Annual Report 2023
Released
Released
Announcement PDF
GOLD MINES LIMITED
A N N UA L R E P O RT 2 0 2 3
CONTENTS
Chairman’s Letter 2
Significant Milestones Achieved in 2023 3
Review of Operations 4
FY23 Highlights 5
Theta’s TGME Underground Gold Mine Definitive Feasibility
Study (FS) 10
Environment, Social and Governance (ESG) 19
Ore Reserve and Mineral Resource Statement 30
Disclaimer’s 33
Corporate Governance Statement 37
Directors’ Report 41
Remuneration Report 50
Directors’ Declaration 56
Auditor Independence Declaration 57
Financial Statements 58
Independent Auditor’s Report 88
Shareholder Information 93
Directory 95
1
THETA GOLD MINES LIMITED | ANNUAL REPORT 2023
CHAIRMANS
LETTER
Dear Fellow Shareholders,
On behalf of the Board of Directors, I am pleased
to present the 2023 Annual Report for Theta
Gold Mines Limited (ASX: TGM | OTC: TGMGF).
The Company has made significant progress over
the last twelve months. The TGME Underground
Feasibility Study (FS) was completed in July 2022,
The Frankfort Mine was fully permitted with the
granting of the necessary Water Use Licence
(WUL) and mining began for the commercial bulk
sampling program. Both the Environmental Impact
Assessment (EIA) and the WUL documentation for
Mining Right (MR) were submitted. The WUL and
the EIA were approved in July 2023 for MR 83,
which is currently in a public process.
As Chairman of TGM I’m extremely proud of the
achievements made by all by our management
during this year which lays down the foundations
that give TGM the opportunity to become the next
significant, mid-tier gold producer in South Africa.
In July 2022, the Company completed a FS for
the first four mines Beta, CDM, Frankfort and
Rietfontein (TGME Underground Gold Project).
The Base Case life of mine (LOM) plan will comprise
a 12.9-year mining operation starting in 2024
to deliver production of 1.24 million ounces of
contained gold. Peak production is expected to be
over 100,000 ounces per year. By adding the fourth
mine Rietfontein to the mining schedule, there has
been a significant scale-up from the April 2021 prefeasibility study with a production rate of just above
60,000 ounces per annum.
The estimated development capital or peak funding
requirement is US$77 million (with a total Capex
of US$100 million), with the project forecast to
generate a pre-tax NPV10% of US$324 million
(A$432 million) and pre-tax Internal Rate of Return
(IRR) of 65% at the forecast average gold price of
US$1,642/oz over the LOM.
Underground mining will deliver higher-grade ore to
the gold plant with a much smaller environmental
footprint that’s well supported by the local
community and key stakeholders, with access to
a larger resource base of 4.5 million ounces of
underground mineral resources.
(“Term Sheet”) with Sprott Streaming who will
advance US$70 million (~A$110 million) cash in
return for a gold stream on Theta’s TGME Gold
Project (the “Project”).
Environment, Social and Governance (ESG) is
enhanced by the TGME Underground Project.
Over 20 environmental studies were completed
for Mining Right (MR)83. The final Environmental
Impact Assessment Report and Environmental
Management Programme (EIA/EMPr) was approved
by the Department of Mineral Resources and
Energy (DMRE) together with the final technical
documents for the integrated Water Use Licence
(WUL) approval in the second half of 2023.
Theta Gold is now able to commence mine planning,
subject to securing funding for the development
and construction of its gold operations. While
the Company actively seeks to finalise funding
packages, it will commence delivery of a series of
bulk samples from its fully approved Frankfort mine
to the Barberton gold plant to begin early cashflow
generation for the Company.²
Moving forward into the 2024 financial year, the
company will continue with progress on its bulk trial
mining program at Frankfort gold mine which will
provide the Company with early cashflows. It will
also look to finalise funding negotiations with Sprott
Streaming to enable it to commence development
construction at its TGME gold project under the
supervision of Chief Operations Officer, a proven
African gold mine builder Mr. Jacques Du Triou.
We appreciate the continued support from our
shareholders, and we welcome new shareholders
to the share register. The Company looks forward
to continuing to progress project development and
deliver good news for shareholders in 2024.
Thank you for your continued support.
