TGM Investor Presentation - Nordic Funds and Mines
Released
Released
Announcement PDF
Theta Gold Mines Limited ACN 131 758 177
Registered Office: Level 35, One International Towers, 100 Barangaroo Avenue
Sydney, NSW 2000, Australia
13 October 2026
ASX ANNOUNCEMENT AND MEDIA RELEASE
(ASX: TGM)
Nordic Funds and Mines Conference – Investor Presentation
Theta Gold Mines Limited (ASX: TGM) (Theta or the Company) is pleased to advise that Chairman, Bill
Guy will be participating in the Nordic Funds and Mines Conference in Stockholm from October 15 to 16,
2026.
The Nordic Funds and Mines Conference is Scandinavia’s premier global mining investment event and
provides the Company with an opportunity to show case progress of the Company’s TGME Gold Mine
Project and engage with Nordic institutional and retail investors.
Bill Guy will also have an opportunity to meet and provide updates to many of the Nordic Bond Holders
who participated in the US$90 Million Bond Issue provided to the Company in June 2026.
An updated Investor Presentation is attached and released with this announcement.
[ENDS]
This announcement was approved for release by Theta Gold Mines Limited’s Chairman.
For more information, please visit www.thetagoldmines.com contact key management:
Bill Guy, Chairman E: billg@thetagoldmines.com
Richie Yang, Executive Director E: richiey@thetagoldmines.com
T: + 61 2 8046 7584
Investor Relations and Media Communications
SOUTH AFRICA’S NEXT
SUSTAINABLE GOLD PRODUCER
Investor Presentation
Nordic Funds and Mines Conference
October 2026
THETA GOLD MINES LIMITED
FORWARD LOOKING AND CAUTIONARY STATEMENTS
This presentation may refer to the intention of Theta Gold Mines regarding estimates or future events which could be considered
forward looking statements. Forward looking statements are typically preceded by words such as “Forecast”, “Planned”,
“Expected”, “Intends”, “Potential”, “Conceptual”, “Believes”, “Anticipates”, “Predicted”, “Estimated” or similar expressions.
Forward looking statements, opinions and estimates included in this announcement are based on assumptions and
contingencies which are subject to change without notice, and may be influenced by such factors including but not limited to
funding availability, market-related forces (commodity prices, exchange rates, stock market indices and the like) and political,
environmental or economic events (including government or community issues, land owners, global or systemic events). Forward
looking statements are provided as a general reflection of the intention of the Company as at the date of release of the document,
however are subject to change without notice, and at any time. Future events are subject to risks and uncertainties, and as such
results, performance and achievements may in fact differ from those referred to in this announcement. Mining, by its nature, and
related activities including mineral exploration, are subject to a large number of variables and risks, many of which cannot be
adequately addressed, or be expected to be assessed, in this document. Work contained within or referenced in this report may
contain incorrect statements, errors, miscalculations, omissions and other mistakes. For this reason, any conclusions, inferences,
judgments, opinions, recommendations or other interpretations either contained in this announcement, or referencing this
announcement, cannot be relied upon. There can be no assurance that future results or events will be consistent with any such
opinions, forecasts or estimates. The Company believes it has a reasonable basis for making the forward-looking statements
contained in this document, with respect to any production targets, resource statements or financial estimates, however further
work to define Mineral Resources or Reserves, technical studies including feasibilities, and related investigations are required
prior to commencement of mining. No liability is accepted for any loss, cost or damage suffered or incurred by the reliance on the
sufficiency or completeness of the information, opinions or beliefs contained in this announcement.
