmony Gold.
Led the Doornkop South Reef
Deepening Project and Kusasalethu
turnaround. Turnaround and
business improvement specialist.
FINN BEHNKEN
TERENCE MOKALE
RICHIE YANG
Puseletso Matete
NON-EXECUTIVE
DIRECTOR
RSA DIRECTOR – SOCIAL
CORPORATE SERVICES
NON-EXECUTIVE
DIRECTOR
RSA DIRECTOR - ESG
Admitted attorney of the
High Court of South Africa
specialising in Social
Facilitation. Also consulted
for Glencore, Gold One and
most recently SibanyeStilwater on community/
stakeholder relations.
Former Executive
Director of gold resource
company Bligh
Resources Ltd (ASX:
BGH) recently taken-over
by Saracens (ASX: SAR).
Former CEO of Tshipi é
Ntle Manganese Mining
(Pty) Limited (currently
49% owned by Jupiter
Mines Ltd).
She is currently Head of
Sustainable Development &
Environment at a tier-1 global
mining house. A member of the
Lesotho Highlands
Development Authority’s
Sustainable Development
Committee. Puseletso is a true
ESG expert.
SIMON LIU
BRETT TANG
BYRON DUMPLETON
NON-EXECUTIVE
DIRECTOR
NON-EXECUTIVE
DIRECTOR
NON-EXECUTIVE
DIRECTOR
Fund manager; co-founder of
Hanhong PE Fund with significant
exposure to gold and oil & gas
projects globally.
Former fund manager at Tasman
Funds with >15 years of gold/base
metal experience.
Over 30 years technical and
operational experience. Mr
Dumpleton has worked for
KCGM (Kalgoorlie Super Pit),
WMC (St Ives Gold Mine),
Straits Resources, Newcrest
(Telfer) and is currently the Chief
Geologist for Red 5.
4
CORPORATE OVERVIEW
A WARM WELCOME to those ex-Focus Mineral
Shareholders to TGM’s register
Ordinary
Shares ASX: TGM
Unlisted options +
management performance
rights
538m
Theta Offered to buy FML shares from its shareholders with scrip
by offering 5 TGM for every 1 FML held.
41.1m + 12.4m
Market Capitalisation
(9 March 2022,
undiluted)
The Offered lapsed on 2 March 2022.
Theta now sits as #4 shareholder in Focus Minerals’ register,
with a ~2.8% interest.
~A$77M
(~US$63M)
Focus’ current Market Capitalisation is ~A$72m
Focus holds two large gold mining assets inside Western
Australia, namely in Laverton and Coolgardie respectively.
68%
Top 10
shareholding
9%
Directors &
Management
Theta strongly believes it may offer Management & Operational
synergies with the Focus Board in the long term, and will stay
pro-active in managing its interest in the company and the
relationship with its controlling shareholder Shandong Gold.
5
PROJECT
OVERVIEW
6
SOUTH AFRICA’S “GOLDEN TRIANGLE”
THETA GOLD – 6.1MOZ DEVELOPER – TO PRODUCE >160KOZ/A [Current Market Capitalisation: AU$80M]
SA host the 3rd largest
gold reserves in the
world (~6,000T Au)
7
6 UG MINES TARGETED FIRST OUT OF POTENTIAL >40
5
solid growth potential
2
3
Modern mining and treatment
methodologies enable
low-cost operations (AISC
US$900/oz) and reserve
expansion
Develop multiple mines,
reaching >160koz/a within
five years, from the resource
base of +6Moz
1
LEGEND
1.
Beta
2.
Frankfort
3.
CDM
4.
Rietfontein
5.
Vaalhoek
6.