Bill Guy
Chairman
Charles (Bill) Guy
Shortly after the release of the FS, the Company
announced it has entered into an agreement
and commenced a due-diligence process with
royalty streaming debt funder, Sprott Streaming
and Royalty Corporation (“Sprott Streaming”)¹.
Under a non-binding Streaming Term Sheet
2
SIGNIFICANT
MILESTONES
ACHIEVED IN
2023
•
Feasibility Study (FS) completed
underpinning an initial 12.9-year mine life to
deliver free cash flows of up to US$500m and
1.24Moz contained gold production;
•
Granted a Water Use License (WUL)
for Frankfort mine by the South African
Department of Water and Sanitation (DWS)
resulting in Frankfort being fully permitted;
•
Execution of A$110m (US$70m) non-binding
Term Sheet (“TGME Stream”) signed with
Sprott Streaming and Royalty Corporation
(Sprott Streaming) for pre-development,
development capital and operating
expenditure to bring the TGME Gold Project
into production subject to completion of
due-diligence;
•
Received blasting license approval to
commence underground blasting operations
at Frankfort mine;
•
Received the Water Use License for its TGME
Gold Project over Mining Right 83 from the
Department of Water and Sanitation (DWS)
of South Africa1;
•
Frankfort Mine commercial bulk sample
mining preparation and operations initiated
with drill and blast options underway for the
first delivery of 3,000 tones;2
•
Final Environmental Authorisation (EA)
received for Mining Right 83 from the
Department of Mineral Resource and
Energy (DMRE) of South Africa. Note
on 11 September 2023 the Company
announced it had received a notice of
objection from a private individual against
the granting of the EA.
Figure 1: Miners entering Frankfort gold Mine
1
2
3
efer to ASX Release dated 11 April 2023 titled, “Theta Received Water Use Licence for Mining Right 83”.
R
Refer to ASX Release dated 15 May 2023 titled, “Operational Update”.
THETA GOLD MINES LIMITED | ANNUAL REPORT 2023
REVIEW OF
OPERATIONS
The Project is located next to the historical gold
mining town of Pilgrim’s Rest, in the Mpumalanga
Province, some 370km northeast of Johannesburg
or 95km north of Nelspruit (the Provincial Capital
City) and includes more than 43 historical mines
identified across the vast prospective gold field of
620 square kilometres (62,000 hectares).
OVERVIEW
The Company delivered its very first definitive
Feasibility Study (FS) in July 2022 which
presents a clear pathway to production via the
re-development of TGME’s gold assets and is
currently focused on the holistic strategy to deliver
long term organic growth, with initial development
focusing on the permitting of six mines to target
a production profile of 160,000 ounces Au per
annum. The TGME Project (Phase 1) incorporates
the first four mines. In April 2021 Theta declared
a maiden underground mining reserve of 419,000
oz @ 5.49 g/t Gold, along with the first Maiden
Underground Pre-Feasibility Study. The Mining
Reserve were based on only 16% of the 4.5 Moz
underground gold resource and incorporated only
three mines across the project area.
Theta Gold Mines Limited (“the Company” or
“Theta Gold” or “TGM”) is a gold exploration
and development company that holds a range of
prospective gold assets through its 74%-owned
subsidiary Transvaal Gold Mining Estate Ltd
(TGME) in a world-renowned South African gold
mining region. The Company’s shares are dual
listed on the Australian Securities Exchange (ASX:
TGM) and the OTC Markets in the United States
(OTC: TGMGF) with Depository Trust & Clearing
(DTC) Eligibility.
The Company’s TGME Underground Gold Mine
Project (“The Project” or “TGME Project”)
phase one consists of four existing mines, Beta,
Frankfort, CDM and the Rietfontein mine.
Figure 2: Location of Theta Gold Mine Project
4
FY23
HIGHLIGHTS
DEFINITIVE FEASIBILITY
STUDY (TGME Underground
Gold Mine Project)
US$834/oz
All-in-sustaining
Cost
1.24Moz
Contained gold
production
All-in-sustaining Cost (AISC) of US$834/oz
(A$1,112/oz) over LOM sits on the bottom
quartile of South Africa and Australian
gold producers;
TGME Feasibility Study3 (FS) delivers 1.24Moz
contained gold production, underpinning an
initial 12.9-year mine life.