The Revised Feasibility Study released to the ASX on 3 February 2026 and referred to in this announcement is based on technical
and economic assessments to support the estimation of Ore Reserves. There is no assurance that the intended development
referred to will proceed as described, and will rely on access to future funding to implement. Theta Gold Mines believes it has
reasonable grounds to expect that the results of the Feasibility Study will be achieved. At this stage there is no guarantee that
funding will be available, and investors are to be aware of any potential dilution of existing issued capital. The production targets
and forward-looking statements referred to are based on information available to the Company at the time of release, and should
not be solely relied upon by investors when making investment decisions. Theta Gold cautions that mining and exploration are
high risk, and subject to change based on new information or interpretation, commodity prices or foreign exchange rates. Actual
results may differ materially from the results or production targets contained in this release. Further evaluation is required prior to a
decision to conduct mining being made. The estimated Mineral Resources quoted in this release have been prepared by
Competent Persons as required under the JORC Code (2012). Material assumptions and other important information are
contained in this release. The Company confirms that all material assumptions underpinning the production target, or the forecast
financial information derived from the production target continue to apply and have not materially changed from that released in the
Revised Feasibility Study released to ASX on 3 February 2026.
BUSINESS STRUCTURE
Theta Gold Mines holds 100% issued capital of its South African subsidiary Theta Gold SA (Pty) Ltd (“TGSA”). TGSA holds a
74% shareholding in both Transvaal Gold Mining Estates Limited (“TGME”) and Sabie Mines (Pty) Ltd (“Sabie Mines”). TGME
holds the various exploration and mining permits. The balance of shareholding is held by Black Economic Empowerment (“BEE”)
entities. The South African Mining Charter requires a minimum of 26% meaningful economic participation by the historically
disadvantaged South Africans (“HDSAs”). The BEE shareholding in TGME and Sabie Mines is comprised of a combination of local
community trusts, an employee trust and a strategic entrepreneurial partner.
DISCLAIMERAND COMPETENT PERSONS STATEMENT
DISCLAIMER
This announcement or presentation has been prepared by and issued by Theta Gold Mines Limited (ASX:TGM) to assist in informing
interested parties about the Company and should not be considered as an offer or invitation to subscribe for or purchase any securities in
the Company or as an inducement to make an offer or invitation with respect to those securities. No agreement to subscribe for securities in
the Company will be entered into on the basis of this announcement.
This announcement or presentation may contain forward looking statements. Whilst Theta Gold Mines has no reason to believe that any such
statements and projections are either false, misleading or incorrect, it does not warrant or guarantee such statements. Nothing contained
in this announcement constitutes investment, legal, tax or other advice. This overview of Theta Gold Mines does not purport to be all
inclusive or to contain all information which its recipients may require in order to make an informed assessment of the Company’s prospects.
Before making an investment decision, you should consult your professional adviser, and perform your own analysis prior to making any
investment decision. To the maximum extent permitted by law, the Company makes no representation and gives no assurance, guarantee or
warranty, express or implied, as to, and take no responsibility and assume no liability for, the authenticity, validity, accuracy, suitability or
completeness of, or any errors in or omissions, from any information, statement or opinion contained in this announcement. This
announcement contains information, ideas and analysis which are proprietary to Theta Gold.
COMPETENT PERSONS STATEMENT
The information in this report relating to mineral resources and ore reserves is based on, and fairly reflects, the information and supporting
documentation compiled by Mr Uwe Engelmann (BSc (Zoo. & Bot.), BSc Hons (Geol.), Pr.Sci.Nat. No. 400058/08, MGSSA), a director of
Minxcon (Pty) Ltd and a member of the South African Council for Natural Scientific Professions and Mr Daniel van Heerden (B.Eng.
(Mining), M.Com. (Business Management)), member of Engineering Council of South Africa (Pr.Eng. Reg. No. 20050318)), a director of
Minxcon (Pty) Ltd and a fellow of the South African Institute of Mining and Metallurgy (FSAIMM Reg. No. 37309).
The original reports titled “Theta Gold Increases Mineral Resource to over 6Moz” dated 16 May 2019, “Optimised Mine Schedule for Theta
Open Pit Starter Project Delivers Significant Improvements” dated 20 April 2020 and “Initial Maiden Underground Mining Reserve 419,000 oz
Gold” dated 8 April 2021 were released to the Australian Securities Exchange (ASX) on those dates. The Company confirms that:
• it is not aware of any new information or data that materially affects the information included in the ASX announcements; and
• all material assumptions and technical parameters underpinning the estimates in the ASX announcements continue to apply and have not
materially changed.
