TGM Investor Presentation - Australian Gold Conference
Released
Released
Announcement PDF
Theta Gold Mines Limited ACN 131 758 177
Registered Office: Level 35, One International Towers, 100 Barangaroo Avenue
Sydney, NSW 2000, Australia
14 October 2026
ASX ANNOUNCEMENT AND MEDIA RELEASE
(ASX: TGM)
Australian Gold Conference – Investor Presentation
Theta Gold Mines Limited (ASX: TGM) (Theta or the Company) is pleased to advise that Executive
Director, Richie Yang will be presenting at the Australian Gold Conference to be held in Sydney from
October 14 – 15, 2026.
The event is one of Australia’s largest dedicated gold and precious metals investment events showcasing
mining companies, retail and institutional investors, fund managers and industry experts.
An updated Investor Presentation is attached and released with this announcement.
[ENDS]
This announcement was approved for release by Theta Gold Mines Limited’s Chairman.
For more information, please visit www.thetagoldmines.com contact key management:
Bill Guy, Chairman E: billg@thetagoldmines.com
Richie Yang, Executive Director E: richiey@thetagoldmines.com
T: + 61 2 8046 7584
Investor Relations and Media Communications
We’re committed to keeping you informed and involved. Sign up for the Engage IR App and Investor Hub
today and join the conversation.
Webpage: www.thetagoldmines.com
https://twitter.com/ThetaGoldMines
https://www.linkedin.com/company/thetagoldmines/
THETA GOLD MINES LIMITED
Investor Presentation
Australian Gold Conference
Presenter: Richie Yang (Executive Director)
Sydney, October 2026
SOUTH AFRICA’S NEXT
SUSTAINABLE GOLD PRODUCER
FORWARD LOOKING AND CAUTIONARY STATEMENTS
This presentation may refer to the intention of Theta Gold Mines regarding estimates or future events which could be considered
forward looking statements. Forward looking statements are typically preceded by words such as “Forecast”, “Planned”,
“Expected”, “Intends”, “Potential”, “Conceptual”, “Believes”, “Anticipates”, “Predicted”, “Estimated” or similar expressions.
Forward looking statements, opinions and estimates included in this announcement are based on assumptions and
contingencies which are subject to change without notice, and may be influenced by such factors including but not limited to
funding availability, market-related forces (commodity prices, exchange rates, stock market indices and the like) and political,
environmental or economic events (including government or community issues, land owners, global or systemic events). Forward
looking statements are provided as a general reflection of the intention of the Company as at the date of release of the document,
however are subject to change without notice, and at any time. Future events are subject to risks and uncertainties, and as such
results, performance and achievements may in fact differ from those referred to in this announcement. Mining, by its nature, and
related activities including mineral exploration, are subject to a large number of variables and risks, many of which cannot be
adequately addressed, or be expected to be assessed, in this document. Work contained within or referenced in this report may
contain incorrect statements, errors, miscalculations, omissions and other mistakes. For this reason, any conclusions, inferences,
judgments, opinions, recommendations or other interpretations either contained in this announcement, or referencing this
announcement, cannot be relied upon. There can be no assurance that future results or events will be consistent with any such
opinions, forecasts or estimates. The Company believes it has a reasonable basis for making the forward-looking statements
contained in this document, with respect to any production targets, resource statements or financial estimates, however further
work to define Mineral Resources or Reserves, technical studies including feasibilities, and related investigations are required
prior to commencement of mining. No liability is accepted for any loss, cost or damage suffered or incurred by the reliance on the
sufficiency or completeness of the information, opinions or beliefs contained in this announcement.