Strong financial return based on LOM plan (at
average gold price of A$2,189/oz) with first
production targeted for, 20244 including:
US$77m
Peak Capital
requirement
• Undiscounted free cash flows of US$508m,
(A$678m), pre-tax US$717, (A$956m);
• NPV (at a 10% discount rate) of US$219m,
(A$292m), pre-tax US$324m, (A$432m);
• Capital payback period of 31 months;
• Pre-tax IRR of 65%; and
• Peak production over 100,000 oz Gold.
Peak Capital requirement is US$77m, (A$103m),
total capital requirements US$174m, (A$232m).
Front-End Engineering Design (FEED) of the TGME
gold plant completed, forming an important input
towards the finalisation of the definitive Feasibility
Study (FS) of the TGME underground project5.
5
THETA GOLD MINES LIMITED | ANNUAL REPORT 2023
BULK SAMPLE
TRIAL MINING
PROGRAM AT
FRANKFORT
GOLD MINE
• Theta Gold announced on 3 April 20236 it
had executed a 3,000 tons commercial bulk
sampling ore delivery contract with Barberton
Mines (Pty) for its fully permitted Frankfort Mine.
The contract schedules for TGME to deliver from
its Frankfort Mine 3,000 tons of ore as a bulk
trial sample.
Figure 3: Front end loader moving ore at Frankfort mine
•T
GME will cover its own mining and delivery
costs. Once delivered and accepted at the
Barberton gold plant, a revenue split (Gold Split)
between the parties will apply, subject to the
average recovered grade of gold ore delivered.
Provided the average grade delivered to the
plant is above 3g/t Au, the parties will be paid
in accordance with the Gold Split, and no other
toll/milling costs are required from the Supplier
post-delivery. If the recovered grade of less than
3g/t is achieved, the Gold Split will cease and a
processing cost per ton will be payable.
•T
he Company announced a A$5 million
(US$3.3 million) funding package on 3 April
2023 to finance the commencement of the
bulk trial sampling program. The funding was
raised with strategic long-term investors via
three separate unsecured Convertible Loan
Agreements (‘Agreements’) to progress the
bulk trial sampling program at the Frankfort
Mine along with funding working capital for the
Company.
Figure 4 & 5: Miners installing pipe ventilation at Frankfort mine
•A
t the time of writing this Annual Report the
Company had completed drill and blasting of the
first 3,000 tons of gold ore and has commenced
processing through an on-site DMS unit. All
other necessary development activities had
been completed including the training of 35 new
underground miners, installation of ventilation
pipes and roof support systems, site power,
fuel farm and necessary mining equipment.
efer to ASX release dated 27 July 2022 titled “Theta’s TGME Project Definitive FS Confirms NPV10% of A$432 million at US$1,642/Oz Gold price.”
R
First gold produced timing will be subject to securing funding and obtaining all necessary regulatory permitting approvals.
Refer to ASX release dated 20 June 2022 titled “TGME Gold Project Update”.
6
Refer to ASX Release dated 3 April 2023 titled “$5 million financing and financing and signing of commercial bulk sampling trial run with Pan African Resources’ Barberton Mines Gold Plant”.
3
4
5
6
ENVIRONMENTAL
PERMITTING
ENVIRONMENTAL IMPACT
ASSESSMENT (EIA)
• The Company announced in July 20227 that
the final Environmental Impact Assessment
(EIA) Report and Environmental Management
Programme (EIA/EMPr) have been submitted
to the Department of Mineral Resources
and Energy (DMRE) and the final technical
documents for the integrated Water Use License
(WUL) application to the Department of Water
and Sanitation (DWS) for final decision.
•T
he Company announced on 26 July 2023 that
it has received its Environmental Authorisation
(EA) and that the South African Department
of Minerals Resources and Energy (DMRE)
has granted the Company’s EA application
over MR83. The Company has also received a
notice of objection by a single individual as part
of the appeal process which enables interest
and affected parties an opportunity to lodge
an appeal.
•A
s a result of the DMRE approval, three
(3) of the four (4) mines within the initial
TGME Underground Gold Project are now
fully permitted, subject to a 90-day public
participation and appeal process which enables
interested and affected parties an opportunity
to review and/or lodge an appeal to the DMRE
decision to approve the EA for MR83.