BASE CASE PRODUCTION TARGET
The Base Case Production Target and forecast financial information disclosed in this study are based on Mineral Resources that include a
proportion of Inferred Mineral Resources and the realisation of the full potential of the Base Case as presented cannot be guaranteed.
Inferred Mineral Resources are considered too speculative geologically to have the economic considerations applied to them that would
enable them to be classified as Ore Reserves. There is no certainty that further exploration work or evaluation studies will result in the
conversion of Inferred Mineral Resources to Indicated or Measured Mineral Resources or Ore Reserves.
AUTHORISATION
This presentation was authorised for release by the Board of Theta Gold Mines Limited.
2
Disclaimer
INVESTOR PRESENTATION | ASX: TGM
TGME Gold Project Summary
TGME Gold Plant Construction
Transvaal Gold Mining Estates
Appendix
1
2
3
4
Table of Contents
Ore stockpile for plant
commissioning
Construction underway with only ~USD 39m1 spent today – commissioning targeted for Q4’2026 / first gold Q1’2027
4
High-grade gold project with a 13.1-year mine life, including 8.8 years of reserves and 6.1Moz of resources
First-quartile cost position with AISC of ~USD 1,181/oz supporting strong operating margins
Resilient economics with breakeven gold price of USD 1,323 – 1,503/oz; NPV10 of USD 490m and 911m at USD 3,000/oz and 4,500/oz gold
price respectively
Led by a seasoned management and operations team with substantial in-country experience
Located in established historic goldfields with proximity to key infrastructure and Johannesburg as a mining services hub
Note: 1) Management's estimate based on unaudited results to 30 September 2026.
Key Investment Highlights
TGME GOLD PROJECT SUMMARY
THETA GOLD MINES | ASX: TGM
5
Overview of Theta Gold
• Theta Gold is an Australian headquartered gold mining
company that owns a 74% stake in the high-grade
Transvaal Gold Mining Estates Project located in the
Mpumalanga province of South Africa
• In February 2026, Theta Gold completed a Revised
Feasibility Study. Under the base case Theta Gold is
forecast to produce 871koz Au over 13.1 years with a
recovered grade of 4.28g/t1
• The high-grade nature of the underground mines within
TGME contributes to Theta Gold having a high-margin first
quartile all-in-sustaining-costs of USD 1,284/oz at gold price
of USD 4,500/oz2
• Theta Gold is in the process of restarting operations at
TGME and has commenced early development works
spending USD 39m3 on the Project development to
September 2026.
• The Company is listed on the Australian Securities
Exchange (“ASX”) with a market capitalization of AUD 254m
(~USD 176m)4
High-grade gold mine(s) located in South Africa’s most prolific gold region supported by existing infrastructure, a skilled workforce, and strong utility access
Key statistics (100% basis) Mine location in South Africa
Q4’2026
Commissioning
13.1 years
Life-of-Mine
604koz Au
Ore Reserves
6.1Moz Au
Mineral Resources
USD 1,284/oz
AISC @ USD 4,500/oz
Au2
USD 102m5
Initial development
capital
USD 1,833m
Post-tax FCF @ USD
4,500/oz Au2
USD 911m
Post-tax NPV10 @
USD 4,500/oz Au2
South Africa
Mpumalanga
Frankfort
CDM
Beta &
Central
Processing
Plant
Rietfontein
Theta Gold at a Glance
TGME GOLD PROJECT SUMMARY
Note: 1) Base case Life-of-Mine (“LOM”) production figures include a proportion of Inferred Mineral Resources. Refer to slide 3 for further details; 2) Based on an average gold price assumption of USD 2,884/oz in the Revised Feasibility Study, AISC, post-tax FCF and post-tax
NPV10 are USD 1,181/oz, USD 933m and USD 455m respectively; 3) As of 30 September 2026; 4) As of 2 October 2026; 5) Development capital required to achieve first gold at Beta mine, excluding income expected from Rock Dumps and the tailings storage facility (“TSF”)
Source: FactSet
