Half-Year Accounts at 31 December 2022
Released
Released
Announcement PDF
Half Year Financial Report
Six Months Ended 31 December 2022
Half-Year Financial Report - 31 December 2022
Theta Gold Mines Limited
Corporate Directory
DIRECTORS
Bill Guy
Richie Yang
Simon Liu
Brett Tang
Byron Dumpleton
Executive Chairman
Non-Executive Director
Non-Executive Director
Non-Executive Director
Non-Executive Director
COMPANY SECRETARY
Brent Hofman
AUDITOR
Ernst & Young
200 George Street
Sydney NSW 2000
Australia
STOCK EXCHANGE LISTINGS
ASX: TGM
OTCQB: TGMGF
AUSTRALIAN BUSINESS NUMBER
30 131 758 177
REGISTERED OFFICE
Suite 80 Level 35
International Tower One
100 Barangaroo Avenue
Sydney NSW 2000
Australia
Tel: +61 2 8046 7584
Email: info@thetagoldmines.com
SHARE REGISTRY
Boardroom Pty Limited
Grosvenor Place
Level 12, 225 George Street
Sydney NSW 2000
Australia
Tel: 1300 737 760 (within Australia)
+61 2 9290 9600 (outside Australia)
Fax: +61 2 9290 9655
WEBSITE
www.thetagoldmines.com
Half-Year Financial Report - 31 December 2022
2
Theta Gold Mines Limited
Directors’ Report
Your Directors present their report, together with the financial statements of Theta Gold Mines Limited
and its controlled entities (“Consolidated Entity”) for the half year ended 31 December 2022.
DIRECTORS
The names of the Directors of Theta Gold Mines Limited during the half year and up to the date of this
report are:
Charles William (Bill) Guy
Bill Richie Yang
Yang (Simon) Liu
Guyang (Brett) Tang
Finn Stuart Behnken
Byron Dumpleton
Executive Chairman
Non-Executive Director (Audit Committee Chair)
Non-Executive Director
Non-Executive Director
Non-Executive Director (ceased 15 August 2022)
Non-Executive Director
REVIEW OF OPERATIONS
Executive Management Changes
During the half year, the Company appointed Mr Bill Richie Yang as Audit Committee Chair after Mr Finn
Stuart Behnken position as a non-executive director on the board ceased in August 2022. Mr Yang is
Director of Corporate and Business Development and has been with the Company since June 2015.
Completion of Definitive Feasibility Study
Definitive Feasibility Study (TGME Underground Gold Mine Project)
The Company’s Feasibility Study (FS)1 for the TGME Project was delivered on 27 July 2022, confirming
Theta Gold’s potential to be a significant near-term, high-margin, low-cost gold producer with
opportunities for future growth. Based on the FS results, the Project will provide robust financial returns
from a long-life large underground mining operation for a modest capital investment given the scale of
operations envisaged.
The Project Life of Mine ‘LOM’ will initially comprise a 12.9-year mining operation starting in Q2, 2023
and delivering LOM production of 1.24 Moz of contained gold. The estimated peak development Capital
Expenditure (“Capex”) is US$77 million, (A$103 million), with the Project forecast to generate a pre-tax
NPV10% of US$324 million, (A$432 million) and pre-tax internal Rate of Return (IRR) of 65% at a forecast
average gold price of US$1,642, (A$2,189) per ounce. Based on these metrics, the Project has a projected
capital payback period of 31 months.
1 Refer to ASX Release dated 27 July 2022 titled “Theta’s TGME Project Definitive FS Confirms NPV(10%) of A$432 Million at US$1,642 / Oz Gold
Price”
3
Theta Gold Mines Limited
The FS paves the way for a Final Investment Decision (‘FID’) by the Theta Gold Board in respect to
funding negotiations and on-going discussions with financiers with respect to full/partial debt and equity
funding options. Theta Gold has appointed a debt funding advisor to manage this important process and
will provide updates in due course.
Feasibility Highlights:
•
TGME Feasibility Study2 delivers 1.24Moz contained gold production, underpinning an initial 12.9-year
mine life.