Glynn’s Lydenburg
Various expansion
opportunities to increase
production and the resource
base for >3 decades
First three-mine operation,
central plant and tailings
facility >60koz/a @ 30-37kt/m
6
4
Expand to >160koz/a - 6
mine operation @ 80kt/m
8
STRATEGY TO BUILD UP TO >160,000OZ/A AU PRODUCTION PROFILE
WITHIN 5 YEARS
PHASE 1
COMMISSION
First Gold
2023
PHASE 2
COMMISSION
50-70koz/a
•
3 mining production units
37.5 kt/m Metallurgical plant
Recommission existing Tailings Storage Facility (TSF)
Production from UG (Beta, Frankfort, CDM) surface
dumps & Pre-Mined Residues
Production 50-70 koz/a
>160koz/a
90-120koz/a
PHASE
1
•
•
•
•
PHASE 3
COMMISSION
PHASE
3
PHASE
2
•
•
•
•
•
Expand to 5 mining production units
Expand Met plant to 50kt/m
Expand TSF and establish underground tailings
deposition
Expand production to Rietfontein
Production 90-120 koz/a
•
•
•
•
Expand to 7 mining production units
Expand Met plant to 80 kt/m
Expand production to Vaalhoek, Glynn’s Lydenburg
and open pit
Production 160 – 200 koz/a
Assess other 40 old mines, expand reserves through exploration, development and drilling on operating mines and new targets exploration
9
FINANCIAL
PROJECTIONS
10
TGME UNDERGROUND INITIAL PFS
FIRST 16 % OF
UNDERGROUND
MINERAL
RESOURCE
Pay-back period from
first gold 13 months
Pay-back period from
start of mining 22
months
419 Koz delivered to
plant over Life of Mine
By third year of production,
almost 70 koz / year
(3 production units)
Life of Mine (LoM)
7.67 years
$241.2 million EBITDA
over LoM
Internal Rate of
Return 82%
SURFACE INFRASTRUCTURE PLAN BETA UNDERGROUND MINE AND
PLANT LAYOUT
US$ 905 / oz all-in sustaining
cost (AISC) over LoM
(bottom quartile SA
Producer)
Note: PFS numbers refering to ASX Released dated 13 April 2021 – “Pre-feasibility Study for Initial Underground Project”
$91.2 million Net
Present Value
Total Capital Expenditure (CAPEX)
$79 million LOM includes:
•
•
•
•
Peak CAPEX - $36M (Start-up
Plant and Beta Mine development )
Total Direct CAPEX - $54M
Total SIB CAPEX - $13.7M
Total contingent CAPEX - $10.8 M
11
Note: All $ in USD, PFS based case done at US$1570/oz gold price.
LOW-COST SUSTAINABLE GOLD PRODUCER WITH HIGH MARGINS
COST DRIVERS
PHASE 1 UG
$1,500
$1,250
>50%
Upside gold
Price potential
Near surface
gold reefs
Pre-developed,
multiple entry
points (flexibility)
Modern mining
methods – safe,
productive
Grade Engineering minimum dilution &
maximum recovery
(Dilution Rate, MCF
& PRF)
Pre-concentration
(DMS, XRT)
High recovered
grades with fitfor-purpose
metallurgical
solutions
Economies of scale
and synergies
Access to trained
labour force
Business approach to
mining – Management
team with solid track
record
$1,000
$750
$500
$250
AISC
GOLD PRICE (US$)
$1,750
MARGIN
$2,000
Low All-in-Sustaining
Cost of US$900 / oz
$0
Note: PFS numbers refering to ASX Released dated 13 April 2021 – “Pre-feasibility Study for Initial Underground Project”
Note: 15% contingency was applied to all operating costs and a 20% contingency to all capital costs.
12
LOW-COST SUSTAINABLE GOLD PRODUCER WITH HIGH MARGINS
TGME Gold Project
(~A$1210)
AISC Curve Public Reported by Australian/New Zealand producing Mines | June Q 2021
Source: PCF Australia Producing Mines public reported. - No responsibility for omission or mistakes.
