TGME Gold Project - Pre-Construction Activities Underway
Released
Released
Announcement PDF
30 April 2025
ASX ANNOUNCEMENT
(ASX: TGM)
TGME Project: Pre-Construction Activities Underway
Theta Gold Mines Limited (“Theta Gold” or the “Company”) (ASX: TGM) is pleased to provide an
operational update on the progress of the TGME Gold Processing Plant. Key pre-construction activities
have commenced, including decommissioning of the old gold plant and completion of the final design
and engineering packages.
A video showcasing the final plant design and approved project footprint is now available on the
Company’s website.
Figure 1: 50 Ton crane on site undertaking decommissioning activities
HIGHLIGHTS
Predevelopment Work
•
•
•
•
•
Procurement of electrical and wastewater management systems for temporary
operations.
Engagement of mobile cranes, flatbed trucks, and heavy equipment to facilitate
decommissioning activities.
Purchase of yellow equipment to dismantle old structures and undertake site
preparation.
Installation of perimeter fencing around the processing plant footprint.
Rerouting of water supply piping and installation of temporary reservoirs - refer
Appendix A.
1
Plant Development Progress
•
•
•
Final Design and Engineering packages for the TGME Gold Plant completed.
Tender process for:
o construction completed with contract drafting in progress, and
o procurement at final stages.
Civil design works and site layout fully permitted and completed - refer Appendix B.
Forecast Schedule - Q2 2025
•
•
•
•
Execution of Engineering, Procurement, Construction and Management (“EPCM”)
contracts for plant procurement and construction.
Purchase orders issued - including crushing circuit and mills.
Pre-execution works to be completed by end of May 2025, enabling bulk earthworks
to commence immediately upon project approval.
Feasibility Study to be refreshed to reflect updated gold pricing and incorporate
surface gold resources.
Figure 2: TGME GOLD PLANT FINAL DESIGN (Video on the company’s website at
https://thetagoldmines.com/)
Comments by the Chairman, Bill Guy:
“We are pleased to report that Theta is nearing build-ready with a fully designed, engineered and
permitted gold processing facility. The transition from planning to action has begun with the
decommissioning of the old plant and site preparation well underway. This is a major step forward in
transforming Theta into a near-term gold producer.
“I encourage all shareholders to review the final design video. Note the video includes all stages of
plant build, including the sulphide circuit, scheduled to be built at later stages.
‘Yellow equipment, including excavators, and cranes will be used to clean up and decommission the
old plant footprint. Repair work will also be done on the existing electrical and water management
system.
“We thank the long-term shareholders who have shown further support for the company’s aspirations
to become a gold producer by exercising their options”.
2
A significant near-term opportunity exists to incorporate approximately 174,000 gold ounces located
in tailings dams and surface rock dumps surrounding the TGME Gold Plant, including 140,600 ounces
of Indicated Resources (refer to JORC Table in Appendix C).
Theta Gold appointed RM Processing (“RMP”) to oversee the comprehensive final plant design and
cost estimates, building on feasibility studies undertaken by Theta Gold and Met63. The TGME Gold
Plant will process underground ore, surface tailings, and rock dumps to produce a Doré bar for
refining.
[ENDS]
This announcement was approved for release by Theta Gold Mines Limited’s Board.
For more information, please visit www.thetagoldmines.com or contact:
Bill Guy, Chairman
Theta Gold Mines Limited
T: + 61 2 8046 7584
E: billg@thetagoldmines.com
Theta Gold Mines' Interactive Investor Hub
The Company encourages shareholders to please join the Theta Investor Hub which allows you to ask
questions directly to the Company, view video’s and keep up to date on progress of the TGME Gold
Project at http://investors.thetagoldmines.com.
Webpage: www.thetagoldmines.com
https://twitter.com/ThetaGoldMines
https://www.linkedin.com/company/thetagoldmines/
3
APPENDIX A: Site Clearing Underway Ahead of Bulk Earthworks
With plant earthworks design complete, the team is clearing the process plant footprint—
relocating equipment and removing old structures. Locally contracted yellow equipment is
supporting prep work for the salvage laydown area, now established in the northeast corner
near the future run-of-mine ore pad.
Figure 3: Delivery of contracted Grader and Roller
Old steel structures, roofing, and mill civils are scheduled for removal in the coming weeks. The
team will drill and blast the mill civils, with all salvaged steel to be stored in the designated
laydown area.
Figure 4: Salvage laydown area
Figure 5: Removal of old conveyor belt structure
4
Figure 6: Cleaning of old mill structures in preparation for drilling and blasting
Figure 7: Old mill civils to be removed
5
APPENDIX B: Updated Feasibility Study in Progress
Pre-project execution is on track for completion by end-May 2025, ensuring the plant site is
fully prepped for bulk earthworks to begin without delay.