The Revised Feasibility Study released to the ASX on 3 February 2026 and referred to in this announcement is based on technical
and economic assessments to support the estimation of Ore Reserves. There is no assurance that the intended development
referred to will proceed as described, and will rely on access to future funding to implement. Theta Gold Mines believes it has
reasonable grounds to expect that the results of the Feasibility Study will be achieved. At this stage there is no guarantee that
funding will be available, and investors are to be aware of any potential dilution of existing issued capital. The production targets
and forward-looking statements referred to are based on information available to the Company at the time of release, and should
not be solely relied upon by investors when making investment decisions. Theta Gold cautions that mining and exploration are
high risk, and subject to change based on new information or interpretation, commodity prices or foreign exchange rates. Actual
results may differ materially from the results or production targets contained in this release. Further evaluation is required prior to a
decision to conduct mining being made. The estimated Mineral Resources quoted in this release have been prepared by
Competent Persons as required under the JORC Code (2012). Material assumptions and other important information are
contained in this release. The Company confirms that all material assumptions underpinning the production target, or the forecast
financial information derived from the production target continue to apply and have not materially changed from that released in the
Revised Feasibility Study released to ASX on 3 February 2026.
BUSINESS STRUCTURE
Theta Gold Mines holds 100% issued capital of its South African subsidiary Theta Gold SA (Pty) Ltd (“TGSA”). TGSA holds a
74% shareholding in both Transvaal Gold Mining Estates Limited (“TGME”) and Sabie Mines (Pty) Ltd (“Sabie Mines”). TGME
holds the various exploration and mining permits. The balance of shareholding is held by Black Economic Empowerment (“BEE”)
entities. The South African Mining Charter requires a minimum of 26% meaningful economic participation by the historically
disadvantaged South Africans (“HDSAs”). The BEE shareholding in TGME and Sabie Mines is comprised of a combination of local
community trusts, an employee trust and a strategic entrepreneurial partner.
DISCLAIMER AND COMPETENT PERSONS STATEMENT
DISCLAIMER
This announcement or presentation has been prepared by and issued by Theta Gold Mines Limited (ASX:TGM) to assist in informing
interested parties about the Company and should not be considered as an offer or invitation to subscribe for or purchase any securities in
the Company or as an inducement to make an offer or invitation with respect to those securities. No agreement to subscribe for securities in
the Company will be entered into on the basis of this announcement.
This announcement or presentation may contain forward looking statements. Whilst Theta Gold Mines has no reason to believe that any such
statements and projections are either false, misleading or incorrect, it does not warrant or guarantee such statements. Nothing contained
in this announcement constitutes investment, legal, tax or other advice. This overview of Theta Gold Mines does not purport to be all
inclusive or to contain all information which its recipients may require in order to make an informed assessment of the Company’s prospects.
Before making an investment decision, you should consult your professional adviser, and perform your own analysis prior to making any
investment decision. To the maximum extent permitted by law, the Company makes no representation and gives no assurance, guarantee or
warranty, express or implied, as to, and take no responsibility and assume no liability for, the authenticity, validity, accuracy, suitability or
completeness of, or any errors in or omissions, from any information, statement or opinion contained in this announcement. This
announcement contains information, ideas and analysis which are proprietary to Theta Gold.
COMPETENT PERSONS STATEMENT
The information in this report relating to mineral resources and ore reserves is based on, and fairly reflects, the information and supporting
documentation compiled by Mr Uwe Engelmann (BSc (Zoo. & Bot.), BSc Hons (Geol.), Pr.Sci.Nat. No. 400058/08, MGSSA), a director of
Minxcon (Pty) Ltd and a member of the South African Council for Natural Scientific Professions and Mr Daniel van Heerden (B.Eng.
(Mining), M.Com. (Business Management)), member of Engineering Council of South Africa (Pr.Eng. Reg. No. 20050318)), a director of
Minxcon (Pty) Ltd and a fellow of the South African Institute of Mining and Metallurgy (FSAIMM Reg. No. 37309).
The original reports titled “Theta Gold Increases Mineral Resource to over 6Moz” dated 16 May 2019, “Optimised Mine Schedule for Theta
Open Pit Starter Project Delivers Significant Improvements” dated 20 April 2020 and “Initial Maiden Underground Mining Reserve 419,000 oz
Gold” dated 8 April 2021 were released to the Australian Securities Exchange (ASX) on those dates. The Company confirms that:
• it is not aware of any new information or data that materially affects the information included in the ASX announcements; and
• all material assumptions and technical parameters underpinning the estimates in the ASX announcements continue to apply and have not
materially changed.