•T
heta Gold is now able to commence mine
planning, subject to securing funding for the
development and construction of its gold
operations. While the Company actively seeks
to finalise funding packages, it will commence
delivery of a series of bulk samples from its fully
approved Frankfort mine to the Barberton gold
plant to begin early cashflow generation for
the Company8.
7
8
9
7
WATER USE LICENCE (WUL)
• The South African Department of Water and
Sanitation (DWS) has granted a Water Use
License (WUL) for the Company’s Mining
Right (MR) 83, which covers the initial TGME
Underground Gold Project mining schedule as
per our Feasibility Study.
• The WUL is issued in accordance with Chapter 4
of the National Water Act, 1998 (Act 36 of 1998)
for a period of 12 years. The WUL forms an
integral part of the TGME Underground Project
since it authorises the extension of the current
Tailings Storage Facility and all planned water
use activities within the MR83 area.
• The approval of the WUL is a result of
comprehensive environmental specialist
studies conducted with detailed engineering
designs that satisfy the extensive regulatory
requirements relating to water and waste
management in South Africa.
• The DWS will inform all interested and affected
parties of the issuing of this licence, which lead
to a 90-day public review and objection period
that has ended on the 30th of June 2023.
The company is still awaiting notification and the
outcome of the 90-day review process from DWS
• The outcome of the decisions from the DMRE
and DWS on the applications are expected in Q2
of 2024 calendar year with an additional 90-days
review and objection period. A positive decision
from the competent authorities will enable
the Company to commence with its MR83
underground mines build.
ATMOSPHERIC EMISSION
LICENSE (AEL)
• An application for an Atmospheric Emissions
License (AEL) was granted for the operation
of the processing plant by the Department of
Forestry, Fisheries and the Environment (DFFE)
in September 2022 along with a State Forest
Licence issued for the Frankfort Mine9.
Refer to ASX release dated 18 July 2022 titled “Permitting Update TGME Underground Gold Project”.
Refer to ASX Release dated, 3 April 2023 titled, “$5 million to fund Bulk Sampling Trial at Theta’s Frankfort mine”.
Refer to ASX release dated 6 September 2022 titled “Two Approvals Granted for the TGME Underground Gold Project”.
THETA GOLD MINES LIMITED | ANNUAL REPORT 2023
Table 1 Environmental Approvals Granted for Mining Rights (MR) 83- Progress Table
Environmental Approvals for Mining Right (MR) 83
Status
Submit application for EA
✓
Submit draft scoping report
✓
Specialists EIA Studies Completed
✓
DMRE acceptance of final Scoping report
✓
Draft EIA/EMPr submitted for public review
✓
Draft IWWMP submitted for public review
✓
Air Quality Emissions approval
✓
Water use approvals
✓
EIA approvals
✓
1. Forestry permits for the continuation of mining are in progress –refer to ASX Release dated 18 July 2022.
2. Refer to ASX Release dated 6 September 2022 “Two License Approvals Granted for TGME Underground Project.”
3. Status of environmental permits as at the completion of this annual report.
CORPORATE
FUNDING
• Theta Gold Raised a total of AU$9.5 million,
(US$6.4 million) during 2023 fiscal year in
development funding for the Frankfort gold mine
bulk sample program and for the TGME gold
mine project, and entered into a non-binding
streaming Term Sheet detailed below as follows:
– AU$2.2 million, (US$1.5 million) of capital
raised (before costs) via a Private Placement
as announced to ASX on 3 August 202
to numerous existing shareholders, new
institutional, professional, and sophisticated
investors. The Company issued a total of
36,584,615 new fully paid TGM Ordinary
Shares (TGM Shares) on the 11 August 2022
via Application for Quotation of Securities
Notice’s made up of 35,384,615 TGM
Shares at the issue price of A$0.065 per
share as part of the Private Placement. In
addition, the Company issued 1,200,000
TGM Shares on the same date at A$0.07
per share to an advising consultant in lieu of
cash consideration.