The following task was completed on-site as part of the preparation for the process plant execution
phase
Description
Completed
Plant Process Design Engineers Appointed – RM Process
✓
Tailings and Environmental Engineers Appointed – Eco Elementum
✓
Additional Metallurgical Test Work
✓
Updated Process Plant Flowsheet
✓
Final Process Plant and Engineering Design
✓
Process Plant footprint layouts and Civil works
✓
Draft schedules for the plant construction
✓
Draft schedule for the dewatering plant, water management and tailings
deposition
✓
Tender process and Requests for Quotes (RFQ)
✓
NDAs signed with all vetted possible Original Equipment Suppliers (OEM)
✓
Long leading items identified
✓
Project Execution Plan completion
✓
Table 1: Provides a summary of the completed design and planning stages of the plant.
The updated Feasibility Study will reflect the increasing gold price and extend mine life by
adding the surface source of gold around the plant site. In total, 174,000 gold ounces sit on
the surface, in tailings dams and surface rock dumps, surrounding the TGME gold plant,
including 140,600 ounces of Indicated Resources in various tailings dams (Refer to JORC
Table Appendix C). Theta is working on adding the surface gold resources into the mine
schedule.
RM Processing (“RMP”) was appointed to prepare a comprehensive cost estimate for
completing the detailed final design engineering of the TGME Gold Processing Plant. This
facility is designed to process "gold ore, based on recent feasibility studies by Theta Gold
and Met63. The project focuses on treating TGME underground ores, tailings material and
surface waste rock dumps to produce a Doré bar.
6
ANNEXURE C
Mineral Resource and Mining Reserves
Combined Mineral Resource as at 1 February 2021
Combined Mineral Resource
Resource
Classification
Measured
Type of Operation
Tonnage
Gold Grade
Mt
g/t
Underground
Open pit
Tailings
Total Measured
Indicated
Underground
Open Pit
Tailings
Total Indicated
Inferred
Underground
Open pit
Tailings
Rock Dump
Total Inferred
Grand Total
Notes:
1.
2.
3.
4.
5.
6.
Gold Content
Kg
koz
0.091
5.37
489
15.7
0.091
4.774
8.109
5.244
18.128
21.452
4.907
0.023
0.885
27.267
45.485
5.37
6.21
2.14
0.83
2.84
5.22
5.11
0.57
1.20
5.06
4.17
489
29 661
17 364
4 373
51 398
111 880
25 057
13
1 059
138,009
189,896
15.7
953.7
558.2
140.6
1,652.5
3597.0
805.6
0.4
34.0
4,437.0
6,105.2
Columns may not add up due to rounding.
Gold price used for the cut-off calculations is USD1,500/oz.
UG Mineral Resources are reported at a cut-off of 160 cm.g/t, open pit at 0.5 g/t and 0.35 g/t, tailings and rock dumps at
0.35 g/t.
Fault losses of 5% for Measured and Indicated, 10% for Inferred Mineral Resources.
Mineral Resources are stated as inclusive of Ore Reserves.
Mineral Resources are reported as total Mineral Resources and are not attributed.
Mineral Resources for the TGM Tailings Dams as at 1 February 2021
Mineral Resource
Classification
Indicated
Surface
Operation
Glynn’s Lydenburg
Blyde 1
Blyde 2
Blyde 3
Blyde 4
Blyde 5
TGM Plant
Reef
Tailings
Tailings
Tailings
Tailings
Tailings
Tailings
Tailings
Total Indicated
Mineral Resource
Classification
Inferred
Total Inferred
Notes:1.
2.
3.
4.
5.
Surface
Operation
Blyde 3a
Reef
Tailings
Tonnage
Mt
1.211
0.590
0.280
0.316
0.164
0.022
2.661
5.244
Gold
Grade
g/t
0.80
0.73
0.83
0.87
0.72
0.61
0.87
0.83
Gold Content
kg
koz
972
31.3
434
14.0
234
7.5
275
8.8
119
3.8
14
0.4
2,325
74.8
4,373
140.6
Tonnage
Mt
0.023
0.023
Gold
Grade
g/t
0.57
0.57
Gold Content
kg
koz
13
0.4
13
0.4
Mineral Resource cut-off of 0.35 g/t applied.
TGM Plant tailings: 10% discount applied for volume uncertainty.
Gold price used for the cut-off calculations is USD1,500/oz.
Mineral Resources are stated as inclusive of Ore Reserves.
Mineral Resources are reported as total Mineral Resources and are not attributed.