BASE CASE PRODUCTION TARGET
The Base Case Production Target and forecast financial information disclosed in this study are based on Mineral Resources that include a
proportion of Inferred Mineral Resources and the realisation of the full potential of the Base Case as presented cannot be guaranteed.
Inferred Mineral Resources are considered too speculative geologically to have the economic considerations applied to them that would
enable them to be classified as Ore Reserves. There is no certainty that further exploration work or evaluation studies will result in the
conversion of Inferred Mineral Resources to Indicated or Measured Mineral Resources or Ore Reserves.
AUTHORISATION
This presentation was authorised for release by the Board of Theta Gold Mines Limited.
2
Disclaimer
INVESTOR PRESENTATION | ASX: TGM
BILL GUY
Executive Chairman
Executive (Geologist) with +30 years of
global experience in resource development.
Previous roles include capital raisings, project
acquisition, project development and joint
venture operations.
Board & Executive Management
BYRON DUMPLETON
Non-Executive Director
Executive (Geologist) with + 30 years of
technical and operational experience
including; Straits Resources, WMC (St Ives
Gold), Newcrest (Telfer) and KCGM (Golden
Mile – Kalgoorlie super pit). Recently Chief
Geologist for Red 5 before the successful
merger with Silver Lake Resources.
BRETT TANG
Non-Executive Director
Lawyer, professional investor and fund
manager with extensive mining Former
Executive Director Yunnan Gold Mountain Ltd
and principal of Tasman Funds Management,
one of TGM’s early investors, and founding
partner of Nanjing Venture Capital Ltd.
RICHIE YANG
Executive Director
Executive (Corporate Finance) with 20 years of
corporate finance and management experience
for junior resource companies, focusing on
capital raising, M&A and corporate structuring.
Australian and African gold project expertise in
managing multi-disciplinary owner
teams/contractors for the project build.
JACQUES DU TRIOU
Chief Operating Officer (RSA)
Mining Engineer with +30 years across all
stages of mine lifecycle. Founded and led
Qmotion Mining, a highly successful
contracting services provider, and delivered
contracts for the Evander Gold Mine, Sibanye
Stillwater, Anglo Platinum, Royal Bafokeng
Platinum and Murray & Roberts Holdings.
BRENT HOFMAN
Company Secretary & CFO (AUS)
Executive (Corporate Law & Finance) with a
resources and energy background, across
Australian and International listed entities.
Exploration and production asset experience
with a diverse skill set in statutory reporting,
corporate governance, disclosures, legal
compliance, M&A and commercial
transactions.
TERRENCE MOKALE
Social Director (RSA)
Attorney of the High Court of South Africa (B
Juris and LLB), specialising in socio-
economic development and municipal
governance. Engaged community
stakeholders and representatives to work
constructively with mining operators, creating
a win-win platform for all parties involved.
PUSELATSO MATETE
Environmental Director (RSA)
Corporate Governance Manager with 25
years of experience. A member of the Lesotho
Highlands Development Authority. Previously
worked on Gold Field’s South Deep project
(tier-1 mining operation) as a Head of
Sustainable Development and Environment.
LESHOTO (FREDDY) MOKETLA
Mine Manager (RSA)
Mining Engineer with extensive underground
mining experience – having served as the
underground production manager at Harmony
Gold, led the production of gold in a
sustainable and safe manner.
HANSJOERG PLAGGEMARS
Non-Executive Director
Hansjörg is an experienced company director
and joins the Board as a representative of
long-term institutional investors, Deutsche
Balaton, Delphi, and Sparta Group. With a
strong background in corporate finance, debt
structuring and capital markets
Board & management combined 16% ownership
CHING IU (SHARON)
Non-Executive Director
Over 10 years of international experience
across the mining, metals and natural
resources sectors, specialising in corporate
finance, mergers and acquisitions, corporate
strategy, capital markets and business
development. .