•
Strong financial return based on LOM plan (at average gold price of US$1,642, (A$2,189) /oz) with first
production targeted for Q2, 20243 including:
o
Undiscounted free cash flows of US$508m, (A$678m), pre-tax US$717m, (A$956m);
o
NPV (at a 10% discount rate) of US$219m, (A$292m), pre-tax US$324m, (A$432m);
o
Capital payback period of 31 months;
o
Pre-tax IRR of 65%; and
o
Peak production over 100,000 oz Gold.
•
All-in-sustaining Cost (AISC) of US$834/oz (A$1,112/oz) over LOM sits on the bottom quartile of South
Africa and Australian gold producers;
•
Peak Capital requirement is US$77m, (A$103m), total capital requirements US$174m, (A$232m);and
•
Front-End Engineering Design (FEED) of the TGME gold plant completed, forming an important input
towards the finalisation of the FS of the TGME underground project4.
Table 1: Key Project Metrics
Description
Units
Base Case
Reserve Plan
Project Start Date5
Qtr/Year-yyyy
Q2 2023
Q2 2023
Commercial Production Start Date
Qtr/Year-yyyy
Q2 2024
Q2 2024
Production build up period
Months
14
14
Life of mine
years
12.9
7.3
Underground ore mined (LOM)
Mt
6.46
2.85
Mined Grade
g/t
5.95
6.09
Gold Mined (LOM)
Moz
1.24
0.56
Production Rate
Kt/a
540
540
Production Rate
Kt/m
45
45
Grind size
µ
106
106
Gold recovered (average LOM)
%
87
87
Gold recovered (LOM)
Moz
1.08
0.49
2 Ref to ASX release dated 27 July 2022 titled “Theta’s TGME Project Definitive FS Confirms NPV10% of A$432 million at US$1,642/Oz Gold price”
3 First gold produced timing will be subject to securing funding and obtaining all necessary regulatory permitting approvals.
4 Refer to ASX release dated 20 June 2022 titled “TGME Gold Project Update”
5 Project start date will be dependent on the Company securing the necessary funding and permitting approvals.
4
Theta Gold Mines Limited
Project economics below shows the sensitivities to the various gold price estimates and demonstrates the
robust financial returns of the Project. The FS completed in July 2022 used an average gold price of US$1,642 /
Oz as a base case.
Table 2: Project Economics at Various Gold Prices – Base Case (USD)
Project Economics at gold price
NPV @ 10% (real) Pre-tax
NPV @ 10% (real) Post-tax
IRR (%) Pre-tax
IRR (%) Post-tax
AISC
EBITDA annual average
EBIT annual average
Free Cash Flow (Pre-tax)
Free Cash Flow (Post-tax)
Development Capital – Peak
Funding
Capital Sustaining
Payback post-tax
Capital Efficiency (Pre-Tax
NPV/Dev Capital
Capital Efficiency (Post-Tax
NPV/Dev Capital
Forecast
USD1,600/ USD1,800/ USD2,000/ USD2,200/
(USD1,642/ USD1,500/oz
oz
oz
oz
oz
oz Avg)
USDm
324
255
304
402
501
601
USDm
219
174
206
269
335
400
%
65%
57%
64%
77%
90%
102%
%
57%
50%
56%
67%
78%
87%
USD/oz
834
822
831
847
862
876
USDm
69
58
66
81
96
111
USDm
60
49
57
72
87
102
USDm
717
576
673
869
1066
1264
USDm
508
412
478
611
747
881
Unit
USDm
77
77
77
77
77
77
USDm
Months
37
31
37
33
37
31
37
28
37
25
37
24
%
422%
332%
395%
524%
653%
783%
%
285%
226%
268%
351%
437%
521%
Table 3: Project Economics at Various Gold Prices – Base Case (AUD)
Project Economics at gold price
NPV @ 10% (real) Pre-tax
NPV @ 10% (real) Post-tax
IRR (%) Pre-tax
IRR (%) Post-tax
AISC
EBITDA annual average
EBIT annual average
Free Cash Flow (Pre-tax)
Free Cash Flow (Post-tax)
Development Capital – Peak
Funding
Capital Sustaining
Payback post-tax
Capital Efficiency (Pre-Tax
NPV/Dev Capital
Capital Efficiency (Post-Tax
NPV/Dev Capital
NOTES:
1.
2.