– On 19 October 2022 the Company
announced that it has entered into a nonbinding Streaming Term Sheet (“Term Sheet”)
with Sprott Resource Streaming and Royalty
Corporation (“Sprott Streaming”) under
which Sprott Streaming is to advance US$70
million (~A$110 million) cash in return for a
gold stream on Theta’s TGME Gold Project
(the “Project”).
he Project is expected to deliver to Sprott
T
Streaming up to 100,000 ounces of gold over
its Life-of-Mine (“LOM”), for which Sprott
Streaming will pay 10% of the gold price per
ounce delivered under the stream. Theta has
the option to buy-back 50% of the stream
based on a pre-agreed price, following which
Theta will deliver 2% of the ongoing gold
production. Prior to initial gold delivery, Theta
will pay in cash or scrip (at 10% discount
to 5 days volume-weighted-average-price
(“VWAP”)) on a semi-annual basis, 9.5% per
annum interest to Sprott Streaming for the
funds advanced.
Under the Term Sheet, conditions precedent
to closing include the completion of technical,
legal, and environmental and social due
diligence, the receipt and review of the project’s
final development budget and schedule, the
completion of definitive documentation, and
the receipt of applicable environmental permits,
operating licences and regulatory approvals.
Closing is scheduled by the first quarter of
2024 calendar year and the funds will be
applied towards the construction of the TGME
Gold Project, located in the Eastern Transvaal
Goldfields in the Mpumalanga Province,
South Africa.
Due diligence remains on-going and has
advanced throughout 2023 calendar year.
Upon a satisfactory conclusion and appropriate
approvals obtained, a Binding Gold Stream
Agreement between Sprott Streaming and
Theta Gold shall be finalised, executed, and
announced to the market in detail.
8
CORPORATE
FUNDING CONT’
Aus Agriculture Pty Ltd (“AAPL”) for
AU$500,000 with terms for each Agreement
identical except for their respective share
in aggregate of a 10% royalty, calculated as
(7%, 2% and 1% respectively based on each
Lenders loaned principal amount) of Gross
Revenues received from the bulk sample
programme. Each Lender named above will
also be entitled to receive a 20% minimum
annual interest rate on loaned amounts
outstanding. Each Lender may at any time
convert all or part of any outstanding amount
into new TGM Shares using a conversion price
calculated as the weighted average price of
trading in TGM Shares on ASX during a 10
day period immediately before the Lender
provides a conversion notice; and
– AU$1.7 million, (US$1.1 million) of capital
raised (before costs) via a Private Placement
to professional and sophisticated investors
as announced on 27 October 2022 . The
Company issued 24,025,716 new fully paid
TGM Ordinary Shares at the issue price of
A$0.070 cents per shares via an Application
for Quotation of Securities released to ASX on
4 November 2022.
– AU$0.572 million, (US$0.383 million) was
raised via a Share Purchase Plan (Plan) to
enable Eligible Shareholders to participate
in the Company’s capital raising activities.
The Company issued 8,171,405 new fully
paid TGM Ordinary Shares on 6 December
2022 via an Application for Quotation of
Securities released to the ASX at the same
price, (A$0.07) as the offer announced
on 27 October 2023, to sophisticated,
institutional and professional investors
who participated in a Private Placement
completed on 4 November 2022.
– AU$5 million, (US$3.5 million) in funding via
three separate unsecured Convertible Loan
Agreements (‘Agreements’) to fund the bulk
trial sampling program at the Frankfort Mine
along with working capital announced by the
Company on 3 April 2023 . The Agreements
are with Deutsche Balaton AG for AU$3.5
million, Golden Asia Investment Group
Ltd (“GAIG”) for AU$1 million, and
– AU$5 million, (US$3.5 million) through a
private placement (Placement) post 30
June 2023 to strategic professional and
sophisticated investors as announced
on 4 July 2023 . Hong Kong Ruihua
Investment Management Limited (“Ruihua”)
cornerstoned AU$3.0 million, (US$2 million)
of the placement. Ruihua is a wholly-owned
subsidiary to its Nanjing based parent
company Jiangsu Ruihua Investment
Holding Group Co., Ltd (since 2003), a fund
manager with over US$3 billion Assets Under
Management who specialises in equity
markets including secondary market trading,
private placements, venture capital and
private equity activities. The Company issued
76,923,077 new fully paid TGM Ordinary
Shares on the 10 July 2023 at the issue price
of A$0.065 cents per share.
Refer to ASX Release dated 27 October 2022 titled, “Theta raise funds to advance TGME gold project”.
Refer to ASX Release dated 6 December 2022 titled, “Purchase Plan Completion Notice”.
