Frankfort mine –The manufacturing of both the Crushing Circuit and the Dense Medium Separation (DMS) units has commenced and is expected to be complete by August 2023. This DMS unit will process 25 tons/hr of ore from the Frankfort mine.
Following the commissioning of this DMS unit, a second 25 tons/hr unit will be procured within the next 6 months to process additional ore at the Frankfort mine.