Forecast
USD1,600/ USD1,800/ USD2,000/ USD2,200/
(USD1,642/ USD1,500/oz
oz
oz
oz
oz
oz Avg)
AUDm
432
339
405
536
669
802
AUDm
292
232
274
359
447
533
%
65%
57%
64%
77%
90%
102%
%
57%
50%
56%
67%
78%
87%
AUD/oz
1,112
1,096
1,107
1,129
1,149
1,167
AUDm
92
77
87
107
128
148
AUDm
80
66
76
96
116
136
AUDm
956
768
897
1,158
1,421
1,686
AUDm
678
550
638
814
996
1,175
Unit
AUDm
102
102
102
102
102
102
AUDm
Months
49
31
49
33
49
31
49
28
49
25
49
24
%
422%
332%
395%
524%
653%
783%
%
285%
226%
268%
351%
437%
521%
Converted to AUD from USD using AUD:USD exchange rate of 1.333 used in the FS.
Due to rounding, numbers presented throughout this document may not add up precisely to the totals, provided and percentages may
not precisely reflect the absolute figures.
5
Theta Gold Mines Limited
Figure 1: Annual Gold Production – Base Case
Figure 2: Annual and Cumulative Cash Flow (Post-Tax) – Base Case (AUD)
NOTES:1. Forecast Prices averaging USD1,642/oz over LOM.
2. Converted to AUD from USD at exchange rate of 1.333 AUD:USD.
Historical Project Summary
The TGME Project targets to restart historical underground gold mines located in a historically prolific gold mining
region in the Mpumalanga Province of South Africa. The Project Areas are centred in the town of Pilgrims Rest,
some 370 km due northeast of Johannesburg, and vast majority of the tenements were under TGME’s ownership
since the late 1800s.
6
Theta Gold Mines Limited
The Project targets the Beta (including the Beta North, Beta Central and Beta South sections), Rietfontein,
Frankfort and Clewer-Dukes Hill-Morgenzon (“CDM”) mines. A significant amount of gold resources remain
underground which were not mined historically due to technological limitations or limiting ore characteristics.
Beta is scheduled as the first operation to commence production, followed by Rietfontein, and finally CDM and
Frankfort simultaneously. In comparison to CDM and Frankfort, Beta and Rietfontein are higher-grade mines.
A gold plant, which acts as the central processing plant for all the historical operations, is situated in close
proximity with a maximum distance to operations of approximately 40km. A new facility will be established on
this footprint to treat all the ore from the surrounding operations.
Two scheduling strategies have been investigated in the FS. The Base Case considers a LOM plan targeting the
total Mineral Resources (Measured, Indicated and Inferred). The Ore Reserve Case considers a LOM plan
targeting only Measured and Indicated Mineral Resources.
This FS demonstrates the ability to achieve optimised cash flows by scheduling production from the operations.
The mine designs and associated costs per operational element feed into a combined operations financial model.
The Ore Reserve Case supports the declaration of compliant JORC Code 2012 Ore Reserves.
TGME Underground Gold Mine Development
As part of the preparation for the installation of the first phase new gold plant, TGME had appointed the services
of Jet Demolition to remove the redundant plant equipment. The process started in the second week of January
2022. Specialised equipment were utilised for demolition, after which it was reduced in size and made ready for
transport to scrap merchants. The project to remove the old plant is now complete6.
Processing consultants Met63 was contracted to do a detailed design and costing of a processing plant designed
for a feed capacity of 45,000 tons per month which is equivalent to 67 tons per hour at 92% availability. A flow
schematic is shown in Figure 3.
Figure 3: Process Flow Schematic Phase 1
6 Ref to ASX release dated 4 March 2022 titled “DFS Update and High-Grade Ore Sweeped from New Historical Mines”.
7
Theta Gold Mines Limited
The FS has been split into three phases, allowing for various processing scenarios aligned with the mining
development program. The design of each phase is based on a stand-alone processing facility aligned with the
mining plan of the ore body.
•
Phase 1 – Carbon-in-Leach (CIL) Plant (Free-milling ore is process for the first 7 Years, see figure 6).