THETA GOLD MINES | ASX: TGM
Note: 1) Forecasts have been prepared by mining industry experts, Minxcon Group, a mining engineering and mineral resources consultancy based in South Africa, and all figures are presented on a 100% basis; 2) Base case LOM production figures include a proportion of
Inferred Mineral Resources. Refer to slide 3 for further details
6
NPV10 Post-tax sensitivity (USDm)1,2
NPV10 post-tax and annual EBITDA sensitivity to gold price assumptions (USD/oz)
348
490
630
770
911
1,051
2,500 3,000 3,500 4,000 4,500 5,000
Gold Price (USD/oz)
Annual EBITDA Sensitivity (USDm)1,2
87
116
145
174
203
232
2,500 3,000 3,500 4,000 4,500 5,000
Gold Price (USD/oz)
Robust economics and solid asset backing for the TGME Project
TGME GOLD PROJECT SUMMARY
THETA GOLD MINES | ASX: TGM
Note: 1) All figures are presented on a 100% basis; 2) Base case LOM production figures include a proportion of Inferred Mineral Resources. Refer to slide 3 for further details; 3) Carbon-in-leach is a metallurgical process in mining for extracting gold
7
Ore mined by source1,2
Ramp up to peak production of ~115kozpa initially utilizing ready-to-access rock dumps and tailings, followed by ore feed from the Beta and Rietfontein mines
1.62
2.81
5.34
6.22 6.82 6.74 7.33 7.31
5.76
3.46
2.07
3.00 3.50
0.
00
1.
00
2.
00
3.
00
4.
00
5.
00
6.
00
7.
00
8.
00
-
1,000
2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039
kt Beta CDM Frankfort
Commentary
• Mining operations are planned to commence at the Beta
mine. A period of 18 months pre-development has been
planned for the Beta mine before stoping commences.
During the Beta development and ramp-up period, TGM
Rock Dumps and plant TSF will be remined and
processed
• Mining operations at the Rietfontein Mine will
commence in Q4’2028
• Following that, the Company plans to scale up
production from the Clewer-Dukes Hill-Morgenzon
(“CDM”) and Frankfort mines
• Theta Gold will continue to expand its resource
potential by systematically evaluating over historic
mines and advancing targeted exploration,
development and drilling across both existing
operations and new high-potential targets
• Free-milling ore (Beta, Rietfontein and CDM)
processed through the Company’s 45kt per month
oxide plant is expected to achieve strong carbon-in-
leach (“CIL”)3 recoveries of 88-96%
Gold production1,2
-
50
100
150
2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039
koz Beta CDM Frankfort Rietfontein Rock Dumps TSF
Mine Plan Overview
TGME GOLD PROJECT SUMMARY THETA GOLD MINES | ASX: TGM
TGME Gold Project Summary
TGME Gold Plant Construction
Transvaal Gold Mining Estates
Appendix
1
2
3
4
Table of Contents
TGME Gold Plant
Construction in Progress
Key contracts already locked in, de-risking the Project
Counterparty Description
Power Supply • Electrical Supply Agreement to TGME
Civil Construction
• The supply, construction, commissioning and related works of the bulk earthworks and civil works for the construction of the TGME gold
plant platforms, roads, pollution control dam, and installation of clean and dirty water channels
Crushing Circuit • Supplier agreement for the crushing circuit
Ball Mills • Contract for two x Titan GDM3065 Ball Mills
Plant Equipment • Design and supply of the agitators, kiln, electrowinning circuit, MPS screens and maintenance bay for the TGME processing facility
Thickeners and
Flocculant Plant
• Design, manufacture and installation of the thickeners and flocculant plant for the TGME processing facility
Diesel • Agreement to provide diesel to the TGME mine site(s) / processing facility
Gold Sales • Contract to purchase gold doré bars from the TGME processing facility1
Note: 1) The Offtake Agreement has not yet been executed as of the date of this Presentation and is expected to be entered in
to prior to commercial production. Please refer to the Term Sheet for further details.