13
LOW-COST SUSTAINABLE GOLD PRODUCER WITH HIGH MARGINS
$900
14
PHASE 1 UG PFS FINANCIAL RESULTS
•
YEAR 7-8 CAPACITY NOT UTILIZED (EXCLUSION OF INFERRED RESOURCES)
•
WITH THE PLANT CAPACITY FULLY UTILIZED BEYOND YEAR 6, AISC CAN BE MAINTAINED AT US$800/OZ
UG Operations
Unit
NPV @ 5%
Forecast
1,500
1,700
1,600
1,800
2,000
USDm
91
81
98
115
132
166
Internal Rate of Return (IRR)
%
82%
75%
88%
100%
111%
134%
Total Oz in Mine Plan
oz
418,845
418,845
418,845
418,845
418,845
418,845
Total Oz Recovered
oz
353,012
353,012
353,012
353,012
353,012
353,012
Average Payback Period (from Start of Mining)
Months
22
23
21
18
17
16
Peak Funding Requirement
USDm
36
36
36
36
36
36
EBITDA over LOM (Undiscounted)
USDm
241
222
254
286
318
382
All-in Sustaining Costs (AISC)
USD/oz
905
900
909
917
926
942
Gold Price
USD/oz
1,570
1,500
1,600
1,700
1,800
2,000
Exchange Rate
ZAR/USD
15.89
15.89
15.89
15.89
15.89
15.89
70,000
7.00
60,000
6.00
50,000
5.00
40,000
4.00
30,000
3.00
20,000
2.00
10,000
1.00
-
0
0
1
2
3
4
5
6
7
8
9
1,600
1,400
1,200
USD/oz
8.00
GRADE (G/T)
RECOVERED Oz
1,800
80,000
1,000
800
600
400
200
0
0
1
2
3
4
YEARS
Recovered Gold
Mill Head Grade
6
5
7
8
YEARS
Recovered Grade
Note: PFS numbers refering to ASX Released dated 13 April 2021 – “Pre-feasibility Study for Initial Underground Project”
Mining cost (Operating)
Plant Cost (Operating)
Other Costs(Operating)
Royalties (Operating)
Royalties (Operating)
Renewals and replacements (AISC)
Reclaimation (AISC)
Other Costs (AISC)
Realised Gold Price
15
CLOSING
HIGHLIGHTS
16
ENVIRONMENTAL, SOCIAL & GOVERNANCE (ESG)
ESG IS INTEGRAL TO THE DEVELOPMENT STRATEGY AND IS
BASED ON:
•
•
•
Holistic risk management
Zero harm approach to health and safety
Environmental stewardship
•
•
•
•
Conservation of biodiversity
Responsible production practices
Positive impact on host communities
Transparent stakeholder engagement and reporting
ENVIRONMENT
•
•
Creating regional
SOCIAL
•
26% of project ownership held by
Environmental
Development Trusts for
local labour force, host communities
and strategic black entrepreneur
alien invasive plants removals
Establish nature reserves and
targeted environmental study
programs
partners
Projects structured for broad based
•
GOVERNANCE
•
•
Ethical business practices
Culture of high ethical standards
throughout the organisation
economic participation
•
•
Alleviation of poverty
TGME will be the biggest employer
in the area
17
ENVIRONMENTAL
ENVIRONMENTAL, SCOPING
SCOPING REPORT
REPORT SUBMITTED,
SUBMITTED,
COMMUNITY SUPPORTS CONTINUES
The final scoping report for the environmental authorisation permitting
process for the 83 MR underground project was submitted to the Department
of Mineral Resources and Energy (DMRE) on 3 February 2022.
The final scoping report will now be assessed by the DMRE and once
approved the process will move to the Environmental Impact Assessment
(EIA) phase of the project.
A very successful Open Day was held in Pilgrims Rest on15 January 2022
with a good turnout of almost 70 people from the community and various
interested parties including stakeholders.
Community is very excited about the job
opportunities and economic upliftment that will be
created by the project.
Director General and delegates from the Department
of Forestry, Fisheries and Environment (“DFFE”)
completed a 2-days site visit in early March with the
aim to resolve the Nature Reserve matters raise
back in October 20211.