The design and costing of a 45,000 tons per month oxide ore processing plant including crushing, milling,
CIL and elution with gold Doré produced on site. Testwork undertaken on various “free-milling” ores has
indicated high undissolved gold losses, indicating the presence of small amounts of sulphidic
constituents. This was particularly evident when completing standard cyanidation bottle roll trials on the
CDM mine samples. Subsequent additional testwork supports this. As a result, the Phase 1 circuit will
include a flash flotation stage post-milling to remove sulphide associated materials before conventional
cyanidation. This flotation mass pull will join the concentrator (production scheduled in Phase 2).
•
Phase 2 – Gold Concentrator Plant
The design and cost of a 20,000 tons per month concentrating plant including crushing, milling, Density
Media separation (DMS) and flotation. The final products consist of a combined carbon and sulphide
flotation concentrate. The carbon flotation concentrate being processed through the CIL plant #3 and
the sulphide flotation concentrate is processed through the CIL plant #1.
•
Phase 3 – Oxidative Leaching of Sulphide Concentrate
The Phase 3 plant includes a 45,000 tons per month Leach-ox processing plant that was designed and
costed, including crushing, milling and carbon/sulphide flotation. The phase 3 plant consists of both the
gold concentrator plant as well as the CIL plant as described in Phase 1 and Phase 2. The carbon flotation
concentrate processed in a dedicated CIL circuit (CIL plant #3), sulphide flotation concentrate oxidized
under atmospheric conditions with liquid oxygen injection and high shear reactors. Oxidised product to
be treated in a separate batch CIL process (CIL #1) with the tails treated in a larger CIL (CIL plant #2), that
also processes the flotation tails as well as “free-milling” ore feed. This option allows for all recovered
gold to be produced as Doré on-site with no concentrate produced.
Although there are some shared infrastructure and processing equipment between the phases, for the purposes
of this FS the phase-one plant will be constructed first to treat Beta, Rietfontein and CDM ore with phase-three
being constructed at a later stage before mining of Frankfort ore commences.
The plant will be developed by an Engineering, Procurement and Construction (EPC) contractor. The Company
will run a tender process to evaluate contracts for the construction and upgrade of existing infrastructure
including detailed engineering for the plant, procurement, fabrication and delivery to site of plant, equipment
and materials and construction of the process plant facilities.
Project Finance
Theta Gold signed a non-binding Term Sheet with Sprott Resource Streaming and Royalty Corporation (“Sprott”)
under which Sprott is to advance US$70 million (~A$110 million) cash in return for a gold stream on Theta’s
TGME Gold Project (the “Project”). A debt funding advisor was engaged to assist in negotiations for the required
Capex requirements of the A$103 million peak capital. The Company is expected to complete negotiations with
debt financing within 2023 calendar year.
The Company is also in negotiation with other investment parties with respect to the equity portion of the
funding requirements and is expected to complete those discussions and secure terms in the third quarter of
2023.
8
Theta Gold Mines Limited
Project Permits and Approvals
The Company announced in July 20227 that the final Environmental Impact Assessment Report and
Environmental Management Programme (EIA/EMPr) have been submitted to the Department of Mineral
Resources and Energy (DMRE) and the final technical documents for the integrated water use license (WUL)
application to the Department of Water and Sanitation (DWS) for final decision.
The outcome of the decisions from the DMRE and DWS on the applications are expected in Q1 of 2023 with an
additional 90-day review and objection period for the public. A positive decision from the competent authorities
will enable the Company to commence with its MR83 underground project.
Over 20 studies have been completed as part of the EIA process. The findings from the EIA/EMPr and specialist
studies have not identified any fatal flaw, unaddressed objection, or significantly high impact ratings. The
requisite mitigation measures are all imminently feasible and this should give all interested and affected parties
the confidence that the impacts of our proposed activities will not threaten the environment.
A comprehensive stakeholder engagement process was undertaken before the submission of the applications. A
very successful open day was held in Pilgrims Rest on 28 May 2022. Feedbacks from the open day was very
positive and the community is very excited about the job opportunities and economic upliftment that will be
created by the project. With the good turnout at the open day and various other stakeholder meetings it can be
concluded that the procedural requirement to consult during the EIA phase is satisfied.
It has been advised that the Department of Forestry, Fisheries and the Environment (“DFFE”) is currently
conducting interdepartmental consultations on the Company’s request for Ministerial conditions for continued
mining in certain sections of Morgenzon Forest Nature Reserve (“FNR”) that was declared in October 2021.