9
Key Contracts Overview
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
Master Project Schedule S-Curve
10
• TGME GOLD Plant construction is
72% complete to 30 September 2026
• First Gold Pour Q1 2027
Commentary
Schedule Overview – Master Project Schedule S-Curve
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
11
TGME – Gold Plant Construction Summary
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
12
Locking in this key long-lead item further reduces execution risk and keeps the Project on track for commissioning in Q4’2026
Inspections with NMS and process engineers ahead of contract award Commentary
• Manufacturing contract with NMS Africa (Pty) Ltd (“NMS”) for a
crushing and screening plant has been executed, with delivery
expected in October.
• The contract covers the manufacture of a three-stage crushing
and screening plant designed to meet initial production
requirements, while allowing for future expansion as the
project scales
- The plant includes ore feed, primary, secondary and tertiary
crushing, plus screening circuits
• All continuing construction activities at the site are progressing
on budget and the Project remains on track for commissioning
in Q4’2026
Supplier Selection - Key Crushing and Screening Plant Contract Secured
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
TGME Gold Plant Milling section under construction
Note: 1) As of 30 September 2026
USD 39m1 already spent to date on earthworks, civils, and processing plant equipment
13
Earthworks Completed in Preparation for the Processing Plant
Carbon in leach tank under construction
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
14
Excavation and Blinding release inspection
of Thickener 600 bund wall.
Pre-concrete shutter inspection of pump
bases at Thickener 1000.
MCC 1 – pour and floating.
Visual post-concrete inspection of the
stacker wall bund wall.
Pre-concrete inspection of Gold room bund
wall area.
Drilling of Pre-Oxidation surface beds to
allow for DCP testing of underlaying layer
works.
Area 800 Stabilenka installation completed
and backfilled.
Road layer works being done on Road 1 at the
southern end of the plant.
Earthworks and Civils (PICM) QAQC Report Pictures
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
15
Superstructure for Elution Circuit and Gold Room
Structural, Mechanical, Piping, and Platework (SMPP)
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
16
Ball Mills Secured, Construction Accelerates
TGME Plant Build Progress
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
17
Elution Building CIL & Tailings Thickeners
Mill Circuit CIL Tanks
Engineering Monitoring SMPP
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
18
Thickener Tanks being constructed
Plant view from Stationary Crane
Gold Room Roof – under construction
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
19
Solar Car Park and New Management Offices
Management Offices, Solar Car Park, Goods shed Solar Car Park and Battery System
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
20
Commentary
Gold Room is close to completion:
Gold Room Equipment for pouring and casting gold
• TGM has purchased a Keegor
Industrial Furnace to be used
for smelting and refining gold.
• Gold Casting equipment is
already on site to cast gold
doré bars.
• Gold room and smelting
equipment to be installed in
the completed gold room
expected to be completed in Q3
2026.
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
21
Tailings Facility System Engineering Testing - Density
JEDD –Tailings Facility System (TFS) Rehabilitation
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
22
• New Siton underground drill rig delivered to site
• Purpose-built for mechanised underground drilling and
mine development
• Mobile, self-contained unit with an articulated hydraulic
drilling boom
• Forms part of the mobilisation of underground mining
equipment
• Supports development of underground mining areas ahead
of production
Underground Mining Equipment
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
Commissioning targeted for Q4’2026, with first gold in Q1’2027
Note: First gold produced timing will be subject to obtaining all necessary regulatory permitting approvals
23
Pathway to Production
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
Note: 1) Theta Gold carries 100% of the development costs of TGME, and the TGME Empowerment Company (Pty) Ltd is loan-carried. Please see slide 50 for more details on the Black Economic Empowerment structure; 2) Capex spent for processing plant is the total
amount over the life of mine, 3) Excluding capex from recoupment
24
Mining and infrastructure capex schedule over the life of bond (USDm)1
Minimal development capex after 2026 as production is expected to commence in Q1’2027
7
58
17
10
3
0
2025 2026 2027 2028 2029 2030
Contingency
Overview of capex costs over the life of the bond
65.2
56.1
9.1
Plant 1 Plant 2 Total
18.9
14.6
Beta
Rietf…
Total capex spending
of USD 33.6m, which
includes access
roads, power, water,
ventilation, and other
infrastructure
Processing Plant Capex
Mining and Infrastructure Capex Split by
Mine
A total of USD 65.2m
is spent on processing
plant capex2
12.3
6.4
5.8
Mining &…
Processin…
Total
Contingency
Total additional
contingency of USD
12.3m is required for
the development on
the Project2,3
Development Capex Overview
TGME GOLD PLANT CONSTRUCTION
THETA GOLD MINES | ASX: TGM
1
2
3
TGME Gold Project Summary
TGME Gold Plant Construction
Transvaal Gold Mining Estates
Appendix
4
Table of Contents
26
Asset overview
Shovel-ready mines with key approvals secured and clear pathway to production
• TGME is situated in South Africa’s prolific Eastern Transvaal
Goldfields (Mpumalanga), with historic production of 6.7Moz Au and
remains active today
• Theta Gold’s base case plan is forecast to produce 871koz Au over
a 13.1 year mine life from Beta, Rietfontein, CDM, Frankfort, and
reprocessing of Rock Dumps and TSF tailings
• Annual production is targeted at 90-120koz, with a modular plant
design supporting a pathway to 160koz per year with minimal capex
Key Summary of Mines:
• 620 Km2 of Gold field under management
• 43 historical gold mines; only four are in the current mine plan.