1Refer to ASX Release ”Project Permitting Update” dated 25 October 2021
18
HIGH
GRADE
NEW
ZONE DISCOVERED AT DESIRE MINE
RAMPING
UP TO
PRODUCTION
Beverly Hills sweeping grab samples – 15.79 g/t Au and 4.37g/t Au
(WGS84 UTM 271354E; 7255302 S)
Beverly Hills chip samples – 11.79g/t Au
Desire sweeping grab samples – 14.27g/t Au and 10.79g/t Au
(WGS84 UTM 276162E; 7240496 S)
RAMPING UP TO PRODUCTION
RESOURCE UPDATE
FUNDING
• High grade Rietfontein Mine PFS completed
and added as fourth mine into DFS.
• Further metallurgical test work on Sulphide
ore from Frankfort Mine and free milling ore
from Beta, CDM and Rietfontein mines.
• All inputs to DFS finalized (Trial mining,
engineering designs, etc.).
• Various UG sampling programs continue for
resource extension.
• Old Plant demolished in preparation for plant
construction.
Q2
2022
Project Financing
discussions ongoing.
Expected post DFS
completion (Q2 2022)
•
•
•
•
Mining preparation continues at First
phase Mines
Construction of underground dams
and water handling systems
Removal of old Mine infrastructure
DMS footprint preparations starts
PERMITTING
Q1
2022
• DFS completed, incorporating Frankfort,
Beta, CDM and Rietfontein mines.
• Detailed engineering designs.
• UG sampling and resource extension
programs continue.
Q3
2022
•
•
•
Q4
2022
• First phase process plant
construction starts
• Stoping starts at Beta and
Frankfort Mines
• Tailings dam re deposition
construction starts
• Development starts at Frankfort and
Beta Mines
Q1
2023
Permitting activities focused
on following the set
government timelines and
includes extensive
stakeholder
participation.(subject to
certain regulatory /
environmental approvals
being granted)
Scoping report submitted Q1
2022.
Final EIA submission in Q4
2022.
APPENDICES
21
COMBINED MINERAL RESOURCE STATEMENT - (~6.1MOZ)
Combined Mineral Resource
Resource Classification
Type of Operation
Underground
Tonnage
Gold Grade
Mt
g/t
Gold Content
Kg
koz
0.091
5.37
489
15.7
0.091
5.37
489
15.7
Underground
4.774
6.21
29 661
953.7
Open Pit
8.109
2.14
17 364
558.2
Tailings
5.244
0.83
4 373
140.6
18.128
2.84
51 398
1652.5
Underground
21.452
5.22
111 880
3597.0
Open pit
4.907
5.11
25 057
805.6
Tailings
0.023
0.57
13
0.4
Rock Dump
0.885
1.20
1 059
34.0
Total Inferred
27.267
5.06
138 009
4 437.0
Grand Total
45.485
4.17
189 896
6 105.2
Measured
Open pit
Tailings
Total Measured
Indicated
Total Indicated
Inferred
Notes:
1.
UG Mineral Resources are reported at a cut-off of 160 cm.g/t, open pit at 0.5 g/t and 0.35 g/t, tailings and rock dumps at 0.35 g/t.
2.
Fault losses of 5% for Measured and Indicated, 10% for Inferred Mineral Resources.
3.
Gold price used for the cut-off calculations is USD1,500/oz.
4.
Mineral Resources are stated as inclusive of Ore Reserves.
5.
Mineral Resources are reported as total Mineral Resources and are not attributed.