The Company is confident that it can successfully implement its mining operations to better protect the strategic
water source and biodiversity area. It is of great concern to the local community and downstream farmers that
environmental degradation is accelerating in this catchment area. A positive response on the request to the
Minister will therefore be welcomed by stakeholders in the light of current challenges in the catchment, the
manageable environmental impacts from the proposed MR83 underground project, and the significant value
offering of the proposed Ecological Compensation Programme to support DFFE’s wider Environmental, Social
and Governance (“ESG”) objectives in the region.
Gold Plant Front-End Engineering Design (Feed) Complete
Front-End Engineering Design (FEED) of the TGME gold plant has been completed, forming an important input
towards the finalisation of the TGME Project.
Theta Gold provides an update on the MR83 gold processing plant advising that it had appointed MET63, which
specialises in the design and construction of advanced modular processing plants, to undertake and complete
the plant design, based on a thorough metallurgical testwork program, and with multi-tier internal and
independent oversight.
Key Features of the Gold Process Plant:
•
•
The new gold processing plant is designed to have a milling capacity of 540,000 tons per annum. The
plant design consists of two individual processing streams, capable of processing free-milling and
sulphide ore separately.
The new gold processing plant is designed to fit into the current plant footprint which forms part of
MR83, therefore no additional environmental permitting will be required.
7 Ref to ASX release dated 18 July 2022 titled “Permitting Update TGME Underground Gold Mine”
9
Theta Gold Mines Limited
•
•
•
•
•
•
•
•
The new processing plant components include three-stage crushing, milling, reagent, flotation, CIL,
elution, and gold room sections as indicated in Figure 2 & 3.
The gold plant will produce dore gold bars.
Engineering and costing have been completed to the required level of accuracy for the FS.
The completed design includes water and power reticulation with the scope to increase the capacity
with modular units for future plant expansions, consistent with the Company’s strategy to reach its gold
production target of 160,000 ounces per annum within five years.
The latest proven available automation technologies were incorporated into the gold processing plant
design which will reduce labour requirements and enhance productivity levels.
The tailings disposal will be moved onto the existing tailings storage facility located some 150 metres
from the plant.
Some existing plant infrastructures were incorporated into the new gold processing plant.
A 3D rendering of the processing plant is illustrated in Figure 4.
Figure 4: 3D Plant Rendering Final design Phase 1-3.
10
Theta Gold Mines Limited
Figure 5: New TGME Plant Layout
Figure 6: Existing Plant Drone View (post demolition of old sections)
11
Theta Gold Mines Limited
FINANCIAL RESULTS
The consolidated loss after income tax for the six months ended 31 December 2022 was US$3,035,000
(31 December 2021: US$3,373,000). The loss largely represents the consolidated entity’s operating costs
for the half year, including exploration expenditure, trial mining operations, finance costs, fair value
adjustment to its investments, general administration and corporate costs as well has non-cash sharebased payment expense.
FINANCIAL POSITION, FUNDING AND CASH BALANCE
Sprott Royalty and Streaming Funding Term Sheet
Theta Gold Mines announced on 19 October 2022 it has entered into a non-binding Streaming Term
Sheet (“Term Sheet”) with Sprott Resource Streaming and Royalty Corporation (“Sprott”) under which
Sprott is to advance US$70 million (~A$110 million) cash in return for a gold stream on Theta’s TGME
Gold Project (the “Project”).
The Project is expected to deliver to Sprott up to 100,000 ounces of gold over its Life-of-Mine (“LOM”),
for which Sprott will pay 10% of the gold price per ounce delivered under the stream. Theta has the
option to buy-back 50% of the stream based on a pre-agreed price, following which Theta will deliver 2%
of the ongoing gold production.
Prior to initial gold delivery, Theta will pay in cash or scrip (at 10% discount to 5 days volume-weightedaverage-price (“VWAP”)) on a semi-annual basis, 9.5% per annum interest to Sprott for the funds
advanced.
Under the Term Sheet, conditions precedent to closing include the completion of technical, legal, and
environmental and social due diligence, the receipt and review of the project’s final development budget
and schedule, the completion of definitive documentation, and the receipt of applicable environmental
permits, operating licences and regulatory approvals.