• TGME Gold Plant designed to be capable of doubling capacity to
90 Ktpm
• Theta mine plan brings on 7 mines in next five years
• 3 Moz of gold resource not included in the current mine plan.
• Exploration drilling to increase the current resource base plan
later this year.
• Vaalhoek, Desire, Glens, Rietfontein extension to be further
developed with drilling
TGME Gold Projects Area
Frankfort
CDM
Beta &
Central
Processin
g Plant
Rietfontein
Growth Potential
TRANSVAAL GOLD MINING ESTATES
THETA GOLD MINES | ASX: TGM
Theta Gold is actively restoring the ecological and hydrological integrity of the catchment to safeguard biodiversity and critical ecosystem services. Key initiatives include:
27
>
These actions are essential for
ensuring long-term resilience of the
catchment, protecting both local
communities and vital ecosystems
downstream
Invasive Tree
Control & Re-
vegetation
Riparian Zone
Management
Fire Belt
Implementation
Erosion &
Sediment Control
Targeted removal of alien species
and replanting with indigenous
vegetation
Ongoing monitoring and removal of
invasive trees within the river
corridor
Strategic fire lines to protect
sensitive areas and promote
natural regeneration
Stabilizing vulnerable zones
through native plant re-vegetation
and landscape rehabilitation
• The critical river system sustains over 20,000 farm workers
and serves as the lifeline for Kruger National Park –
especially during dry winter months
• Unless urgent action is taken, collapse is projected within
15 years
Critical river
system
• Invasive species and unsustainable land use are already
placing significant pressure on the system
• Theta Gold is acting now – before this vital water source
disappears
• Theta Gold will join local industry and NGOs to rehabilitate
the catchment and rivers
Invasive species
& unsustainable
land use
Theta Gold has launched an Ecological Compensation programme
ESG: Restoring the Local Catchment and River System
TRANSVAAL GOLD MINING ESTATES
THETA GOLD MINES | ASX: TGM
Occupational health and safety training and local skills development
28
Direct employment over LoM (FTEs)
Workforce builds to ~500 FTEs by Year 4 and peaks at ~535, supported by a zero-harm, health-focused culture
50
200
370
513 517 515 509 505 493 535
478
349 306
181
1 2 3 4 5 6 7 8 9 10 11 12 13 14
LoM Year HIV & AIDS
program
TB
program
Other HSEs
program
Employee wellness
program
Substance abuse
program
Communicable diseases
protocols
ESG: Direct Employment and Workplace Health & Safety
TRANSVAAL GOLD MINING ESTATES
THETA GOLD MINES | ASX: TGM
Note: 1) FTE = full-time equivalent.