Refer to ASX Release dated 3 April 2023 titled, “$5 million to fund bulk sampling trial at Theta’s Frankfort mine”.
14
Refer to ASX Release dated 4 July 2023 titled, “5 million private placement and corporate update”.
11
12
13
9
THETA GOLD MINES LIMITED | ANNUAL REPORT 2023
THETA’S TGME
GOLD PROJECT
DEFINITIVE
FEASIBILITY
STUDY (FS)
The FS15 for the TGME Project was delivered on
27 July 2022, confirming Theta Gold’s potential
to be a significant near-term, high-margin, lowcost gold production project with tremendous
opportunities for future growth. Based on the FS
results, the Project will provide robust financial
returns from a long-life large underground mining
operation for a modest capital investment given
the scale of operations envisaged.
The Project LOM will initially comprise a 12.9-year
mining operation starting in , 202416 calendar year
and delivering LOM production of 1.24 Moz of
contained gold. The estimated peak development
Capital Expenditure (“Capex”) is A$103 million,
with the Project forecast to generate a pre-tax
NPV10% of A$432 million and pre-tax internal
Rate of Return (IRR) of 65% at a forecast average
gold price of A$2,189 per ounce. Based on these
metrics, the Project has a projected capital
payback period of 31 months.
The FS paves the way for a Final Investment
Decision (‘FID’) by the Theta Gold Board in
respect to funding negotiations and on-going
discussions with financiers with respect to full/
partial debt and equity funding options. Theta Gold
has appointed a debt funding advisor to manage
this important process and will provide updates in
due course.
Figure 6: Scenic photo of TGME gold mine project
15
16
Refer to ASX Release dated 27 July 2022 titled “Theta’s TGME Project Definitive FS Confirms NPV(10%) of A$432 Million at US$1,642 / Oz Gold Price”.
Start time will be dependent on securing necessary funding and permitting approvals.
10
KEY FEATURES OF PROJECT
THETA GOLD MINES LIMITED CONTROLS THE EASTERN
TRANSVAAL GOLD FIELDS, WHERE SOUTH AFRICA’S GOLD
MINING INDUSTRY BEGAN ALMOST 130 YEARS AGO.
Project Life
12.9 Years
Metallurgical Recovery
87%
AISC US$788oz (Year 1-4)
US$847/oz (LOM)
US$788oz
Underground ore mined
6.46Mt@5.95g/t Au for
1.24M oz of contained gold
Payback Period Start of
Project – 31 Months. Start of
Mining – 18 Months.
Peak Funding Requirements
US $77M
Pre-Tax NPV 10% US$324M @
USD/oz 1.642 (avg-Base Case)
IRR 65%
First Gold Pour
20241
INCORPORATING
ONLY 4 OF MORE
THAN 40 PREVIOUSLY
DEVELOPED MINES.
Note1. First gold pour is subject to securing funding and all necessary regulatory permits.
11
THETA GOLD MINES LIMITED | ANNUAL REPORT 2023
SOLID GROWTH POTENTIAL
Modern mining and
treatment methodologies
enable low-cost operations
(AISC <US$900/oz) and
reserve expansion
Develop multiple mines,
reaching >160koz/a
within five years, from the
resource base of +6Moz
First four-mine operation,
central plant and tailings
facility – up to 100koz/a
Various expansion opportunities
to increase production and the
resource base for >3 decades
Capacity to expand to
>160koz/a - 6 mine
operation @ 80kt/m
6 UG MINES TARGETED FIRST OUT OF POTENTIAL >40
Figure 7: Location of first 6 gold mine sites included in Feasibility Study
12
Table 2: Key Project Metrics
Description
Units
Base Case
Reserve Plan
Project Start Date¹
Year
2024
2024
Commercial Production Start Date
Year
2025
2025
Production build up period
Months
14
14
Life of mine
years
12.9
7.3
Underground ore mined (LOM)
Mt
6.46
2.85
Mined Grade
g/t
5.95
6.09
Gold Mined (LOM)
Moz
1.24
0.56
Production Rate
Kt/a
540
540
Production Rate
Kt/m
45
45
Grind size
µ
106
106
Gold recovered (average LOM)
%
87
87
Gold recovered (LOM)
Moz
1.08
0.49
Project economics below shows the sensitivities to the various gold price estimates and demonstrates the robust
financial returns of the Project. The FS completed in July 2022 used an average gold price of USD 1,642 / Oz as a
base case.