22
MINERAL RESOURCE STATEMENT - UNDERGROUND (~4.5MOZ)
Mineral Resource
Classification
Mine
Reef
Reef Grade
Stope Grade
Reef Width
Stope width
Content
Reef Tonnes
Stope Tonnes
g/t
g/t
cm
cm
cm.g/t
Mt
Mt
Au Content
7.13
5.37
73
103
520
0.069
0.091
489
koz
15.7
7.13
5.37
73
103
520
0.069
0.091
489
15.7
7.86
13.19
21.66
14.57
13.90
16.97
5.13
3.80
6.58
8.20
6.34
4.62
58
23
23
52
36
25
96
90
90
92
90
90
452
307
499
755
499
416
0.243
0.258
0.716
0.517
0.064
0.026
0.373
0.895
2.357
0.919
0.140
0.091
1,912
3,401
15,506
7,534
887
422
61.5
109.4
498.5
242.2
28.5
13.6
Total Indicated
16.26
6.21
36
91
591
1.824
4.774
29,661
953.7
Total Measured & Indicated
15.93
6.20
38
91
600
1.893
4.865
30,150
969.4
Measured
Frankfort
Bevetts
Total Measured
Indicated
Mineral Resource
Classification
Inferred
Frankfort
CDM
Beta
Rietfontein
Vaalhoek
Olifantsgeraamte
UG Mine
Frankfort
CDM
Beta
Rietfontein
Olifantsgeraamte
Vaalhoek
Vaalhoek
Glynns Lydenburg
Ponieskrantz*
Frankfort Theta*
Nestor*
Bevetts
Rho
Beta
Rietfontein
Vaalhoek
Olifantsgeraamte
Reef
Bevetts
Rho
Beta
Rietfontein
Olifantsgeraamte
Vaalhoek
Thelma Leaders
Glynns
Portuguese
Theta
Sandstone
Total Inferred
kg
Reef Grade
Stope Grade
Reef Width
Stope width
Content
Reef Tonnes
Stope Tonnes
g/t
g/t
cm
cm
cm.g/t
Mt
Mt
Au Content
7.41
10.06
16.51
14.06
18.33
16.28
12.18
15.87
13.26
7.22
5.54
4.27
3.02
5.43
8.52
4.68
4.77
9.47
5.19
3.99
3.24
2.92
48
24
25
57
23
22
96
25
22
34
41
93
90
90
94
90
90
123
90
90
90
90
356
244
414
803
422
361
1166
397
287
244
225
0.343
0.544
1.107
1.190
0.059
0.873
0.023
3.218
0.064
0.099
0.101
0.596
1.811
3.367
1.962
0.248
2.980
0.030
9.833
0.213
0.220
0.193
kg
2,543
5,472
18,285
16,721
1,162
14,209
284
51,078
849
714
562
14.68
5.22
31
91
458
7.622
21.452
111,880
koz
3,597 597.0
81.8
175.9
587.9
537.6
37.3
456.8
9.1
1 642.2
27.3
23.0
18.1
Notes:
1. Mineral Resource cut-off of 160 cm.g/t applied.
2. Fault losses of 5% for Measured and Indicated, 10% for Inferred Mineral Resources.
3. Gold price used for the cut-off calculations is USD1,500/oz.
4. cm.g/t and g/t figures will not back calculate due to variable densities in reef and waste rock.