INVESTOR PRESENTATION | ASX: TGM
3
16% Directors and
Management
64% Top 10
Shareholding
COMPANY SNAPSHOT (October 2026)
SHARES ON ISSUE ON ASX 1,376 Million
OPTIONS AND PERFORMANCE RIGHTS¹ (FULLY DILUTED
POSITION)
223 Million
SHARE PRICE A$0.19
CASH ON HAND & EXPECTED SHORTLY² A$37 Million
MARKET CAPITALISATION (UNDILUTED)³ A$255 Million
TOP 10 SHAREHOLDERS (October 2026)
1 BNP PARIBAS NOMINEES PTY LTD <IB AU NOMS
RETAILCLIENT>
25.9%
2 CITICORP NOMINEES PTY LIMITED 6.5%
3 CHENGTUN GOLD (HONG KONG) LIMITED 4 5.9%
4 HONGKONG RUIHUA INVESTMENT MANAGEMENT LIMITED 4.6%
5 OATVEST CAPITAL LIMITED 4.1%
6 HSBC CUSTODY NOMINEES (AUSTRALIA) LIMITED 3.7%
7 DEUTSCHE BALATON AKTIENGESELLSCHAFT 5 3.4%
8 ZENITH (HK) HOLDING LIMITED 3.4%
9 MR XINZHOU LI 3.2%
10 2INVEST AG 6 3.0%
1. Fully diluted position if all options and performance rights issued, note 124 million are investor options 13 to 32 cents
2. RBA exchange rate of 0.70 USD:AUD (includes current cash of circa US$26m)
3. Based on the share price of A$0.185 per share on 13 October 2026
4. Sharon Iu – Non-Executive Director and corporate representative of Chengtun Gold (Hong Kong) Limited
5. Related party to 2 Invest AG, acting in concert
6. Hansjoreg Plaggemars – Non-Executive Director and corporate representative of 2 Invest AG.
TRANSVAAL GOLD MINING ESTATE LTD (TGME)
Theta Gold Mines Ltd (ASX:TGM) 74% Local Entrepreneur Trust 5%
Local BEE Entities (Landowners) 16% Local Employees Trust 5%
TGM SHARE PRICE AND VOLUME (Last 3 years)
4
Company Overview
INVESTOR PRESENTATION | ASX: TGM
TGME Gold Project Summary
Funding Completion
TGME Gold Plant Construction
Transvaal Gold Mining Estates (TGME)
Appendix
1
2
3
4
5
Table of Contents
Ore stockpile for plant
commissioning
Construction underway with ~USD 39m1 Spent todate – commissioning targeted for Q4’2026 / first gold Q1’2027
6
High-grade gold project with a 13.1-year mine life, including 8.8 years of reserves and 6.1Moz of resources
First-quartile cost position with AISC of ~USD 1,181/oz supporting strong operating margins
Resilient economics with breakeven gold price of USD 1,323 – 1,503/oz; NPV10 of USD 490m and 911m at USD 3,000/oz and 4,500/oz gold
price respectively
Led by a seasoned management and operations team with substantial in-country experience
Located in established historic goldfields with proximity to key infrastructure and Johannesburg as a mining services hub
Note: 1) Managements estimate based on un-auditd results to 30 September 2026.
Key Investment Highlights
TGME GOLD PROJECT SUMMARY
THETA GOLD MINES | ASX: TGM
7
Overview of Theta Gold
• Theta Gold is an Australian headquartered gold mining
company that owns a 74% stake in the high-grade
Transvaal Gold Mining Estates Project located in the
Mpumalanga province of South Africa
• In February 2026, Theta Gold completed a Revised
Feasibility Study. Under the base case Theta Gold is
forecast to produce 871koz Au over 13.1 years with a
recovered grade of 4.28g/t1
• The high-grade nature of the underground mines within
TGME contributes to Theta Gold having a high-margin first
quartile all-in-sustaining-costs of USD 1,284/oz at gold price
of USD 4,500/oz2
• Theta Gold is in the process of restarting operations at
TGME and has commenced early development works
spending USD 39m3 on the Project development to
September 2026.