1. Start-up of project and commercial production is subject to receiving all necessary funding and permit approvals.
Table 3: Project Economics at Various Gold Prices – Base Case (AUD)
Project Economics at gold price
Unit
Forecast
USD1,500/oz USD1,600/oz
(USD1,642/ oz Avg)
USD1,800/oz USD2,000/oz USD2,200/oz
NPV @ 10% (real) Pre-tax
AUDm
432
339
405
536
669
802
NPV @ 10% (real) Post-tax
AUDm
292
232
274
359
447
533
IRR (%) Pre-tax
%
65%
57%
64%
77%
90%
102%
IRR (%) Post-tax
%
57%
50%
56%
67%
78%
87%
AISC
AUD/oz
1,112
1,096
1,107
1,129
1,149
1,167
EBITDA annual average
AUDm
92
77
87
107
128
148
EBIT annual average
AUDm
80
66
76
96
116
136
Free Cash Flow (Pre-tax)
AUDm
956
768
897
1,158
1,421
1,686
Free Cash Flow (Post-tax)
AUDm
678
550
638
814
996
1,175
Development Capital – Peak Funding
AUDm
102
102
102
102
102
102
Capital Sustaining
AUDm
49
49
49
49
49
49
Payback post-tax
Months
31
33
31
28
25
24
Capital Efficiency (Pre-Tax NPV/Dev Capital
%
422%
332%
395%
524%
653%
783%
Capital Efficiency (Post-Tax NPV/Dev Capital
%
285%
226%
268%
351%
437%
521%
NOTES:
1. Converted to AUD from USD using AUD:USD exchange rate of 1.333.
2. Due to rounding, numbers presented throughout this document may not add up precisely to the totals, provided and percentages may not precisely reflect the absolute figures.
13
THETA GOLD MINES LIMITED | ANNUAL REPORT 2023
Figure 8: Annual Gold Production – Base Case
Figure 9: Annual and Cumulative Cash Flow (Post-Tax) – Base Case (AUD)
NOTES:
1. Forecast Prices averaging USD1,642/oz over LOM.
2. Converted to AUD from USD at exchange rate of 1.333 AUD:USD.
The TGME Project targets to restart historical underground gold mines located in a historically prolific gold mining
region in the Mpumalanga Province of South Africa. The Project Areas are centred in the town of Pilgrims Rest,
some 370 km due northeast of Johannesburg, and vast majority of the tenements were under TGME’s ownership
since the late 1800s.
The Project targets the Beta (including the Beta North, Beta Central and Beta South sections), Rietfontein,
Frankfort and Clewer-Dukes Hill-Morgenzon (“CDM”) mines. A significant amount of gold resources remain
underground which were not mined historically due to technological limitations or limiting ore characteristics.
Beta is scheduled as the first operation to commence production, followed by Rietfontein, and finally CDM and
Frankfort simultaneously. In comparison to CDM and Frankfort, Beta and Rietfontein are higher-grade mines.
A gold plant, which acts as the central processing plant for all the historical operations, is situated in close
proximity with a maximum distance to operations of approximately 40km. A new facility will be established on this
footprint to treat all the ore from the surrounding operations.
14
Two scheduling strategies have been investigated in the FS. The Base Case considers a LOM plan targeting
the total Mineral Resources (Measured, Indicated and Inferred). The Ore Reserve Case considers a LOM plan
targeting only Measured and Indicated Mineral Resources.
This FS demonstrates the ability to achieve optimised cash flows by scheduling production from the operations.
The mine designs and associated costs per operational element feed into a combined operations financial model.
The Ore Reserve Case supports the declaration of compliant JORC Code 2012 Ore Reserves.
TGME UNDERGROUND GOLD MINE DEVELOPMENT
As part of the preparation for the installation of the first phase new gold plant, TGME had appointed the services
of Jet Demolition to remove the redundant plant equipment. The process started in the second week of January
2022. Specialised equipment was utilised for demolition, after which it was reduced in size and made ready for
transport to scrap merchants. The project to remove the old plant is now complete17.
Processing consultants Met63 was contracted to do a detailed d