7
Mineral Resources for the TGM Rock Dumps as at 1 February 2021
Mineral Resource
Classification
Inferred
Inferred
Inferred
Inferred
Inferred
Total Inferred
Notes:1.
2.
3.
4.
Surface Operation
Reef
Vaalhoek
South East (DGs)
Peach Tree
Ponieskrantz
Dukes Clewer
Rock Dump
Rock Dump
Rock Dump
Rock Dump
Rock Dump
Tonnage
Mt
0.121
0.408
0.092
0.129
0.134
0.885
Gold
Grade
g/t
1.64
0.93
1.23
1.63
1.16
1.20
Gold Content
kg
koz
199
6.4
379
12.2
114
3.7
211
6.8
156
5.0
1,059
34.0
Mineral Resource cut-off of 0.35 g/t applied.
Gold price used for the cut-off calculations is USD1,500/oz.
Mineral Resources are stated as inclusive of Ore Reserves.
Mineral Resources are reported as total Mineral Resources and are not attributed.
Combined Underground and Open Pit Ore Reserves as at 1 February 2021
Operation
Beta
Frankfort
CDM
Open Pit (MR83)
Total
Notes:
1.
Grade
g/t
6.51
4.13
2.31
2.74
3.98
Tonnes
kt
1,662
319
385
2,164
4,530
Au Content
kg
koz
10,822
347.94
1,317
42.33
889
28.58
4,996
160.61
18,023
579.46
The information pertaining to the Ore Reserve estimation is detailed in the notes of the Ore Reserve tabulation for the
individual operations.
8
ABOUT THETA GOLD MINES LIMITED
Theta Gold Mines Limited (ASX: TGM) is an advanced gold development company focused on
unlocking value from its extensive suite of projects in South Africa’s renowned Eastern Transvaal
goldfields. The Company’s flagship TGME Gold Project offers near-surface and shallow underground
ore bodies with compelling cost advantages.
TGM’s core project is located next to the historical gold mining town of Pilgrim’s Rest, in Mpumalanga
Province, some 370km northeast of Johannesburg by road or 95km north of Nelspruit (Capital City of
Mpumalanga Province). Following small scale production from 2011 – 2015, the Company is currently
focussing on the construction and financing of a new gold processing plant.
TGM has completed a Feasibility Study (FS) released to ASX on 27 July 2022, for the first four mines
Beta, CDM, Frankfort and Rietfontein (TGME Underground Project). The Base Case LOM plan
comprises a 12.9-year mining operation starting in 2023 and delivering production of 1.24 million
ounces of contained gold.
The estimated development capital or peak funding requirement is USD77 million (AUD102 million),
with the Project forecast to generate a pre-tax NPV10% of USD324 million (AUD432 million) and pretax Internal Rate of Return (IRR) of 65% at the forecast gold price of averaging USD1,642/oz over the
LOM.
TGM aims to build a solid production platform to over next 5 years to 160kozpa based primarily around
shallow, open-pit or adit-entry shallow underground hard rock mining sources. Theta Gold has access
to over 43 historical mines and prospect areas that can be accessed and explored, with over 6.7Moz
of historical production recorded.
TGM holds 100% of Theta Gold SA (Pty) Ltd, which in turn owns 74% of TGME and Sabie Mines, meeting
Black Economic Empowerment (BEE) ownership standards as per South African Mining Charter
requirements.
DISCLAIMER
This announcement has been prepared by and issued by Theta Gold Mines Limited to assist in
informing interested parties about the Company and should not be considered as an offer or invitation
to subscribe for or purchase any securities in the Company or as an inducement to make an offer or
invitation with respect to those securities. No agreement to subscribe for securities in the Company
will be entered into on the basis of this announcement.
This announcement may contain forward looking statements. Whilst Theta Gold has no reason to
believe that any such statements and projections are either false, misleading or incorrect, it does not
warrant or guarantee such statements. Nothing contained in this announcement constitutes
investment, legal, tax or other advice. This overview of Theta Gold does not purport to be all inclusive
or to contain all information which its recipients may require in order to make an informed assessment
of the Company’s prospects. Before making an investment decision, you should consult your
9
professional adviser, and perform your own analysis prior to making any investment decision. To the
maximum extent permitted by law, the Company makes no representation and gives no assurance,
guarantee or warranty, express or implied, as to, and take no responsibility and assume no liability
for, the authenticity, validity, accuracy, suitability or completeness of, or any errors in or omissions,
from any information, statement or opinion contained in this announcement. This announcement
contains information, ideas and analysis which are proprietary to Theta Gold.
The Company confirms that all material assumptions underpinning the production target, or the
forecast financial information derived from the production target continue to apply and have not
materially changed from those previously released to ASX in a Feasibility Study dated 27 July 2022.
10
Share your feedback
Discover