Closing is scheduled by the second quarter of 2023 and the funds will be applied towards the construction
of the TGME Gold Project, located in the Eastern Transvaal Goldfields in the Mpumalanga Province, South
Africa.
A due diligence team appointed by Sprott already began working since November 2021, upon a
satisfactory conclusion, a Binding Gold Stream Agreement between Sprott and Theta Gold shall be
finalised, executed and announced to the market in detail.
12
Theta Gold Mines Limited
Placements and Share Purchase Plan
During the half-year ended 31 December 2022, the Company completed two Private Placements
(Placement) along with a Share Purchase Plan (SPP) raising a total of US$3.2 million (A$4.6 million) before
costs as follows:
On 3 August 2022, the Company announced it had raised A$2.3 million (before fees) through a placement
from numerous existing shareholders, new institutional, professional and sophisticated investors. The
Company issued 36,584,615 new fully paid TGM Ordinary Shares at the issue price of A$0.0658 per share,
using the Company’s existing placement capacity pursuant to Listing Rule 7.1.
On 27 October 2022, TGM announced it had completed a capital raise of A$1.7 million (before costs)
through a placement from a majority of existing institutional, professional and sophisticated investors.
The Company issued 24,025,716 new TGM Ordinary Shares at the issue price of A$0.07 cents per share,
using the Company’s existing placement capacity pursuant to Listing Rule 7.1.
Following the successful completion of the Private Placement, the Company announced it would allow
existing Shareholders the opportunity to participant on the same terms as the Placement via a Share
Purchase Plan (SPP) which raised $572,000 and issued 8,171,405 new TGM Ordinary Shares at A$0.07 as
announced to ASX on 6 December 20229.
Cash Balance
As at 31 December 2022, the Consolidated Group held US$573,000 in cash or cash equivalents.
OTC MARKETS LISTING
The Company’s shares are dual listed on the OTCQB market in the United States under the code TGMGF.
The Company's primary listing is on the Australian Securities Exchange.
The Company’s application for DTC eligibility with the Depository Trust and Clearing Corporation (DTC),
part of the US Federal Reserve System, was approved during the half year.
DTC eligibility facilitates electronic trading of securities by individual investors that use self-managed online
broking accounts (such as TD Ameritrade and E-Trade), as opposed to restricted trading through market
makers. It will enable electronic clearing and settlement of the shares traded on OTCQB, which will provide
easier access for North American investors to invest in the Company.
8
Shares issue price of $0.065 cents is 6.73% discount to the 15 day VWAP calculated days prior to the release of this capital raise.
9
ASX release dated 6 December 2022 titled “Share Purchase Plan Completion Notice”
13
Theta Gold Mines Limited
OUTLOOK
The Company remains focused on pursuing the development and commencement of mining operations
in the Eastern Transvaal Goldfields, (TGME Gold Project). The Company has considerable optionality
across its vast asset base. It will continue to assess the potential underground development of its TGME
Gold Mine Project which it plans to bring into production in the fourth quarter of 2024.
AUDITOR'S INDEPENDENCE DECLARATION
The auditor's independence declaration under s 307C of the Corporations Act 2001 is set out on
page 15.
ROUNDING OF AMOUNTS TO NEAREST THOUSAND DOLLARS
The Company is of a kind referred to in ASIC Corporations Instrument 2016/191 (Rounding in
Financial/Directors’ Reports) and in accordance with that Instrument, amounts in the Directors’ Report
and the Financial Report have been rounded to the nearest thousand dollars, unless otherwise stated.
Signed in accordance with a resolution of the directors.
On behalf of the Board
Charles William Guy
Chairman
Sydney, 15 March 2023
14
Ernst & Young
200 George Street
Sydney NSW 2000 Australia
GPO Box 2646 Sydney NSW 2001
Tel: +61 2 9248 5555
Fax: +61 2 9248 5959
ey.com/au
Auditor’s independence declaration to the directors of Theta Gold Mines
Limited
As lead auditor for the review of the half-year financial report of Theta Gold Mines Limited for the halfyear ended 31 December 2022, I declare to the best of my knowledge and belief, there have been:
a. No contraventions of the auditor independence requirements of the Corporations Act 2001 in
relation to the review;
b. No contraventions of any applicable code of professional conduct in relation to the review; and
c. No non-audit services provided that contravene any applicable code of professional conduct in
relation to the review.