• The Company is listed on the Australian Securities
Exchange (“ASX”) with a market capitalization of AUD 254m
(~USD 176m)4
High-grade gold mine(s) located in South Africa’s most prolific gold region supported by existing infrastructure, a skilled workforce, and strong utility access
Key statistics (100% basis) Mine location in South Africa
Q4’2026
Commissioning
13.1 years
Life-of-Mine
604koz Au
Ore Reserves
6.1Moz Au
Mineral Resources
USD 1,284/oz
AISC @ USD 4,500/oz
Au2
USD 102m5
Initial development
capital
USD 1,833m
Post-tax FCF @ USD
4,500/oz Au2
USD 911m
Post-tax NPV10 @
USD 4,500/oz Au2
South Africa
Mpumalanga
Frankfort
CDM
Beta &
Central
Processin
g Plant
Rietfontein
Theta Gold at a Glance
TGME GOLD PROJECT SUMMARY
Note: 1) Base case Life-of-Mine (“LOM”) production figures include a proportion of Inferred Mineral Resources. Refer to slide 3 for further details; 2) Based on an average gold price assumption of USD 2,884/oz in the Revised Feasibility Study, AISC, post-tax FCF and post-tax
NPV10 are USD 1,181/oz, USD 933m and USD 455m respectively; 3) As of 30 September 2026 (un-audited estimates); 4) As of 13 October 2026; 5) Development capital required to achieve first gold at Beta mine, excluding income expected from Rock Dumps and the tailings
storage facility (“TSF”) Source: FactSet
THETA GOLD MINES | ASX: TGM
Note: 1) Forecasts have been prepared by mining industry experts, Minxcon Group, a mining engineering and mineral resources consults based in South Africa, and all figures are presented on a 100% basis; 2) Base case LOM production figures include a proportion of
Inferred Mineral Resources. Refer to slide 3 for further details
8
NPV10 Post-tax sensitivity (USDm)1,2
NPV10 post-tax and annual EBITDA sensitivity to gold price assumptions (USD/oz)
348
490
630
770
911
1,051
2,500 3,000 3,500 4,000 4,500 5,000
Gold Price (USD/oz)
Annual EBITDA Sensitivity (USDm)1,2
87
116
145
174
203
232
2,500 3,000 3,500 4,000 4,500 5,000
Gold Price (USD/oz)
Robust economics and solid asset backing for the TGME Project
TGME GOLD PROJECT SUMMARY
THETA GOLD MINES | ASX: TGM
Note: 1) All figures are presented on a 100% basis; 2) Base case LOM production figures include a proportion of Inferred Mineral Resources. Refer to slide 3 for further details; 3) Carbon-in-leach is a metallurgical process in mining for extracting gold
9
Ore mined by source1,2
Ramp up to peak production of ~115kozpa initially utilizing ready-to-access rock dumps and tailings, followed by ore feed from the Beta and Rietfontein mines
1.62
2.81
5.34
6.22
6.82 6.74 7.33 7.31
5.76
3.46
2.07
3.00 3.50
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
-
1,000
2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039
kt Beta CDM Frankfort
Commentary
• Mining operations are planned to commence at the Beta
mine. A period of 18 months pre-development has been
planned for the Beta mine before stoping commences.
During the Beta development and ramp-up period, TGM
Rock Dumps and plant TSF will be remined and
processed
• Mining operations at the Rietfontein Mine will
commence in Q4’2028
• Following that, the Company plans to scale up
production from the Clewer-Dukes Hill-Morgenzon
(“CDM”) and Frankfort mines
• Theta Gold will continue to expand its resource
potential by systematically evaluating over historic
mines and advancing targeted exploration,
development and drilling across both existing
operations and new high-potential targets
• Free-milling ore (Beta, Rietfontein and CDM)
processed through the Company’s 45kt per month
oxide plant is expected to achieve strong carbon-in-
leach (“CIL”)3 recoveries of 88-96%
Gold production1,2
-
50
100
150
2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039
koz Beta CDM Frankfort Rietfontein Rock Dumps TSF
Mine Plan Overview
TGME GOLD PROJECT SUMMARY THETA GOLD MINES | ASX: TGM
TGME Gold Project Summary
Funding Completion
TGME Gold Plant Construction
Transvaal Gold Mining Estates (TGME)
Appendix
1
2
3
4
5
Table of Contents
Terrance 2 under construction – Now
complete
Note: 1) Assuming USD 90m bond issued at 95.9% net of OID leaves net balance of US$86.3m; 2) Development capex – spent is TGME project capital spent up to 30 September 2026 (un-audited est.)