5. Mineral Resources are stated as inclusive of Ore Reserves.
6. Mineral Resources are reported as total Mineral Resources and are not attributed.
23
MINERAL RESOURCE STATEMENT – OPEN PIT (~1.4MOZ)
Mineral Resource Classification
Indicated
Open Pit Mine
Hermansburg
DG1
DG2
Vaalhoek
Theta & Browns Hill
Theta & Browns Hill
Theta & Browns Hill
Theta & Browns Hill
Theta & Browns Hill
Iota
Iota
Iota
Iota
Reef
Reef Grade
Reef Width
Content
Reef Tonnes
g/t
cm
cm.g/t
Mt
Eluvial
Eluvial
Eluvial
Vaalhoek
Shale
Bevett's
Upper Theta
Lower Theta
Beta
Bevett's
Upper Rho
Lower Rho
Upper Theta
Open Pit Mine
Hermansburg
DG1
DG2
Inferred
Reef
kg
koz
1.79
2.24
0.66
17.25
1.02
1.08
2.41
3.79
2.51
2.98
2.33
2.51
1.06
0
0
0
33
200
223
100
100
100
114
402
520
114
0
0
0
574
204
241
241
379
251
340
937
1306
121
0.505
0.640
1.586
0.111
0.397
0.856
0.651
0.839
0.373
0.108
0.897
0.981
0.163
905
1 432
1 041
1920
404
925
1571
3178
938
323
2090
2464
173
29.1
46.0
33.5
61.7
13.0
29.7
50.5
102.2
30.1
10.4
67.2
79.2
5.6
2.14
168
360
8.109
17 364
558.2
Total Indicated
Mineral Resource Classification
Au Content
Reef Grade
Reef Width
Content
Reef Tonnes
g/t
cm
cm.g/t
Mt
Au Content
kg
koz
Vaalhoek
Vaalhoek
Theta & Browns Hill
Theta & Browns Hill
Theta & Browns Hill
Theta & Browns Hill
Theta & Browns Hill
Eluvial
Eluvial
Eluvial
Vaalhoek
Thelma Leaders
Shale
Bevett's
Upper Theta
Lower Theta
Beta
0.88
0.00
0.00
20.32
14.25
1.12
1.17
1.86
8.06
2.17
0
0
0
43
97
215
217
100
100
100
0
0
0
880
1 388
240
254
186
806
217
0.110
0.000
0.000
0.213
0.293
0.600
0.451
0.948
1.384
0.778
97
0
0
4 319
4 172
668
528
1762
11153
1686
3.1
0.0
0.0
138.9
134.1
21.5
17.0
56.6
358.6
54.2
Iota
Upper Rho
5.12
134
687
0.131
673
21.6
5.11
121
617
4.907
25 057
805.6
Total Inferred
Notes:
1. Mineral Resource cut-off of 0.5 g/t and 0.35 g/t applied.
2. Fault losses of 5% for Measured and Indicated, 10% for Inferred Mineral Resources.
3. Gold price used for the cut-off calculations is USD1,500/oz.
4. Vaalhoek, Theta Hill, Browns Hill and Iota Mineral Resources stated utilising pit optimisation.
5. Mineral Resources are stated as inclusive of Ore Reserves.
6. Mineral Resources are reported as total Mineral Resources and are not attributed.
24
ORE RESERVE STATEMENT
Ore Reserve Classification
Proved
Total Proved
Probable
Grade
Tonnes
g/t
kt
kg
koz
4,24
60
254
8,16
4,24
60
254
8,16
Beta
6,51
1 662
10 822
347,94
Frankfort
4,11
259
1 063
34,16
CDM
2,31
385
889
28,58
Theta Project (MR 83)
2,31
2 164
4 996
160,61
3,98
4 470
17 770
571,29
Operation
Frankfort
Total Probable
Au Content
Notes:
Underground Operations
1. An Ore Reserve cut-off of 170 cm.g/t has been applied for the Beta Mine.
2. An Ore Reserve cut-off of 150 cm.g/t has been applied for the Frankfort Mine.
3. An Ore Reserve cut-off of 121 cm.g/t has been applied for the CDM Mine.
4. A gold price of USD 1,465 / oz and exchange rate of 16 ZAR / USD was used for the cut- off calculation.
5. Ore Reserves are reported as total Ore Reserves and are not attributed.
Theta Project (Open Pit MR 83)
1. An Ore Reserve cut – off of 0.4 g/t was applied.
2. A gold price of USD 1,300 / oz was used for the cut - off calculation.
25
QUESTION TIME
WWW.THETAGOLDMINES.COM
TICKER: TGM (TRADE IN AU$)
TICKER: TGMGF (TRADE IN US$)
BILL GUY
MITFORD MUNDELL
CHAIRMAN
CEO
Email: billg@thetagoldmines.com
Email: mitfordm@tgme.co.za
Share your feedback
Discover