This declaration is in respect of Theta Gold Mines Limited and the entities it controlled during the financial
period.
Ernst & Young
Scott Nichols
Partner
Sydney
15 March 2023
A member firm of Ernst & Young Global Limited
Liability limited by a scheme approved under Professional Standards Legislation
15
Theta Gold Mines Limited
Directors’ Declaration
The directors declare that:
1.
2.
the financial statements and notes, as set out on pages 17 to 30, are in accordance with the
Corporations Act 2001 and:
a.
comply with Accounting Standard AASB 134: Interim Financial Reporting; and
b.
give a true and fair view of the financial position of the Consolidated Entity as at 31
December 2022 and of its performance for the half year ended on that date;
in the directors' opinion there are reasonable grounds to believe that the Company will be able to
pay its debts as and when they become due and payable.
Signed in accordance with a resolution of the directors.
On behalf of the Board
Charles William Guy
Chairman
Sydney, 15 March 2023
16
Theta Gold Mines Limited
Condensed Consolidated Statement of Financial Performance
and Other Comprehensive Income
for the Half Year ended 31 December 2022
Six months
ended
31 December
2022
US$’000
Six months
ended
31 December
2021
US$’000
Loss before income tax expense
Income tax expense
44
11
(1,050)
(283)
(38)
(402)
(888)
(429)
(3,035)
-
56
28
(985)
(115)
(113)
(579)
(1,665)
(3,373)
-
Loss for the period
(3,035)
(3,373)
Items that may be reclassified subsequently to profit
or loss:
Exchange difference on translating foreign controlled
entities
(589)
(1,681)
Unrealised gain / (loss) on financial assets
608
219
(3,016)
(4,835)
(3,035)
(3,035)
(3,373)
(3,373)
(3,016)
(3,016)
(4,835)
(4,835)
(0.6)
(0.6)
(0.7)
(0.7)
Notes
Interest income
Other income
Finance costs
Salary expense
Share-based payments
Exploration expenses
Operating expenses
Fair value gain / loss on investment
7
Other comprehensive income, net of tax
Total comprehensive loss for the period, net of
income tax
Loss attributable to:
Equity holders of the parent
Total comprehensive loss attributable to:
Equity holders of the parent
Loss per share
Basic (cents per share)
Diluted (cents per share)
The accompanying notes form part of these financial statements.
17
Theta Gold Mines Limited
Condensed Consolidated Statement of Financial Position
as at 31 December 2022
31 December
2022
US$’000
30 June
2022
US$’000
CURRENT ASSETS
Cash and cash equivalents
Trade and other receivables
TOTAL CURRENT ASSETS
573
196
769
22
149
171
NON-CURRENT ASSETS
Receivables
Other receivable
Property, plant and equipment
Exploration expenditure
Other financial assets
TOTAL NON-CURRENT ASSETS
TOTAL ASSETS
38
1,408
631
15,828
1,309
19,214
19,983
39
1,427
695
16,193
1,328
19,682
19,853
1,312
157
8,061
9,530
1,087
682
7,749
9,518
1,719
3,941
5,660
15,190
4,793
1,701
3,817
5,518
15,036
4,817
95,845
6,604
(97,656)
4,793
92,891
6,546
(94,620)
4,817
Notes
ASSETS
LIABILITIES
CURRENT LIABILITIES
Trade and other payables
Provisions
Borrowings
TOTAL CURRENT LIABILITIES
NON- CURRENT LIABILITIES
Provisions
Borrowings
TOTAL NON- CURRENT LIABILITIES
TOTAL LIABILITIES
NET ASSETS
EQUITY
Issued capital
Reserves
Accumulated losses
TOTAL EQUITY
3
7
4
4
5
The accompanying notes form part of these financial statements
18
Theta Gold Mines Limited
Condensed Consolidated Statement of Changes in Equity
for the Half Year ended 31 December 2022
Option
Premium
reserve
US$’000
Sharebased
Payment
Reserve
US$’000
Foreign
Currency
Translation Accu