1
2
4
TGME Gold Project Summary
TGME Gold Plant Construction
Transvaal Gold Mining Estates
Appendix
3
Table of Contents
Mineral Resource
Classification
Mine Reef
Reef Grade
Stope
Grade Reef Width Stope width Content
Reef
Tonnes
Stope
Tonnes Au Content
g/t g/t cm cm cm.g/t Mt Mt kg koz
Measured Frankfort Bevetts 7.13 5.37 73 103 520 0.069 0.091 489 15.7
Total Measured 7.13 5.37 73 103 520 0.069 0.091 489 15.7
Indicated Frankfort Bevetts 7.86 5.13 58 96 452 0.243 0.373 1,912 61.5
CDM Rho 13.19 3.80 23 90 307 0.258 0.895 3,401 109.4
Beta Beta 21.66 6.58 23 90 499 0.716 2.357 15,506 498.5
Rietfontein Rietfontein 14.57 8.20 52 92 755 0.517 0.919 7,534 242.2
Total Indicated 16.35 6.24 30 91 540 1.734 4.543 28,352 912
Total Measured & Indicated 16.00 6.22 32 92 540 1.803 4.634 28,841 927
Mineral Resource
Classification
UG Mine Reef
Reef Grade
Stope
Grade Reef Width Stope width Content
Reef
Tonnes
Stope
Tonnes Au Content
g/t g/t cm cm cm.g/t Mt Mt kg koz
Inferred Frankfort Bevetts 7.41 4.27 48 93 356 0.343 0.596 2,543 81.8
CDM Rho 10.06 3.02 24 90 244 0.544 1.811 5,472 175.9
Beta Beta 16.51 5.43 25 90 414 1.107 3.367 18,285 587.9
Rietfontein Rietfontein 14.06 8.52 57 94 803 1.190 1.962 16,721 537.6
Total Inferred 13.51 5.56 39 92 524 3.184 7.736 43,022 1,383.2
Notes:-
1. Mineral Resource cut-off of 160 cm.g/t applied.
2. Fault losses of 5% for Measured and Indicated, 10% for Inferred Mineral Resources.
3. Gold price used for the cut-off calculations is USD1,500/oz.
4. cm.g/t and g/t figures will not back calculate due to variable densities in reef and waste rock.
5. Mineral Resources are stated as inclusive of Ore Reserves.
6. Mineral Resources are reported as total Mineral Resources and are not attributed.
The company confirms that it is not aware of any new information or data that materially affects the information included in the presentation and that all material assumptions and parameters underpinning the estimates in the release continue to apply and have not materially
changed. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the reported tables in this presentation.
30
Total Mineral Resources of the 4 Mines included in the DFS
- Combined as of 1 February 2021
THETA GOLD MINES | ASX: TGM
APPENDIX
Notes:
•An Ore Reserve cut-off of 170 cm.g/t has been applied for the Beta Mine.
•An Ore Reserve cut-off of 150 cm.g/t has been applied for the Frankfort Mine.
•An Ore Reserve cut-off of 121 cm.g/t has been applied for the CDM Mine.
Table: Ore Reserve Estimate for TGM Mines (Ore Reserve Plan)
Notes:
•An Ore Reserve cut-off of 160 cm.g/t has been applied for the Rietfontein Mine.
•A gold price of USD2,710/oz and exchange rate of ZAR/USD 19.65 was used for the cut-off calculation.
•Discrepancy due to summation may occur due to rounding.
The company confirms that it is not aware of any new information or data that materially affects the information included in the presentation and that all material assumptions and parameters underpinning the estimates in the release continue to apply and have
not materially changed. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the reported tables in this presentation.
31
THETA GOLD MINES | ASX: TGM
APPENDIX
Mineral Resource
Classification
Mine Reef
Reef Grade Stope Grade
Reef
Width
Stope
width
Content
Reef
Tonnes
Stope
Tonnes
Au Content
g/t g/t cm cm cm.g/t Mt Mt kg koz
Measured Frankfort Bevetts 7.13 5.37 73 103 520 0.069 0.091 489 15.7
Total Measured 7.13 5.37 73 103 520 0.069 0.091 489 15.7
Indicated
Frankfort Bevetts 7.86 5.13 58 96 452 0.243 0.373 1,912 61.5
CDM Rho 13.19 3.80 23 90 307 0.258 0.895 3,401 109.4
Beta Beta 21.66 6.58 23 90