11
Transaction overview
Deployment of TGME funded through a USD 90 million Nordic bond
Funding Completion
• In June 2026 Theta Gold Mines Ltd ( the “Company”, or “Theta Gold”) issued USD
90m senior secured bonds (the “Bonds” or the “Bond Issue”) to finance the
development of the Transvaal Gold Mining Estates (“TGME” or “Project”) in South
Africa.
• The Bonds will have a 4-year tenor, with make whole provisions through the first 2 years
• The Bonds will be amortized by six equal quarterly instalments, each at USD 7.5m
commencing 30 months from the Issue Date
• Theta Gold Mines completed all conditions Precedent to the first drawdown of the bond
in September 2026 for USD 37 million.
• TGME Project build is monitored by the Independent Engineer
• Pareto Securities was the sole Manager of the Nordic bond issue market
• Argonaut (Perth) acted as debt and finance advisors
Sources (30 Sept 2026)
USDm 86.3
“ (37.0)
“ 49.3
Sources
Senior Secured Bonds1
First Drawdown (10 September)
Undrawn Bond Balance
Breakdown (as at 30 September):
Existing Cash balance “ 26.0
Project Costs Spent2 “ (39.0)
THETA GOLD MINES | ASX: TGM
TGME Gold Project Summary
Funding Completion
TGME Gold Plant Construction
Transvaal Gold Mining Estates (TGME)
Appendix
1
2
3
4
5
Table of Contents
TGME Gold Plant Construction in
Progress
Key contracts already locked in, de-risking the Project
Counterparty Description
Power Supply • Electrical Supply Agreement to TGME
Civil Construction
• The supply, construction, commissioning and related works of the bulk earthworks and civil works for the construction of the TGME gold
plant platforms, roads, pollution control dam, and installation of clean and dirty water channels
Crushing Circuit • Supplier agreement for the crushing circuit
Ball Mills • Contract for two x Titan GDM3065 Ball Mills
Plant Equipment • Design and supply of the agitators, kiln, electrowinning circuit, MPS screens and maintenance bay for the TGME processing facility
Thickeners and
Flocculant Plant
• Design, manufacture and installation of the thickeners and flocculant plant for the TGME processing facility
Diesel • Agreement to provide diesel to the TGME mine site(s) / processing facility
Gold Sales • Contract to purchase gold doré bars from the TGME processing facility1
Note: 1) The Offtake Agreement has not yet been executed as of the date of this Presentation and is expected to be entered into prior to commercial production. Please refer to the Term Sheet for further details.
13
Key Contracts Overview
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
14
• TGME GOLD Plant construction is
72% complete to 30 September 2026
• First Gold Pour Q1 2027
Commentary
Schedule Overview – Project Schedule S-Curve
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
15
TGME –Gold Plant Construction Summary
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
16
Completed crushing and screening plant equipments enroute to South Africa (October 2026)
NMS equipment (part) been loaded to ship for delivery (ETA to Durban Port in Oct 2026) Commentary
• Manufacturing contract with NMS Africa (Pty) Ltd (“NMS”) for a
crushing and screening plant has been executed, with delivery
expected in October.
• The contract covers the manufacture of a three-stage crushing and
screening plant designed to meet initial production requirements,
while allowing for future expansion as the project scales
- The plant includes ore feed, primary, secondary and tertiary
crushing, plus screening circuits
• All continuing construction activities at the site are progressing on
budget and the Project remains on track for commissioning in
Q4’2026
Crushing and Screening Plant Been Delivered to Site
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
17
Ball Mills Secured, Construction Accelerates
TGME Plant Build Progress
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
TGME Gold Plant Milling section under construction
Note: 1) As of 30 September 2026
USD 39m1 already spent to date on earthworks, civils, and processing plant equipment
18
Earthworks Completed in Preparation for the Processing Plant
Carbon in leach tank under construction
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
19
Excavation and Blinding release inspection
of Thickener 600 bund wall.
Pre-concrete shutter inspection of pump
bases at Thickener 1000.
MCC 1 – pour and floating.
Visual post-concrete inspection of the
stacker wall bund wall.
Pre-concrete inspection of Gold room bund
wall area.
Drilling of Pre-Oxidation surface beds to
allow for DCP testing of underlaying layer
works.
Area 800 Stabilenka installation completed
and backfilled.
Road layer works being done on Road 1 at the
southern end of the plant.
Earthworks and Civils (PICM) QAQC Report Pictures
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
20
Super Structure for Elution Circuit and Gold Room
Structural, Mechanical, Piping, and Platework (SMPP)
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
21
Thicker Tanks being constructed
Plant view from Stationary Crane
CIL Tanks and Elution Circuit erected
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
22
Solar Car Park and New Management Offices
Management Offices, Solar Carpark, Goods shed Solar Car Park and Battery System
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
23
Commentary
Gold Room is close to completion:
Gold Room Equipment for pouring and casting gold
• TGM has purchased a Keegor
Industrial Furnace to be used
for smelting and refining gold.
• Gold Casting equipment is
already on site to cast gold
doré bars.
• Gold room and smelting
equipment to be installed in
the completed gold room
expected to be completed in Q3
2026.
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
24
Tailing Facility System Engineering Testing - Density
JEDD – Tailing Facility System (TFS) Rehabilitation
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
25
Underground Mining Equipment
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
• New Siton underground drill rig delivered to site
• Purpose-built for mechanised underground drilling and
mine development
• Mobile, self-contained unit with an articulated hydraulic
drilling boom
• Forms part of the mobilisation of underground mining
equipment
• Supports development of underground mining areas ahead
of production
Commissioning targeted for Q4’2026, with first gold in Q1’2027
Note: First gold produced timing will be subject to obtaining all necessary regulatory permitting approvals
26
Pathway to Production
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
Note: 1) Theta Gold carries 100% of the development costs of TGME, and the TGME Empowerment Company (Pty) Ltd is loan-carried. Please see slide 50 for more details on the Black Economic Empowerment structure; 2) Capex spent for processing plant is the total
amount over the life of mine, 3) Excluding capex from recoupment
27
Mining and infrastructure capex schedule over the life of bond (USDm)1
Minimal development capex after 2026 as production is expected to commence in Q1’2027
7
58
17
10
3
0
2025 2026 2027 2028 2029 2030
Contingency
Overview of capex costs over the life of the bond
65.2
56.1
9.1
Plant 1 Plant 2 Total
18.9
14.6
Beta
Rietf…
Total capex spending
of USD 33.6m, which
includes access
roads, power, water,
ventilation, and other
infrastructure
Processing Plant Capex
Mining and Infrastructure Capex Split by
Mine
A total of USD 65.2m
is spent on processing
plant capex2
12.3
6.4
5.8
Mining &…
Processin…
Total
Contingency
Total additional
contingency of USD
12.3m is required for
the development on
the Project2,3
Development Capex Overview
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
1
2
3
4
TGME Gold Project Summary
Funding Completion
TGME Gold Plant Construction
Transvaal Gold Mining Estates (TGME)
Appendix
5
Table of Contents
New Ball Mill #1 delivered to site – a
day for the history books
29
Asset overview
Shovel-ready mines with key approvals secured and clear pathway to production
• TGME is situated in South Africa’s prolific Eastern Transvaal
Goldfields (Mpumalanga), with historic production of 6.7Moz Au and
remains active today
• Theta Gold’s base case plan is forecast to produce 871koz Au over
a 13.1 year mine life from Beta, Rietfontein, CDM, Frankfort, and
reprocessing of Rock Dumps and TSF tailings
• Annual production is targeted at 90-120koz, with a modular plant
design supporting a pathway to 160koz per year with minimal capex
Key Summary of Mines:
• 620 Km2 of Gold field under management
• 43 historical gold mines; only four are in the current mine plan.
• TGME Gold Plant designed to be capable of doubl
Share your feedback
Discover